HomeMy WebLinkAbout2017 CON Portillo Concrete - Sewer Line Replacement Upsizing CIP 16-05 - Change Order #2 and #3CAI FOliN1A
L CET"
�NCOA.POiiAT�D
Sewer Line Replacement and Upsizing (Phase 1)
CIP NO. 16-05
Contractor: Portillo Concrete, Inc.
Reason/Purpose for this Change Order:
During construction of the National City Blvd. portion of the work, numerous unknown utilities were found. As a
result, changes were made to the location and installation of the storm drain.
CHANGE ORDER NO. 2
March 22, 2017
The City of National City and Contractor agree to the following change to the original Contract:
The City and the Contractor agree that the Contractor shall proceed with the work described above and
particularly described in PCO 13 and 14, see attachment for cost breakdown.
Original Contract Amount... $ 2,496,925.00
Net change by previously authorized Change Orders 26,206.86
Subtotal ... 2,523,131.86
Amount of this change order 20,548.14
New contract amount... .. $ 2,543,680.00
Working days added: 0 Working days subtracted: 0 Percent change in Contract to date 1.87%
Sub ted
3� 1 7
Pa - • er Date
Approved by:
Cites/ _ ngineer Date City Manager,
required for Change Orders >524.sss Date
By signing this Change Order the Contractor confirms that he/she is completely familiar with its terms and conditions and has fairly negotiated
its price, terms and conditions. If this Change Order is approved, Contractor will provide all of the equipment, materials and labor necessary to
provide a complete work as described above at that the price stated herein. Additionally, Contractor confirms that the price is fair and complete
and represents all costs associated with the work, including but not limited to all equipment, materials, labor, supervision, overhead, fees,
bonds, insurance, profit, etc. and that there will be no further compensation. All of the terms and conditions of the original contract documents
are incorporated herein.
Accqpt and agreed to byilo Concrete, Inc.:
U'a /7
Name: .ChA, e _/ / 0 Date
Note to Contractor: If you do not agree with this Change Order you may be directed to proceed with this work under the terms of the contract
and you may proceed under protest. You must comply with the contract requirements of submitting a written protest to protect your claim.
Originals: City Clerk, Contractor cc: Engineering project file, Project Manager
1243 National City Boulevard, National City, CA 91950
Telephone (619) 336-4380
,/
CALIFORNIA - y
r TI O J � L
nau
`--" 4NC.OR oR ATE
Sewer Line Replacement and Upsizing Project (Phase I)
CIP NO. 16-05
DATE: March 22, 2017
CHANGE ORDER NO. 2
WORK PERFORMED BY: Portillo Concrete, Inc.
DESCRIPTION OF WORK: Stormdrain work around unknown utilities
ACCOUNTING FOR TIME, MATERIALS, AND EQUIPMENT
1)
2)
Stormdrain - unknown utilities
16 feet of storm drain install
T&M 13
T&M 14
8,772.91
11,775.23
TOTAL:
$ 20, 548.14
CALIFORNIA
NATIONIALC'flh'V
e e
INCORPORATED
Sewer Line Replacement and Upsizing Project (Phase I) CHANGE ORDER NO. 2
CIP NO. 16-05
DATE: March 22, 2017
WORK PERFORMED BY: Portillo Concrete, Inc.
DESCRIPTION OF WORK: Stormdrain work around unknown utilities
ACCOUNTING FOR TIME, MATERIALS, AND EQUIPMENT
1)
2)
Stormdrain - unknown utilities
T&M 13
8,772.91
16 feet of storm drain install
T&M 14
11,775.23
TOTAL:
$ 20,548.14
# Equipment
PORTILLO CONCRETE, INC.
