HomeMy WebLinkAbout2017 CON Palm Engineering - Westside Mobility Improvements CIP No. 17-04 - Change Orders #5 through #9WESTSIDE MOBILITY IMPROVEMENTS
CIP NO. 17-04
Contractor: Palm Engineering Construction Company, Inc.
CHANGE ORDER NO. 5
November 16, 2017
Reason/Purpose for this Change Order.
The trench drains at the 14th Street and Harding Avenue Roundabout had to be modified In the field after
delivery to meet the flow lines specified In the plans. Under direction of the Engineer the Contractor proceeded
under time and materials to adjust the trench drains.
The City of National City and Contractor agree to the following change to the original Contract:
The City and the Contractor agree that the Contractor shall proceed with adjusting the trench drains in the field to
meet the flow lines specified in the plans. The agreed upon price for all costs associated with this work is as
stated on this Change Order. See Attachments for cost breakdown.
Original Contract Amount........
Net change by previously authorized Change Orders
Subtotal.
Amount of this change order
New contract amount
Working days added: 0 • Working days subtracted: 0
Submitted by:
Approved by:
lI
Date
1,780,325.57
19,026.92
1,799,352.49
1,349.46
$ 1,800,701.9
Percent change in Contract to date 1.14%
/./42/1.7
Cit ngineer "...... . . Date CityManager, required for Change Orders>$24,999 Date
By signing this Change Order the Contractor confirms that he/she is completely familiar with its terms and conditions and has fairly negotiated
its price, terms and conditions. If this Change Order is approved, Contractor will provide all of the equipment, materials and labor necessary to
provide a complete work as described above at that the price stated herein. Additionally, Contractor confirms that the price is fair and complete
and represents all costs associated with the work, including but not limited to all equipment, materials, labor, supervision, overhead, fees,
bonds, insurance, profit, etc. and that there will be no further compensation. All of the terms and conditions of the original contract documents
are incorporated herein.
Accep =• and agreed to by Palm Engineering Construction Company, Inc.
NaLAC/7-7
e: Date
Note to Contractor: If you do not agree with this Change Order you may be directed to proceed with this work under the terms of the contract
and you may proceed under protest. You must comply with the contract requirements of submitting a written protest to protect your claim.
Originals: City Clerk, Contractor cc: Engineering project file, Project Manager
1243 National City Boulevard, National City, CA 91/S6 Telephone (619) 336-4380
11/28/r7
INCORPORATED
WESTSIDE MOBILITY IMPROVEMENTS CHANGE ORDER NO. 5
CIP NO. 17-04
DATE: October 12, 2017
WORK PERFORMED BY: Palm Engineering
DESCRIPTION OF WORK: 14th and Harding adjust trench drain flow lines
ACCOUNTING FOR TIME, MATERIALS, AND EQUIPMENT
Unit
I. Avila - Cement Mason Hour
F. Hernandez - Cement Mason Hour
J. Resendez - Laborer G1 Hour
E. Carrilo - Laborer G1 Hour
Qty
8.00
2.00
2.00
4.00
Wage
53.65
53.65
52.53
52.53
Sub -Total Labor:
Labor surcharge (29.45%):
Total
429.20
107.30
105.06
210.12
$ 851.68
$ 250.82
Labor Markup (20%): $ 220.50
TOTAL LABOR:
-111
Unit
1)
Qty
Rate 1 Total 1
Sub -Total Materials: $ -
Materials Markup (15%): $ -
TOTAL MATERIALS:
EQUIPMENT
Unit
Qty
Rate
Total
Sub -Total Equipment:
Equipment Markup (15%):
$
TOTAL EQUIPMENT:
SUB TOTAL:
1 323.00
BOND AND INSURANCE (2%): 26.46
GRAND TOTAL:
CALIFORNIA
NATIONAL
C_ INCORPORATES
WESTSIDE MOBILITY IMPROVEMENTS
CIP NO. 17-04
Contractor: Palm Engineering Construction Company, Inc.
CHANGE ORDER NO. 6
November 16, 2017
Reason/Purpose for this Change Order:
The frontage of 1539 Roosevelt Ave had to be adjusted due to the elevations of the new improvements to meet
ADA requirements. Under direction of the Engineer the Contractor proceeded under time and materials to
remove and replace concrete steps and landing to meet new improvement elevations.
