HomeMy WebLinkAboutA Good Sign and Graphics Co - Wayfinding Signage Project CIP No. 16-03 - Change Order Nos. 7-8 2017CHANGE ORDER NO. 7
October 2, 2017
WAYFINDING SIGNAGE PROJECT
CIP NO. 16-03
A Good Sign, Inc.
Reason/Purpose for this Change Order:
After inspecting the aluminum poles that will be used for the proposed signs to be installed in the marina district,
the architect determined that the poles were oversized and needed to be modified. The architect requested that ,
smaller galvanized steel poles would be utilized to match the size of the wayfinding signs installed in the area.
The City of National City and Contractor agree to the following change to the original Contract
The City and the Contractor agree that the Contractor shall replace the 6" diam. aluminum poles for the three (3)
signs in the Marina district area. The contractor shall instead provide and install 4" diam. galvanized steel poles
as a substitute per the architect's direction. This replacement shall include the engineering calculations
approved and certified by engineer before installation. The agreed upon price for all cost associated is
$1,768.80.
Original Contract Amount ...
Net change by previously authorized Change Orders
Subtotal
Amount of this change order
New contract amount
Working days added: 0 Working days subtracted: 0 Percent change in Contract to date 12.67%
Subm - d b :
Pro'ect Ma...... r D
270,359.00
32,496.21
302,855.21
1,768.80
to
0/a 2.O 7
I
304,624.01
Approved by:
r... ✓. _...yam...,....
Ci ngineer
(..0/(Y7
Date
City Mana^" er required for Change Orders >$24,999 Date
By signing this Change Order the Contractor confirms that he/she is completely familiar with its terms and conditions and has fairly negotiated
its price, terms and conditions. If this Change Order is approved, Contractor will provide all of the equipment, materials and labor necessary to
provide a complete work as described above at that the price stated herein. Additionally, Contractor confirms that the price is fair and complete
and represents all costs associated with the work, including but not limited to all equipment, materials, labor, supervision, overhead, fees,
bonds, insurance, profit, etc. and that there will be no further compensation. All of the terms and conditions of the original contract documents
are incorporated herein.
Accepted and afire - •, o by A Good Sign, Inc.:
Name:
ate
Note to Contractor: If you do not agree with this Change Order you may be directed to proceed with this work under the terms of the contract
and you may proceed under protest. You must comply with the contract requirements of submitting a written protest to protect your claim.
Originals: City Clerk, Contractor cc: Engineering project file, Project Manager
1243 National City Boulevard, National City, CA 91950
Telephone (619) 336-4380
'>-
CALIFORNIA .,
�� i'ION1 �_�L CIT'VN1A'
-
INCORPORATED
WAYFINDING SIGNAGE PROJECT
CIP NO. 16-03
DATE: October 2, 2017
CHANGE ORDER NO. 7
WORK PERFORMED BY: A Good Sign, Inc.
DESCRIPTION OF WORK: Replacement of the Aluminum to Galvanized Steel Poles
Three (3) 4" diam. Galvanized
steel poles
EA 3.00 499.66 1,498.98
Sub -Total Labor:
Material Markup (15%):
$ 1,498.98
$ 224.85
TOTAL MATERIALS:
Bonding (3%)
44.97
GRAND TOTAL:
1.,768.80
A GOOD SIGN & GRAPHICS CO
COR #e'S
Job Name: National City Wayfinding
Job Number. 1221
Date: September 27, 2017
ASI #:
Time Impact
Full Description of Change in Scope:
single pole banner hardware
Breakdown
Direct Labor
Sign Type
Sign Detail
Quantity Rate
Cost
single pole banner hardware
36.00
$93.00
$3,348.00
single pole banner hardware
(Discount)
36.00
-$16.75
-$603.00
$0.00
$0.00
SUBTOTALS
72.0
$2,745.00
Breakdown
Direct Materials
Sign Type Sign Detail
Quantity
Rate
Cost
$0.00
$0.00
$0.00
$0.00
SUBTOTALS
( 0.0
I $0.00
Breakdown
Direct Equipment
Sign Type
Sign Detail
Qty
Rate
Cost
$0.00
SUBTOTALS
0.0
$0.00
Breakdown
Other
Sign Type Sign Detail Quantity
Rate
Cost
SUBTOTALS
*Combined Subtotal:
15% Markup:
Combined Subtotal + Markup:
(Including GC & First Tier Sub cost) Bond 3% (of *Subtotal):
$0.00 I
$2,745.00
$411.75
$3,156.75
$82.35
GRAND TOTAL
$3,239.10
Project Manager for Conti or
DATE:
SUB. CON - NAME/TITLE
DATE
WAYFINDING SIGNAGE PROJECT
CIP NO. 16-03
A Good Sign, Inc.