3527CITRUS ST
LEMON GROVE, CA. 91945
OFFICE (619) 466-4639
FAX (619) 466-4685
Hours
Rate Extension
2 Crew truck
1 T.C. Truck
Ten Wheeler
Bobtail
2.5 Ton Lumber Trk
8
3
1 Saw Truck 2
Bobcat & Attachments
1 Kawasaki 65Z Loader 8
Roller 5-7 ton
Light Plants
1 Equipment Move 1
1 Excavator 135 8
1 Excavator 75 8
$27.33
$27.33
$45.00
$40.00
$25.00
$50.00
$50.00
$84.06
$50.00
$22.00
$400.00
$85.00
$50.00
$437.28
$81.99
$0.00
$0.00
$0.00
$100.00
$0.00
$672.48
$0.00
$0.00
$400.00
$680.00
$400.00
Date
Job Name
Job #
T/M #
By
2/14/2017
SEWER LINE REPLACEMENT AND
UPSIZING PROJECT (PHASE 1)
16-16
13
Mario Portillo
SCOPE OF WORK:
During the installation of the 24" strom drain, the 12" high
pressure water main was mislocated by 10.5'. We needed
to shut down operations and wait for a water main shut down
and decision on amonut of pipe to replace.
Materials
Qty. Unit Price Extension
Asphalt - Vulcan
Traffic Control Devices
Rock -Vulcan
Pipe - Furgeson
Misc. shoring
Coupling
TNS
EA
TN
LF
LS
EA
1
$0.00
$0.00
$0.00
$0.00
$500.00 $500.00
$0.00
Subcontractors
Rats Trucking (1 Equip move)
PRSI / Lindys
Pacific Oil Spreading
Urbinas Sweeping
Statewide Stripes
HR
SF
SF
HR
EA
Labor
Hours
10 $105.00
$1,050.00
$0.00
$0.00
$0.00
$0.00
Rate Extension Total Prime Labor Cost
1
1
Superintendent 8 $80.00
Foreman - Reg 6 $88.50
Cement Mason - Reg
Cement Mason - OT
$640.00 Labor Mark-up
$531.00 Total Prime Equip. Cost
$45.55 $0.00 Equipt Mark-up
$58.20 $0.00 Total Prime Mat. Cost
1 Laborer - Saw Cutter 2 $63.50
2 Laborer - Reg 7 $63.50
Laborer - Reg - APP
Operator - Roller
Operator - Bobcat
$127.00 Material Mark-up
$889.00 Total Sub -Contractor Cost
$36.25 $0.00 Sub Contractors Mark-up
$88.50 $0.00 Sub Total
$88.50 $0.00 Office Overhead
1 Operator - Excav 8 $88.50
Operator - Loader
$708.00 Total
$88.50 $0.00 Bond
20%
15%
15%
5%
$2,895.00
$579.00
$2,771.75
$415.76
$500.00
$75.00
$1,050.00
$105.00
$8,391.51
$251.75
$8,643.26
$129.65
PROJECT / ITEM TOTAL
$8,772.91
PORTILLO CONCRETE, INC.
3527CITRUS ST
LEMON GROVE, CA. 91945
OFFICE (619) 466-4639
FAX (619) 466-4685
# Equipment Hours
Rate Extension
2 Crew truck
1 T.C. Truck
Ten Wheeler
Bobtail
2.5 Ton Lumber Trk
Saw Truck
8 $27.33 $437.28
3 $27.33 $81.99
$45.00 $0.00
$40.00 $0.00
$25.00 $0.00
$50.00 $0.00
Bobcat & Attachments $50.00
1 Kawasaki 65Z Loader 8 $84.06
Roller 5-7 ton $50.00
2 Light Plants 8 $22.00
Equipment Move $400.00
1 Excavator 135 8 $85.00
1 Excavator 75 8 $50.00
$0.00
$672.48
$0.00
$352.00
$0.00
$680.00
$400.00
Date
Job Name
2/16/2017
SEWER LINE REPLACEMENT AND
UPSIZING PROJECT (PHASE 1)
Job # 16-16
T/M # 14
By Mario Portillo
SCOPE OF WORK:
Installed 16 LF of 24" Storm Drain @ Mile of Cars Way &
National City Blvd. Had Watermain shutdown and left down
to pour concrete collars. Filled a large area with 1" rock that
was voided from the previous mis-aligned pipe. Soil was
soft and fluffy in this area.