The City of National City and Contractor agree to the following change to the original Contract:
The City and the Contractor agree that the Contractor shall proceed with adjusting the elevations of the frontage
of 1539 Roosevelt Ave to meet ADA requirements. The agreed upon price for all costs associated with this work
is as stated on this Change Order. See Attachments for cost breakdown.
Original Contract Amount
Net change by previously authorized Change Orders........ ............. ........................ 20,376.38
Subtotal.
Amount of this change order
1,800,701.95
2,840.07
New contract amount $
Percent change in Contract to date 1.30%
days added: 0 Working days subtracted: 0
1,803,542.02 11/291/)
Submitted by:
p4j ect Man
er
11 2i/11
Date
Approved by:
2
City ngineer
. lib . ..74.
Date
City Mana er, required for Change Orders >$24,999
Date
By signing this Change Order the Contractor confirms that he/she is completely familiar with its terms and conditions and has fairly negotiated
its price, terms and conditions. If this Change Order is approved, Contractor will provide all of the equipment, materials and labor necessary to
provide a complete work as described above at that the price stated herein. Additionally, Contractor confirms that the price is fair and complete
and represents ail costs associated with the work, including but not limited to all equipment, materials, labor, supervision, overhead, fees,
bonds, insurance, profit, etc. and that there will be no further compensation. All of the terms and conditions of the original contract documents
are incorporated herein.
Accepted an agreed to by Palm Engineering Construction Company, Inc.
Name:
1,780,325.57
11/2 a /r7
Date
Note to Contractor: If you do not agree with this Change Order you may be directed to proceed with this work under the terms of the contract
and you may proceed under protest. You must comply with the contract requirements of submitting a written protest to protect your claim.
Originals: City Clerk, Contractor cc: Engineering project file, Project Manager
Telephone (619) 336-4380
1243 National City Boulevard, National City, CA 91950
WESTSIDE MOBILITY IMPROVEMENTS CHANGE ORDER NO. 6
CIP NO. 17-04
DATE: October 4, 2017
WORK PERFORMED BY: Palm Engineering
DESCRIPTION OF WORK: Setting and pouring frontage at 1539 Roosevelt Ave
ACCOUNTING FOR TIME, MATERIALS, AND EQUIPMENT
Unit
Qty
Wage
Total
I. Avila - Cement Mason
Hour
8.00
53.65
429.20
2)
3)
S. Avila - Cement Mason
Hour
8.00
53.65
429.20
4)
5)
E. Garcia - Cement Mason
A. Martinez - P3 CM Apprentice
Hour
Hour
2.00
4.00
53.65
42.02
107.30
168.08
F. Hernandez - Laborer G1
Hour
8.00
52.53
420.24
Sub -Total Labor:
Labor surcharge (29.45%):
$ 1,554.02
$ 457.66
Labor Markup (20%) $ 402.34
TOTAL _730FEEIMI
Unit
Qty
1) (Concrete (Superior) 1 CY
Rate Total
128.820 322.05
Sub -Total Materials: $ 322.05
Materials Markup (15%): $ 48.31
TOTAL MATERIALS:
2.50
EQUIPMENT
Unit
Qty
Rate
Total
1)
Sub -Total Equipment:
Equipment Markup (15%):
$
$
TOTAL EQUIPMENT:
SUB TOTAL:
BOND AND INSURANCE (2%):
GRAND TOTAL:
2,784.38
55.69
DATE
SUPERIOR READY MIX
CONCRETE, L.P. INVOICE
1508 W. MISSION RD. * ESCONDIDO, CA 92029
PHONE: (760) 745-0556 * FAX: (760) 740-9557
CUSTOMER NO. DATE INVOICE NO. PAGE I
PALME005 10/04/2017 903211 1
PALM ENGINEERING CONSTRUCTION
7330 OPPORTUNITY RD. STE J
SAN DIEGO, CA 92111
TERMS: NET 30 DAYS
A FINANCE CHARGE WILL BE IMPOSED ON PAST DUE ACCOUNTS. THE
FINANCE CHARGE IS COMPUTED BY A'PERIODIC RATE OF1 1/2% PER
MONTH, WHICH IS AN ANNUAL PERCENTAGE RATE OF 18%OR A MINIMUM
SERVICE CHARGE OF$5.00 WHICHEVER IS GREATER.