Reason/Purpose for this Change Order:
+ ,,CAUFORNiA`-
talfirONAktirry
160V
zNC08PORATED
CHANGE ORDER NO. 8
October 2, 2017
This Change Order replaces the banners that uses double brackets with a single bracket install method. During
the placement of the double banners in NC Old Town district, it was observed that the large light posts blocked
portions of the banner due the installation. After looking at a sample installation on -site, the designer decided
that it would be best to have the banners installed using a single bracket method instead of the double bracket
method to avoid blocking any part of the signage.
The City of National City and Contractor agree to the following change to the original Contract:
The City and the Contractor agree that the Contractor shall replace the double bracket installation for banners to
single bracket installation. The contractor shall install all hardware and appurtenances associated with this
change order. The agreed upon price for all cost associated is$l- 00 6 -
.t3, Z 31 • / o
Original Contract Amount
Net change by previously authorized Change Orders...
Subtotal
Amount of this change order
270, 359.00
34,265.01
304, 624.01
3,239.10
New contract amount......... $
Workin • days added: 0 Working days subtracted: 0 Percent change in Contract to date 13.87%
Pro
Approved by:
D
307,863.11
Date . City Manager, required for Change Orders >$24,999 Date
By signing this Change Order the Contractor confirms that he/she is completely familiar with its terms and conditions and has fairly negotiated
its price, terms and conditions. If this Change Order is approved, Contractor will provide all of the equipment, materials and labor necessary to
provide a complete work as described above at that the price stated herein. Additionally, Contractor confirms that the price is fair and complete
and represents all costs associated with the work, including but not limited to all equipment, materials, labor, supervision, overhead, fees,
bonds, insurance, profit, etc. and that there will be no further compensation. All of the terms and conditions of the original contract documents
are incorporated herein.
ted and a ►reed to r A Good Sign, Inc.:
Name: Date :
Note to Contractor: If you do not agree with this Change Order you may be directed to proceed with this work under the terms of the contract
and you may proceed under protest. You must comply with the contract requirements of submitting a written protest to protect your claim.
Originals: City Clerk, Contractor cc: Engineering project file, Project Manager
1243 National City Boulevard, National City, CA 91950 Telephone (619) 336-4380
CALIFORNIA
N!L1(T'V
INCORPORATED
WAYFINDING SIGNAGE PROJECT CHANGE ORDER NO. 8
CIP NO. 16-03
DATE: October 2, 2017
WORK PERFORMED BY: A Good Sign, Inc.
DESCRIPTION OF WORK: Modification of double bracket method to single bracket method
ACCOUNTING FOR TIME, MATERIALS, AND EQUIPMENT
Single pole banner harware
Discount for additional hardware
cost
Unit
EA
EA
Qty
36.00
36.00
Rate
93.00
(16.75)
Total
3,348.00
(603.00)
Sub -Total Labor:
$ 2,745.00
Material Markup (15%): 411.75
TOTAL MATERIALS:
Bonding (3%)
GRAND TOTAL:
82.35
$ 3, 239,1 O
PROJECT PROFESSIONALS CORPORATION
TRANSMITTAL COVER
To: National City Engineering Department
Project Name: Wayfinding Signage project, CIP No. 16-03
ITEMS DELIVERED:
Change Order No. 7 and 8
Delivered by: Vim
Project Professionals Corporation
Received by:
Date:
CITY OF NATIONAL CITY
Office of the City Clerk
1243 National City Blvd., National City, California 91950-4397
619-336-4228
Michael R. Dalla, CMC - City Clerk
A GOOD SIGN, INC.
Change Orders #7 and #8
Wayfinding Signage Project
CIP No. 16-03
Judy Hernandez (Engineering/Public Works) Forwarded
Copy of Change Orders to A Good Sign, Inc.