Materials
Qty. Unit Price Extension
Concrete - Robertsons (short Load)
Robertsons Plant Opening
Rock -Vulcan
24" Pipe - Furgeson
Misc. shoring
Coupling
CY
EA
TN
LF
LS
EA
3 $150.00 $450.00
1 $750.00 $750.00
10 $22.00 $220.00
16 $38.00 $608.00
1 $500.00 $500.00
$0.00
Subcontractors
Rats Trucking (1 Equip move)
PRSI / Lindys
Pacific Oil Spreading
Urbinas Sweeping
Statewide Stripes
HR
SF
SF
HR
EA
Labor
Hours
Rate
8 $105.00
$840.00
$0.00
$0.00
$0.00
$0.00
Extension Total Prime Labor Cost
1 Superintendent 8 $80.00
1 Foreman - Reg 7 $88.50.
Cement Mason - Reg $45.55
Cement Mason - OT $58.20
1 Laborer - Saw Cutter 2 $63.50
2 Laborer - Reg 7.25 $63.50
Laborer - Reg - APP $36.25
Operator - Roller $88.50
Operator - Bobcat $88.50
2 Operator - Excav 7.75 $88.50
Operator - Loader $88.50
$640.00 Labor Mark-up
$619.50 Total Prime Equip. Cost
$0.00 Equipt Mark-up
$0.00 Total Prime Mat. Cost
$127.00 Material Mark-up
$920.75 Total Sub -Contractor Cost
$0.00 Sub Contractors Mark-up
$0.00 Sub Total
$0.00 Office Overhead
$1,371.75 Total
$0.00 Bond
20%
15%
15%
$3,679.00
$735.80
$2,623.75
$393.56
$2,528.00
$379.20
$840.00
$84.00
$11,263.31
$337.90
$11,601.21
$174.02
PROJECT / ITEM TOTAL
$11,775.23
+a.4 CALIFORNIA
taxi'ANAL Cillt
ligtv
INCORPORATED
Sewer Line Replacement and Upsizing (Phase I)
CIP NO. 16-05
Contractor: Portillo Concrete, Inc.
CHANGE ORDER NO. 3
March 22, 2017
Reason/Purpose for this Change Order:
During construction of the National City Blvd. portion of the work, numerous unknown utilities were found. As a
result, changes were made to the location and installation of the storm drain and a sewer lateral,
The City of National City and Contractor agree to the following change to the original Contract:
The City and the Contractor agree that the Contractor shall proceed with the work described above and
particularly described in PCO 15, 16, and 17, see attachment for cost breakdown.
Original Contract Amount
Net change by previously authorized Change Orders
Subtotal
Amount of this change order
New contract amount $ 2,561,472.81
Working days added: 0 Working days subtracted: 0 Percent change in Contract to date 2.59%
2,496,925.00
46,755.00
2,543,680.00
17,792.81
. mi e• .
P IP
Project Manager
Approved by:
City 'ngineer
3)21)
Date
9/rf
Date City Manager, required for Change Orders 424.999 Date
By signing this Change Order the Contractor confirms that he/she is completely familiar with its terms and conditions and has fairly negotiated
its price, terms and conditions. If this Change Order is approved, Contractor will provide all of the equipment, materials and labor necessary to
provide a complete work as described above at that the price stated herein. Additionally, Contractor confirms that the price is fair and complete
and represents all costs associated with the work, including but not limited to all equipment, materials, labor, supervision, overhead, fees,
bonds, insurance, profit, etc. and that there will be no further compensation. All of the terms and conditions of the original contract documents
are incorporated herein.
