HomeMy WebLinkAbout2017 CON Kinsman Construction - Police Department Building Improvements - Notice of CompletionPLEASE COMPLETE THIS INFORMATION
(),Q RECORDING REQUESTED BY:
City Engineer
City of National City
1243 National City Blvd.
National City, CA 91950
AND WHEN RECORDED MAIL TO:
City Engineer
City of National City
1243 National City Blvd.
National City, CA 91950
DOC# 2017-0548727
111EliltIll llI II II III IH III I III II III
Nov 27, 2017 03:01 PM
OFFICIAL RECORDS
Ernest J. Dronenburg, Jr.,
SAN DIEGO COUNTY RECORDER
FEES: $0.00
PAGES 2
THIS SPACE FOR RECORDER'S USE ONLY
(Note: This document is recorded on behalf of the City of National City, a municipal corporation, and is exempt
from Recorder's fees pursuant to Government Code Section 27383)
NOTICE OF COMPLETION:
POLICE DEPARTMENT BUILDING IMPROVEMENTS PROJECT
CIP No. 15-06
THIS PAGE ADDED TO PROVIDE ADEQUATE SPACE FOR RECORDING INFORMATION
(Additional recording fee applies)
111
RECORDING REQUESTED BY
WHEN RECORDED MAIL TO:
NAME: CITY OF NATIONAL CITY
ADDRESS: 243 NATIONAL CITY BOULEVARD
NATIONAL CITY, CA 91950
NOTICE OF COMPLETION
CALIFORNIA CIVIL CODE SECTION 3093
NOTICE IS HEREBY GIVEN of the completion on April 12, 2017 of the:
Police Department Building Improvements, CIP No. 15-06
Work of improvement or portion of work of improvement under construction or alteration.
1200 National City Blvd. National City CA 91950
Street Address
City State Zip Code
The undersigned owns the following interest or estate in said property:
Owner in fee
Nature of the interest or estate of owner (mortgagor, lessee, etc.)
Said work of improvement was performed on the property pursuant to a contract with
Kinsman Construction, Inc.
Name of Original Contractor
The following work and material were supplied:
Labor provided: General laborer. Materials: HVAC systems, plumbing fixtures, fire alarm/sprinkler
system, and electrical equipment.
General statement of kind of labor, services, equipment or materials
The names and addresses of co-ownets.are: N/A
Dated: April 12, 2017;
Joint tenan to nts in common, or other owners
Signature of Owner
City of National City, 1243 National City Blvd., National City, CA 91950
I, the undersigned, say: I have read the foregoing Notice of Completion and know the contents
thereof; the same is true of my own knowledge. I declare under penalty of perjury that the forgoing
is true and correct.
Executed on Apr 11 , 2017 at, National City, California.
Signature:
RON MORRISON, MAYOR
Noc15-06
FINAL CONTRACT BALANCE
POLICE DEPARTMENT BUILDING IMPROVEMENTS
CIP No. 15-06
Change Order #18. The City found the contractor unable to finish the as -built drawings. The City asked
the designer to conduct a field verification of the installation and to update the record drawings
themselves. This deductive change order was applied to account for the increase in design team costs.
This change order amount is $900.
All Change Orders listed above increased the total contract amount $359,189.27.
CONTRACT ADJUSTMENT:
As a result of the above change orders and line item adjustments, the contract price is adjusted as
follows:
1. The final contract price is adjusted to $1,127,648.27.
2. As a result of the satisfactory completion of said project, a retention amount of $5,527.43 is set
for invoice processing and payment upon the receipt of signatures and City Council's ratification
of this agreement and the Notice of Completion.
This document and its purpose to balance payment shall be considered full compensation for furnishing
and installing the materials, labor, tools and equipment, profit, overhead, and all incidentals for
performing the work described above. Kinsman Construction, Inc. will not be entitled to damages or
additional payment for delays as described in the 2012 edition of the Standard Specifications for Public
Works Construction, Section 6-6.3, for performing the work as described above.