JOB NUMBER - JOB LOCATION - ADDRESS UNIT
QUANITY UNIT DESCRIPTION PRICE
000290 (1704) WESTSIDE MOBILITY IMPROVEMENTS
HARDING AVE. & 14TH ST. NATIONAL CITY
PO NUMBER: 1704
TAX TOTAL
10/04/17 9.50 CY 5553 92.850 68.36
520-C-2500 CONCRETE
17.00 EA ST 1.500 0.00
STAND BY TIME - MIXER
1.00 LD EE 30.000 2.33
ENVIRONMENTAL/ENERGY SUR
1.00 LD PWF 200.000 15.50
PUBLIC WORKS FEE
TICKET DATE TOTALS: 1137.58 86.19
JOB TOTALS 1137.58
TICKETS: 004-257545
950.44
25.50
32.33
215.50
1223.77
86.19 1223.77
)7,117s6.vixZ.S=32z°s
9S
WESTSIDE MOBILITY IMPROVEMENTS
CIP NO. 17-04
Contractor: Palm Engineering Construction Company, Inc.
CHANGE ORDER NO. 7
November '16, 2017
Reason/Purpose for this Change Order:
The telespar post called out in the specifications would not be sufficient to support the crosswalk flashing beacon
system and had to he replaced with the type 1•A pole, plate and foundation. Under direction of the Engineer the
Contractor proceeded with furnishing and installing 2 type 1-A poles, plates and foundations.
The City of National City and Contractor agree to the following change to the original Contract:
The City and the Contractor agree that the Contractor shall proceed with furnishing and installing 2 type 1-A
poles, plates and foundations to support the crosswalk flashing beacon system. The agreed upon price for all
costs associated with this work is as stated on this Change Order. See Attachments for cost breakdown.
Original Contract Amount
Net change by previously authorized Change Orders
Subtotal
Amount of this change order
New contract amount.....
Working days added: 0 Working days subtracted: 0
Submitted by:
P %ject Ma ger
1,780,325.57
23,216.45
1,803,542.02
4,039.20
Percent change in Contract to date 1.53%
1,807,581.22
Approved by:
Cite ngineer
By signing this Change Order the Contractor confirms that he/she is completely familiar with its terms and conditions and has fairly negotiated
its price, terms and conditions. If this Change Order is approved, Contractor will provide all of the equipment, materials and labor necessary to
provide a complete work as described above at that the price stated herein. Additionally, Contractor confirms that the price is fair and complete
and represents all costs associated with the work, including but not limited to all equipment, materials, labor, supervision, overhead, fees,
bonds, insurance, profit, etc. and that there will he no further compensation. All of the terms and conditions of the original contract documents
are incorporated herein.
//On?
ate City Manager, required for Change Orders.$24.999 Date
Accepted and a 'r ed to by Palm Engineering Construction Company Inc.
Name:
Note to Contractor: If you do not agree with this Change Order you may be directed to proceed with this work under the terms of the contract
and you may proceed under protest. You must comply with the contract requirements of submitting a written protest to protect your claim.
Originals: City Clerk, Contractor cc: Engineering project file, Project Manager
1243 National City Boulevard, National City, CA 91950 Telephone (619) 336-4380
/1/2 /r)
Date
1
�CALI 4/N *-e
NKf1ONAL Cflr'
/N?cyy
e D J
CORPORATE
WESTSIDE MOBILITY IMPROVEMENTS CHANGE ORDER NO. 7
CIP NO. 17-04
(
DATE: October 24, 2017
WORK PERFORMED BY: Palm Engineering
DESCRIPTION OF WORK: Furnish and install 2 each Type 1B foundations and poles with plates
ACCOUNTING FOR TIME, MATERIALS, AND EQUIPMENT
Unit
Qty
Wage
Total
Sub -Total Labor:
Labor surcharge (29.45%):
Labor Markup (20%): $ -
TOTAL LABOR:
Unit
Qty
Rate
Total
Furnish/Install 2 Type 1A
1)
foundations, poles, and plates
LS
1.00
4,893.900
4,893.90
Credit for 2 Telspar posts with
2)
sleeves in concrete
LS
1.00
(933.900)
(933.90)
Sub -Total Materials:
$ 3,960.00
Materials Markup (15%):
$ -
TOTAL MATERIALS:
EQUIPMENT
Unit
Qty
Rate
Total
1) N/A
Sub -Total Equipment:
Equipment Markup (15%):
TOTAL EQUIPMENT: $
SUB TOTAL: $ 3,960.00
BOND AND INSURANCE (2%): , .79.20
GRAND TOTAL:
WESTSIDE MOBILITY IMPROVEMENTS
CIP NO. 17-04
Contractor: Palm Engineering Construction Company, Inc.