Accepted and agree
Name:
Date
Note to Contractor: If you do not agree wbe directed to proceed with this work under the terms of the contract
and you may proceed under protest. You must comply with the contract requirements of submitting a written protest to protect your claim.
Originals: City Clerk, Contractor cc: Engineering project file, Project Manager
Telephone (619) 336-4380
with thisan a Order you may
• o b.�%illo Concrete, Inc.:
ai/p40
1-
Y
1243 National City Boulevard, National City, CA 91950
t 1 r
CALIFORNIA
ilaat
micoapoR AT V)
Sewer Line Replacement and Upsizing Project (Phase I)
CIP NO. 16-05
DATE: March 22, 2017
CHANGE ORDER NO. 3
WORK PERFORMED BY: Portillo Concrete, Inc.
DESCRIPTION OF WORK: Lateral and Stormdrain work around unknown utilities
ACCOUNTING FOR TIME, MATERIALS, AND EQUIPMENT
1)
Storm drain install
T&M 15
$ 2,757.89
2)
Unknown utilities around
stormdrain
T&M 16
6,869.80
3)
8" sewer lateral, unknown
utilities
T&M 17
8,165.12
TOTAL:
$ 17,792.81
�i 4E 1
CALIFORNIA
ctry,
e e
CINCORPORATED
Sewer Line Replacement and Upsizing Project (Phase I) CHANGE ORDER NO. 3
CIP NO. 16-05
DATE: March 22, 2017
WORK PERFORMED BY: Portillo Concrete, Inc.
DESCRIPTION OF WORK: Lateral and Stormdrain work around unknown utilities
ACCOUNTING FOR TIME, MATERIALS, AND EQUIPMENT
1)
Storm drain install
T&M 15
$ 2,757.89
2)
Unknown utilities around
stormdrain
T&M 16
6,869.80
3)
8" sewer lateral, unknown
utilities
T&M 17
8,165.12
TOTAL:
$ 17,792.81
PORTILLO CONCRETE, INC.
3527CITRUS ST
LEMON GROVE, CA. 91945
OFFICE (619) 466-4639
FAX (619) 466-4685
# Equipment Hours Rate Extension
1 Crew truck
T.C. Truck
Ten Wheeler
Bobtail
2.5 Ton Lumber Trk
4 $27.33 $109.32
$27.33 $0.00
$45.00 $0.00
$40.00 $0.00
$25.00 $0.00
Saw Truck $50.00 $0.00
Bobcat & Attachments $50.00 $0.00
1 Kawasaki 65Z Loader 4 $84.06 $336.24
Roller 5-7 ton $50.00 $0.00
Light Plants $22.00 $0.00
Equipment Move $400.00 $0.00
1 Excavator 135 4 $85.00 $340.00
Excavator 75 $50.00 $0.00
Date 2/17/2017
Job Name SEWER LINE REPLACEMENT AND
UPSIZING PROJECT (PHASE 1)
Job # 16-16
T/M # 15
By Mario Portillo
SCOPE OF WORK:
Installed 16 LF of 24" Storm Drain @ Mile of Cars Way &
National City Blvd. Had Watermain shutdown and left down
to pour concrete collars. Filled a large area with 1" rock that
was voided from the previous mis-aligned pipe. Soil was
soft and fluffy in this area.