RESOLUTION 2017 — 207
RESOLUTION OF THE CITY COUNCIL OF THE CITY OF NATIONAL CITY
ACCEPTING THE WORK PERFORMED BY KINSMAN CONSTRUCTION
COMPANY, INC., FOR THE POLICE DEPARTMENT BUILDING
IMPROVEMENTS PROJECT, APPROVING THE FINAL CONTRACT
AMOUNT OF $1,127,648.27, RATIFYING THE RELEASE OF RETENTION
IN THE AMOUNT OF $5,527.43, AND AUTHORIZING THE MAYOR
TO SIGN THE NOTICE OF COMPLETION FOR THE PROJECT
WHEREAS, the Engineering Department is satisfied that all work required to be
performed by Kinsman Construction Company, Inc., for the Police Department Building
Improvements Project has been completed.
NOW, THEREFORE, BE IT RESOLVED by the City Council of the City of
National City that the work performed by Kinsman Construction Company, Inc., for the Police
Department Building Improvements Project is accepted, the total final contract amount of
$1,127,648.27 is approved, the Mayor is authorized to execute the Notice of Completion, and
payment for said work is ordered to be made in accordance with said contract, including release
of retention in the amount of $5,527.43.
PASSED and ADOPTED this 7th day of Nove 017.
on • rrison, ' ayor
ATTEST:
Mic . el R. Dalla, Ci r Clerk
APPROVED AS • FORM:
. Morri -Jones
Attorney
Passed and adopted by the Council of the City of National City, California, on
November 7, 2017 by the following vote, to -wit:
Ayes: Councilmembers Cano, Mendivil, Morrison, Rios, Sotelo-Solis.
Nays: None.
Absent: None.
Abstain: None.
AUTHENTICATED BY: RON MORRISON
Mayor of the City of National City, California
A
City Clerk of the City c(f National City, California
By:
Deputy
I HEREBY CERTIFY that the above and foregoing is a full, true and correct copy of
RESOLUTION NO. 2017-207 of the City of National City, California, passed and
adopted by the Council of said City on November 7, 2017.
City Clerk of the City of National City, California
By:
Deputy
CITY OF NATIONAL CITY, CALIFORNIA
COUNCIL AGENDA STATEMENT
MEETING DATE: November 7, 2017
AGENDA ITEM NO. 6
ITEM TITLE:
Resolution of the City Council of the City of National City: 1) accepting the work performed by
Kinsman Construction Company, Inc. for the Police Department Building Improvements Project, CIP
No. 15-06; 2) approving the final contract amount of $1,127,648.27; 3) ratifying the release of retention
in the amount of $5,527.43; and 4) authorizing the Mayor to sign the Notice of Completion for the
project.
PREPARED BY: Jose Lopez, Assistant Engineer - Civil DEPARTMENT: Engineers g P Works
PHONE: 619-336-4312
EXPLANATION:
See attached.
APPROVED BY:
'INANCIAL STATEMENT:
ACCOUNT NO.
N/A
ENVIRONMENTAL REVIEW:
N/A
ORDINANCE: INTRODUCTION:
FINAL ADOPTION:
APPROVED:
APPROVED:
Finance
MIS
STAFF RECOMMENDATION:
Adopt Resolution accepting the work performed by Kinsman Construction Company, Inc. for the Police
Department Building Improvements Project, CIP No. 15-06 and approving the final contract amount of
$1,127,648.27.
BOARD / COMMISSION RECOMMENDATION:
N/A
ATTACHMENTS:
1. Explanation
2. Notice of Completion
3. Final Contract Balance Report
4. Resolution
Ae s 0 �it ?Liao /00. 2.O ! q- - 20 -
EXPLANATION
The Police Department Building Improvements Project, CIP No. 15-06, included electrical
and mechanical upgrades to support expansion of the Police Department Property and
Evidence Room, ADA upgrades, fire suppression system upgrades to both the Police
Department server room and City Hall server room, HVAC upgrades to the Police
Department sever room, and waterproofing.
On July 16, 2015, the bid solicitation was posted on PlanetBids, a free public electronic
bidding system for contractors. On July 17, 2015 and July 21, 2015, the bid solicitation was
advertised in local newspapers.