CHANGE ORDER NO.8
November 16, 2017.
Reason/Purpose for this Change Order:
The West Avenue bulbout did not account for the drainage within the bulbout and trench drains had to be added.
Under direction of the Engineer the Contractor proceeded with furnishing and installing trench drains within the
West Avenue bulbout.
The City of National City and Contractor agree to the following change to the original Contract:
The City and the Contractor agree that the Contractor shall proceed with furnishing and installing trench drains
within the West Avenue bulbout. The agreed upon price for all costs associated with this work is $105 a linear
foot. 112 linear feet was installed fora total of $11,760.00.
Original Contract Amount
Net change by previously authorized Change Orders
Subtotal...
Amount of this change order
New contract amount
Working days added: 0
Working days subtracted: 0
1,780, 325.57
27,255.65
1,807,581.22
11,760.00
Percent change In Contract to deb 2.19%
1,819,341.22
Submitted by:
Date City Manager, required for Change Orders >$2+.ass Date
By signing this Change Order the Contractor confirms that he/she is completely familiar with its terms and conditions and has fairly negotiated
its price, terms and conditions. If this Change Order is approved, Contractor will provide all of the equipment, materials and labor necessary to
provide a complete work as described above at that the price stated herein. Additionally, Contractor confirms that the price is fair and complete
and represents all costs associated with the work, including but not limited to all equipment, materials, labor, supervision, overhead, fees,
bonds, insurance, profit, etc. and that there will be no further compensation. All of the terms and conditions of the original contract documents
are incorporated herein.
l
Acce fed ajil�►c agreed to by Palm Engineering Construction Company, Inc
Name:
i/ /c.((
ate
Note to Contractor: If you do not agree with this Change Order you may be directed to proceed with this work under the terms of the contract
and you may proceed under protest. You must comply with the contract requirements of submitting a written protest to protect your claim.
Originals: City Clerk, Contractor cc: Engineering project tile, Project Manager
Telephone (619) 336-4380
1243 National City Boulevard, NationarCity, CA 91950
+** CALIFoRNIA
M ►T IO €iI '
13 t1
INCORiPORATsp
� e
WESTSIDE MOBILITY IMPROVEMENTS
CIP NO. 17-04
Contractor: Palm Engineering Construction Company, Inc.
Reason/Purpose for this Change Order:
The West Avenue bulbout inlet could not be capped as specified in the plans because of the surface runoff from
the bulbout. Under direction of the Engineer the Contractor proceeded with furnishing and installing an ADA inlet
frame and grate within the West Avenue bulbout.
CHANGE ORDER NO. 9
November 16, 2017
The City of National City and Contractor agree to the following change to the original Contract:
The City and the Contractor agree that the Contractor shall proceed with furnishing and installing an ADA inlet
frame and grate within the West Avenue bulbout. The agreed upon price for all costs associated with this work is
as stated on this Change Order. See Attachments for cost breakdown.
Original Contract Amount
Net change by previously authorized Change Orders
Subtotal
Amount of this change order
New contract amount
Working days added: 0 Working days subtracted: 0 Percent change in Contract to date 2.22%
Submitted by:
ect Ma
er
1,780,325.57
39,015.65
1,819,341.22
555.0
1,819,896.2
--v- —r
Approved by:
::
. -
2. ..... .
City ngineer
•
././h. 1.//)
Date
•
City Manager, required for Change Orders >S24,999
.
Date
By signing this Change Order the Contractor confirms that he/she is completely familiar with its terms and conditions and has fairly negotiated
its price, terms and conditions. If this Change Order is approved, Contractor will provide all of the equipment, materials and labor necessary to
provide a complete work as described above at that the price stated herein. Additionally, Contractor confirms that the price Is fair and complete
and represents all costs associated with the work, including but not limited to all equipment, materials, labor, supervision, overhead, fees,
bonds, insurance, profit, etc. and that there will be no further compensation. All of the terms and conditions of the original contract documents
are incorporated herein.
Note to Contractor: If you do not agree with this Change Order you may be directed to proceed with this work under the terms of the contract
and you may proceed under protest. You must comply with the contract requirements of submitting a written protest to protect your claim.