Materials
Qty. Unit Price Extension
Concrete - Robertsons (short Load) CY $0.00
Robertsons Plant Opening EA $0.00
Rock -Vulcan TN $0.00
24" Pipe - Furgeson LF $0.00
Misc. shoring LS $0.00
Coupling EA $0.00
Subcontractors
Rats Trucking (1 Equip move) HR
PRSI / Lindys SF
Pacific Oil Spreading SF
Urbinas Sweeping HR
Statewide Stripes EA
6
$105.00 $630.00
$0.00
$0.00
$0.00
$0.00
Labor Hours Rate Extension Total Prime Labor Cost $868.00
1 Superintendent 2 $80.00 $160.00 Labor Mark-up 20% $173.60
1 Foreman - Reg 4 $88.50 $354.00 Total Prime Equip. Cost $785.56
Cement Mason - Reg $45.55 $0.00 Equipt Mark-up 15% $117.83
Cement Mason - OT $58.20 $0.00 Total Prime Mat. Cost $0.00
Laborer - Saw Cutter $63.50 $0.00 Material Mark-up 15% $0.00
Laborer - Reg $63.50 $0.00 Total Sub -Contractor Cost $630.00
Laborer - Reg - APP $36.25 $0.00 Sub Contractors Mark-up 5% $63.00
Operator - Roller $88.50 $0.00 Sub Total $2,637.99
Operator - Bobcat $88.50 $0.00 Office Overhead 3% $79.14
1 Operator - Excav 4 $88.50 $354.00 Total $2,717.13
Operator - Loader $88.50 $0.00 Bond 1.5% $40.76
PROJECT / ITEM TOTAL $2,757.89
Equipment
PORTILLO CONCRETE, INC.
3527CITRUS ST
LEMON GROVE, CA. 91945
OFFICE (619) 466-4639
FAX (619) 466-4685
Hours
Rate Extension
2 Crew truck
1 T.C. Truck
Ten Wheeler
Bobtail
2.5 Ton Lumber Trk
Saw Truck
6 $27.33 $327.96
6 $27.33 $163.98
$45.00 $0.00
$40.00 $0.00
$25.00 $0.00
$50.00 $0.00
Bobcat & Attachments 4 $50.00
Kawasaki 65Z Loader 6 $84.06
Roller 5-7 ton $50.00
2 Light Plants 6 $22.00
Equipment Move $400.00
1 Excavator 135 6 $85.00
Excavator 75 $50.00
$200.00
$504.36
$0.00
$264.00
$0.00
$510.00
Date
Job Name
12/27/2016
SEWER LINE REPLACEMENT AND
UPSIZING PROJECT (PHASE 1)
Job # 16-16
T/M # 16
By Mario Portillo
SCOPE OF WORK:
Scheduled to install 24" Storm Drain, set up and ground the
road to surface install trench plates when complete. Began
excavation for work and discovered 2 unmarked utility lines
directly in our path of excavation and pipe installation. We
lost the entire shift. The shift was cut short.
$0.00
Materials
Qty. Unit Price Extension
Concrete - Robertsons (short Load)
Robertsons Plant Opening
Rock -Vulcan
24" Pipe - Furgeson
Misc. shoring
Coupling
CY
EA
TN
LF
LS
EA
$0.00
$0.00
$0.00
$0.00
$0.00
$0.00
Subcontractors
Rats Trucking (1 Equip move)
PRSI / Lindys
Pacific Oil Spreading
Urbinas Sweeping
Statewide Stripes
HR
SF
SF
HR
EA
Labor
Hours
Rate
6 $105.00
$630.00
$0.00
$0.00
$0.00
$0.00
Extension Total Prime Labor Cost
1 Superintendent 7 $80.00
1 Foreman - Reg 6 $88.50
Cement Mason - Reg $45.55
Cement Mason - OT $58.20
1 Laborer - Pipelayer 6 $63.50
1 Laborer - Reg 7.5 $63.50
Laborer - Reg - APP $36.25
Operator - Roller $88.50
1 Operator - Bobcat 6 $88.50
1 Operator - Excav 6 $88.50
Operator - Loader $88.50
$560.00 Labor Mark-up
$531.00 Total Prime Equip. Cost
$0.00 Equipt Mark-up
$0.00 Total Prime Mat. Cost
$381.00 Material Mark-up
$476.25 Total Sub -Contractor Cost
$0.00 Sub Contractors Mark-up
$0.00 Sub Total
$531.00 Office Overhead
$531.00 Total
$0.00 Bond
20%
15%
15%
5%
3%
1.5%
$3,010.25
$602.05
$1,970.30
$295.55
$0.00
$0.00
$630.00
$63.00
$6,571.15
$197.13
$6,768.28
$101.52
PROJECT / ITEM TOTAL
$6,869.80
PORTILLO CONCRETE, INC.