On August 20, 2015, four (4) bids were received electronically on PlanetBids by the
3:00 p.m. deadline. Bid results were available immediately after the 3:00 p.m. deadline.
Kinsman Construction, Inc. was the apparent lowest bidder with a total bid amount of
$768,463.00 as the basis of bid award. Upon review of all documents submitted and
reference checks, Kinsman Construction, Inc.'s bid was found to be responsive, and they
were the lowest responsible bidder qualified to perform the work as described in the project
specifications.
On September 15, 2015, the City Council adopted Resolution No. 2015-139 awarding the
contract to Kinsman Construction, Inc. (KCI) in the not -to -exceed amount of $768,463
authorized a 25% contingency in the amount of $192,115.75 for any unforeseen changes.
The Notice to Proceed with construction was issued on November 12, 2015, with a
construction start date of November 16, 2015.
On May 3, 2016, the City Council adopted Resolution No. 2016-59 increasing the contract
with KCI in the not to exceed amount of $127,007.15, and authorized the Mayor to execute
Change Order No. 7 in the amount of $127,007.15 to provide waterproofing around the
entire ground floor perimeter of the Police Department Building, planter boxes and the two
pedestrian decks on the second floor.
The Police Department Upgrades project construction was completed on April 11, 2017.
The majority of the building improvements were completed in 2016, however the added
waterproofing scope extended the contract duration into 2017. During the final three months
of the work, both KCI's project manager and project superintendent left the company,
leaving KCI with a Toss of institutional knowledge concerning the project required to
complete the project's record drawings. While the final construction invoice was paid in July
2017, along with 90% of the retention as a result of satisfactory completion of the project,
the remaining retention balance was held to ensure KCI created and submitted record
drawings as required by the construction contract.
The record drawings were initially submitted by KCI for review in September 2017.
However, after reviewing the record drawings, missing information was noticed. Because of
the loss of KCI's personnel who were familiar with the work, the missing plan information
could not be provided. The CM team, with approval from the City, tasked the design team
with conducting field reconnaissance to record the missing information and updating the
record drawings. This effort was conducted in early October. A deductive change order in
the amount of -$900 was processed in order to back charge KCI for the designer's effort to
finalize the record drawings.
The change orders issued for this project are detailed in the Final Contract Balance Report
(see attached). The change orders increased the contract by $359,185.27. This results in
a 46.7% contract increase for a final contract balance of $1,127,648.27.
As a result of satisfactory completion of the project, staff recommends that City Council: 1)
accept the work of Kinsman Construction, Inc. for the Police Department Building
Improvements Project, CIP No. 15-06; 2) approve the final contract amount of
$1,127,648.27; 3) authorize the release of retention in the amount of $5,527.43; and 4)
authorize the Mayor to sign the Notice of Completion for the project.
The Notice of Completion will be filed with the San Diego County Recorder's Office.
RECORDING REQUESTED BY
WHEN RECORDED MAIL TO:
NAME: CITY OF NATIONAL CITY
ADDRESS: 243 NATIONAL CITY BOULEVARD
NATIONAL CITY, CA 91950
NOTICE OF COMPLETION
CALIFORNIA CIVIL CODE SECTION 3093
NOTICE IS HEREBY GIVEN of the completion on April 12, 2017 of the:
Police Department Building Improvements, CIP No. 15-06
Work of improvement or portion of work of improvement under construction or alteration.
1200 National City Blvd. National City CA. 91950
Street Address
City State Zip Code
The undersigned owns the following interest or estate in said property:
Owner in fee
Nature of the interest or estate of owner (mortgagor, lessee, etc.)
Said work of improvement was performed on the property pursuant to a contract with
Kinsman Construction, Inc.
Name of Original Contractor
The following work and material were supplied:
Labor provided: General laborer. Materials: HVAC systems, plumbing fixtures, fire alarm/sprinkler
system, and electrical equipment.
General statement of kind of labor, services, equipment or materials
The names and addresses of co -owners are: N/A
Joint tenants, tenants in common, or other owners
Dated: April 12, 2017;
Signature of Owner
City of National City, 1243 National City Blvd., National City, CA 91950
I, the undersigned, say: I have read the foregoing Notice of Completion and know the contents
thereof; the same is true of my own knowledge. I declare under penalty of perjury that the forgoing
is true and correct.