Originals: City Clerk, Contractor cc: Engineering project file, Project Manager
Telephone (619) 336-438d
1243 National City fioulevard, National City, CA 91950
WESTSIDE MOBILITY IMPROVEMENTS CHANGE ORDER NO. 9
CIP NO. 17-04
DATE: October 17, 2017
WORK PERFORMED BY: Palm Engineering
DESCRIPTION OF WORK: Furnish and install ADA inlet grade for West Avenue bulbout
ACCOUNTING FOR TIME, MATERIALS, AND EQUIPMENT
Unit
Qty
Wage
Total
$
Sub -Total Labor:
Labor surcharge (29.45%):
Labor Markup (20%): $ -
TOTAL LABOR-1111111.11
Unit
ADA inlet frame and grate LS
Qty
1.00
Rate
473.160
$
Total
473.16
Sub -Total Materials:
$ 473.16
Materials Markup (15%): $ 70.97
TOTAL MATERIALS:
EQUIPMENT
1)
N/A
Unit
Qty
Rate
Total
Sub -Total Equipment:
Equipment Markup (15%):
TOTAL EQUIPMENT:
$
SUB TOTAL:
BOND AND INSURANCE (2%):
GRAND TOTAL:
46.11 Oldcastle Precast*
PO Box 310039
Fontana, CA 92331
Telephone:
Fax •
BY:— ---
909-428-3700
877-797-0750
SOLD TO: SHIP TO:
4779 1 Ali 0.403 E0121X 10185 D2941480783 S2 P4742025 0001:0001
r11Ir111111111+rr111111111111111111111111111r11r1111111111111111
PALM ENGINEERING
7330 OPPORTUNITY RD STE J
SAN DIEGO CA 92111-2221
INVOICE
Page 1 of!
Remit to:
Oldcastle Precast Inc.
P.O. Box 742387
Los Angeles, CA 90074-2387
Site:
LAKESIDE- WILL CALL
10441 VINE ST
LAKESIDE, CA 92040 2415
Lakeside
Invoice No.
070216958
Date
10/17/2017
Packing slip(s) ...: SP259604
Customer No.
070100260
Order No. Customer P/q'
S199703 Job 17057
Delivery Terms
Plant Pickup
Mode of Delivery
Qty Unit Item Description Mark Unit Price Amount
1.00 Ea 990017430 2424 TRF GRATE,ADA,BD/GALV
1.00 Ea 990032090 FRAME FOR 2424VF GALVANIZED -INCLUDES
HARDWARE AND INSERTS FOR BOLT -DOWN
APPLICATION -
TOTAL AMOUNT DUE BY: 11/16/17
369.12 369.12
70.00 70.00
Tax 34.04
US 473.16
Ainimum 10% handling charge on all returned goods. No goods to be returned without consent. Give as reference our invoice number and date. Claims for damages, back charges for labor. other expenses, will not be
Wowed unless authorized in writing by the seller. The articles and/or services covered by this invoice were produced in compliance with the Federal Labor Standards Act of 1938, as amended.
;he Customer Agrees
1. THAT THE ABOVE TOTAL IS PAST DUE IF NOT PAID WITHIN 30 DAYS OF DATE OF THIS INVOICE
2. TO PAY A FINANCE CHARGE OF 1.5% PER MONTH (18% PER ANNUM) ON ANY PAST DUE AMOUNT.
3. TO PAY COLLECTION COSTS, INCLUDING REASONABLE ATTORNEY FEES, AFTER DEFAULT BY THE CUSTOMER
1001:0001
PROJECT PROFESSIONALS CORPORATION
TRANSMITTAL COVER
To: National City Engineering Department
Project Name: Westside Mobility Improvements
Spec No 17-04
ITEMS DELIVERED:
Change Orders #5-9
Delivered by:
Received by:
Date:
Pro ect Professionals Corporation
���111Hw ..... n�iNll/�
A1i
CITY OF NATIONAL CITY
Office of the City Clerk
1243 National City Blvd., National City, California 91950-4397
619-336-4228
Michael R. Dalla, CMC - City Clerk
PALM ENGINEERING CONSTRUCTION COMPANY, INC.
Change Orders #5 through #9
Westside Mobility Improvements Project
CIP No. 17-04
Judy Hernandez (Engineering/Public Works) Forwarded
Copy of Change Orders to Palm Engineering Construction Company, Inc.