3527CITRUS ST
LEMON GROVE, CA. 91945
OFFICE (619) 466-4639
FAX (619) 466-4685
Equipment Hours
Rate
Extension
2 Crew truck 7.5
1 T.C. Truck 8.5
Ten Wheeler
1 Bobtail
2.5 Ton Lumber Trk
Saw Truck
1 Bobcat & Attachments
1 Kawasaki 65Z Loader
Roller 5-7 ton
2 Light Plants
Equipment Move
1 Excavator 135
1 Excavator 75
$27.33
$27.33
$45.00
8 $40.00
$25.00
$50.00
4 $50.00
8 $84.06
$50.00
8 $22.00
$400.00
8 $85.00
8 $50.00
$409.95
$232.31
$0.00
$320.00
$0.00
$0.00
$200.00
$672.48
$0.00
$352.00
$0.00
$680.00
$400.00
Date
Job Name
12/20/2016
SEWER LINE REPLACEMENT AND
UPSIZING PROJECT (PHASE 1)
Job # 16-16
T/M # 17
By Mario Portillo
SCOPE OF WORK:
Installed the 8" lateral @ Sta 77+34 on T/M due to
multiple unmarked utilities. This lateral is also mis-marked on
the plans and mis-surveyed as well
Materials
Qty. Unit Price
Extension
Concrete - Robertsons (short Load)
Robertsons Plant Opening
Rock -Vulcan
24" Pipe - Furgeson
Misc. shoring
Coupling
CY
EA
TN
LF
LS
EA
5
1
$23.00
$75.00
$0.00
$0.00
$115.00
$0.00
$75.00
$0.00
Subcontractors
Rats Trucking (1 Equip move)
PRSI / Lindys
Pacific Oil Spreading
Urbinas Sweeping
Statewide Stripes
HR
SF
SF
HR
EA
Labor
Hours
$0.00
$0.00
$0.00
$0.00
$0.00
Rate Extension Total Prime Labor Cost
1 Superintendent
1 Foreman - Reg
Cement Mason - Reg
Cement Mason - OT
1 Laborer - Pipelayer 7 $63.50
1 Laborer - Reg 6.5
Laborer - Reg - APP
Operator - Roller
1 Operator - Bobcat 7 $88.50
1 Operator - Excav 7 $88.50
Operator - Loader
6 $80.00
7 $88.50
$480.00 Labor Mark-up
$619.50 Total Prime Equip. Cost
$45.55 $0.00 Equipt Mark-up
$58.20 $0.00 Total Prime Mat. Cost
$444.50 Material Mark-up
$63.50 $412.75 Total Sub -Contractor Cost
$36.25 $0.00 Sub Contractors Mark-up
$88.50 $0.00 Sub Total
$619.50 Office Overhead
$619.50 Total
$88.50 $0.00 Bond
20%
15%
15%
$3,195.75
$639.15
$3,266.74
$490.01
$190.00
$28.50
$0.00
$0.00
$7,810.15
$234.30
$8,044.45
$120.67
PROJECT / ITEM TOTAL
$8,165.12
CITY OF NATIONAL CITY
Office of the City Clerk
1243 National City Blvd., National City, California 91950-4397
619-336-4228
Michael R. Dalla, CMC - City Clerk
PORTILLO CONCRETE
Change Order # 2 and #3
Sewer Line Replacement and Upsizing (Phase I)
Judy Hernandez (Engineering/Public Works) Forwarded
Copy of Change Orders to Portillo Concrete