Executed on April 12, 2017 at, National City, California.
Signature:
RON MORRISON, MAYOR
Noc15-06
-1-
CALIFO N` A..
NATIi1%NAL CITT
aE33V
INCORrpor,ATED
FINAL CONTRACT BALANCE
DATE: October 17, 2017
PROJECT: Police Department Building Improvements
FY 15-17
CIP No. 15-06
TO:
Kinsman Construction, Inc.
6711 Nancy Ridge Drive
San Diego, CA 92121
ORIGINAL CONTRACT AMOUNT:
START DATE:
COMPLETION DATE:
ORIGINAL CONTRACT LENGTH:
EXTENTION OF WORK DAYS:
TOTAL CONTRACT TIME:
FINAL CONTRACT AMOUNT:
DESCRIPTION:
$768,463.00
November 16, 2015
April 11, 2017
120 Working Days
231 Working Days
351 Working Days
$1,127, 648.27
The Final Contract Balance reports final line item amounts and summarizes all change orders to produce
a final contract amount.
CHANGE ORDERS AND LINE ITEM ADJUSTMENTS:
Change Order #1. The owner asked Kinsman Construction to remove dirt from additional planter boxes
around the building. The owner also requested the use of a special inspector to witness and certify the
anchor bolts being installed for the shelving systems. This Change Order total amount is $ 7,148.00
Change Order #2. Due to lack of space available to temporarily store evidence, the City approved the use
of a 40-foot shipping container to accommodate additional storage. Additionally, the City requested a
proposal to reconfigure office partitions on the third floor and to provide additional partitions. This
Change Order amount is $ 14,367.20
Change Order #3. As a result of further investigations by the waterproofing consultant, David Reed, the
curtain wall injection called out as Additive Bid item 4 is not deemed necessary and is deleted by this
change order. This Change Order credit amount is ($ 22,471.00)
Change Order #4. It was determined that the 6'6" doors will not work. New doors will need to be 7' tall.
The City directed the contractor to install 7' doors. Also, it was determined that an existing electrical
panel did not have the proper cover. A new panel will be required to meet code. This Change Order
amount is $ 8,060.55
-2-
FINAL CONTRACT BALANCE
POLICE DEPARTMENT BUILDING IMPROVEMENTS
CIP No. 15-06
Change Order #5. The City asked for additional crystalline waterproofing, concrete bottoms to the
planters with waterproofing and drainage. This Change Order amount is $ 19,011.07
Change Order #6. The City requested electrical revisions as suggested by PD staff. Also, the City asked
that burned out lights within the building be replaced. This Change Order amount is $ 20,775.93
Change Order #7. The City requested additional waterproofing per David Reed's recommendations,
added concrete bottoms to the planters currently not in the contract with additional waterproofing and
drainage. This Change Order amount is $ 127,007.00
Change Order #8. The City requested a revision to the duct in the basement. Also, a new valve is
required on the fire riser at City Hall. A new ADA ramp is needed at the door to the evidence area from
the basement. This Change Order amount is $ 14,753.76
Change Order #9. Due to a conflict with the size of the AC units to be installed in the server room on the
second floor, the contractor found it necessary to use a crane to place the units on the patio at the
break room and then to remove a door frame leading into the hall in order to get the units into the
server room. Also, the City requested replacement of door hardware on 18 doors and the provisions for
6 spare hardware sets for building stock. This Change Order amount is $ 23,358.48
Change Order #10. The City requested a proposal from the contractor to replace a damaged roll up gate
at the entrance to the parking deck. This Change Order amount is $ 4,910.50
Change Order #11. The City requested a proposal from the contractor to replace the main sign at the
entrance to the building. This Change Order amount is $ 8,481.25
Change Order #12. The City requested a proposal from the contractor to repair the hot water
recirculation pipe in the building. This Change Order amount is $ 23,009.26
Change Order #13. The City requested a proposal from the contractor to replace the ballasts for all non-
functioning lights in the building. The City also requested a proposal from the contractor to provide
waterproofing of the parking deck in areas where it has failed. This Change Order amount is $ 19,187.13
Change Order #14. The City requested a proposal from the contractor to repair additional waterproofing
around the perimeter of the building. This Change Order amount is $ 19,153.00
Change Order #15. Request to replace flagpole Tight, refrigerator outlets, access control at gun locker,
biometric scanner. This Change Order amount is $ 4,938.00
Change Order #16. Request to planter irrigation, backfill with city material, cores, and electrical at
planter, irrigation per plan, landscape planting, and maintenance. $ 45,959.00
Change Order #17. The City asked for a proposal to repair the deck slab waterproofing between the
planter box and ADA parking stall on the parking deck (COR 37R1), to relocate the existing flagpole light
located on the roof and replace two red exit signs with green signs (COR 38), and to remove wall
covering and replace with textured painted surface (COR 39), and irrigation trench backfill (COR 41). This
Change Order amount is $ 22,436.14
-3-
FINAL CONTRACT BALANCE
POLICE DEPARTMENT BUILDING IMPROVEMENTS
CIP No. 15-06
Change Order #18. The City found the contractor unable to finish the as -built drawings. The City asked
the designer to conduct a field verification of the installation and to update the record drawings
themselves. This deductive change order was applied to account for the increase in design team costs.
This change order amount is $900.
All Change Orders listed above increased the total contract amount $359,189.27.
CONTRACT ADJUSTMENT:
As a result of the above change orders and line item adjustments, the contract price is adjusted as
follows:
1. The final contract price is adjusted to $1,127,648.27.
2. As a result of the satisfactory completion of said project, a retention amount of $5,527.43 is set
for invoice processing and payment upon the receipt of signatures and City Council's ratification
of this agreement and the Notice of Completion.
This document and its purpose to balance payment shall be considered full compensation for furnishing
and installing the materials, labor, tools and equipment, profit, overhead, and all incidentals for
performing the work described above. Kinsman Construction, Inc. will not be entitled to damages or
additional payment for delays as described in the 2012 edition of the Standard Specifications for Public
Works Construction, Section 6-6.3, for performing the work as described above.
-4-
RESOLUTION 2017 —
RESOLUTION OF THE CITY COUNCIL OF THE CITY OF NATIONAL CITY
ACCEPTING THE WORK PERFORMED BY KINSMAN CONSTRUCTION
COMPANY, INC., FOR THE POLICE DEPARTMENT BUILDING
IMPROVEMENTS PROJECT, APPROVING THE FINAL CONTRACT
AMOUNT OF $1,127,648.27, RATIFYING THE RELEASE OF RETENTION
IN THE AMOUNT OF $5,527.43, AND AUTHORIZING THE MAYOR
TO SIGN THE NOTICE OF COMPLETION FOR THE PROJECT
WHEREAS, the Engineering Department is satisfied that all work required to be
performed by Kinsman Construction Company, Inc., for the Police Department Building
Improvements Project has been completed.
NOW, THEREFORE, BE IT RESOLVED by the City Council of the City of
National City that the work performed by Kinsman Construction Company, Inc., for the Police
Department Building Improvements Project is accepted, the total final contract amount of
$1,127,648.27 is approved, the Mayor is authorized to execute the Notice of Completion, and
payment for said work is ordered to be made in accordance with said contract, including release
of retention in the amount of $5,527.43.
PASSED and ADOPTED this 7th day of November, 2017.
Ron Morrison, Mayor
ATTEST:
Michael R. Dalla, City Clerk
APPROVED AS TO FORM:
Angil P. Morris -Jones
City Attorney
CITY OF NATIONAL CITY
Office of the City Clerk
1243 National City Blvd., National City, California 91950-4397
619-336-4228
Michael R. Dalla, CMC - City Clerk
KINSMAN CONSTRUCTION COMPANY, INC.
NOTICE OF COMPLETION
POLICE DEPARTMENT BUILDING IMPROVEMENTS PROJECT
CIP NO. 15-06
Vendor has original copy of recorded Notice of Completion
Confirmed by Judy H. (ENG/PW)