Contractor: Dick Miller, Inc.
Reason/Purpose for this Change Order:
Through value engineering during construction multiple line items were deleted resulting in a total base bid
deduction of $136,322.00. The line items associated with this were 22, 28, 33, 34, 36, 47, 54, 55, 67 and 68. See
attachment for details.
CHANGE ORDER NO. 49
September 27, 2017
The City of National City and Contractor agree to the following change to the original Contract:
The City and the Contractor agree that line items 22, 28, 33, 34, 36, 47, 54, 55, 67 and 68 are to be deleted from
the Contract. The line item deletion will be reflected on the final billing statement as 0 value on each individual
line item and the deduction is not indicated here. See Attachment for details.
Original Contract Amount $ 1,894,498.10
Net change by previously authorized Change Orders
Subtotal
Amount of this change order
143,788.22
2,038,286.32
New contract amount $ 2,038,286.32
Working days added: 0 Working days subtracted: 0 Percent change in Contract to date 7.59%
Submitted by:
/1-41-
ect M.'aeer
Date
Approved by:
2
Citngineer
City Manager, required for Change Orders >$24,999 Date
By signing this Change Order the Contractor confirms that he/she is completely familiar with its terms and conditions and has fairly negotiated
its price, terms and conditions. If this Change Order is approved, Contractor will provide all of the equipment, materials and labor necessary to
provide a complete work as described above at that the price stated herein. Additionally, Contractor confirms that the price is fair and complete
and represents all costs associated with the work, including but not limited to all equipment, materials, labor, supervision, overhead, fees,
bonds, insurance, profit, etc. and that there will be no further compensation. All of the terms and conditions of the original contract documents
are incorporated herein.
Accepted and agreed to by Dick Miller, Inc.:
Name:Thav4LArocA,I..ss Date
Note to Contractor: If you do not agree with this Change Order you may be directed to proceed with this work under the terms of the contract
and you may proceed under protest. You must comply with the contract requirements of submitting a written protest to protect your claim.
Originals: City Clerk, Contractor cc: Engineering project file, Project Manager
1243 National -City BouTivin, National ty, er91 0- Telep one (619) 3A6-4 86
-- CALIFORNIA +-+=F
NoiONAL
nay
CoRpoRAT
PLAZA BLVD WIDENING "N" AVENUE TO 1-805
Specification #16-01
DATE: September 27, 2017
CHANGE ORDER NO. 49
WORK PERFORMED BY: -
DESCRIPTION OF WORK: Line item deletions
No.
Item
Unit
Quantit
Unit Price
Amount
Description
22
CONCRETE CURB - TYPE B-3
(SDRSD G-6)
LF
302
22.00
(6,644.00)
Deletion of median to
accommodate access to
businesses
28
TYPE A PEDESTRIAN CURB
RAMP (SDRSD G-27)
EA
3
1,380.00
(4,140.00)
Type A Pedestrian Ramps did
not work and proceeded with
Type C Ramps
33
STAMPED MEDIAN CONCRETE
SF
514
14.50
(7,453.00)
Deletion of median to
accommodate access to
businesses
34
EXPOSED AGGREGATE
MEDIAN CONCRETE
SF
3069
10.00
(30,690.00)
Deletion of median to
accommodate access to
businesses
36
DECORATIVE FENCE IN
MEDIAN
LF
480
128.00
(61,440.00)
Deletion of median to
accommodate access to
businesses
47
TYPE A CURB OUTLET(SDRSD
D-25, MODIFIED) (WESTERN
DENTAL)
EA
1
3,100.00
(3,100.00)
Did not need curb outlet with
drainage layout
54
STORM DRAIN CLEANOUT
(SDRSD SC-01)
EA
2
2,800.00
(5,600.00)
Did not need storm drain
cleanouts as it was for roof
drains
55
12" CONCRETE AREA DRAIN
(STEEL TRAFFIC GRATE - ADA)
EA
3
755.00
(2,265.00)
Did not need area drains with
drainage layout
67
ALLOWANCE FOR CALTRANS
PERMIT FEES
LS
1
5,000.00
(5,000.00)
Deletion of median to
accommodate access to
businesses
68
FIELD ORDERS
LS
1
10,000.00
(10,000.00)
Did not proceed with any field
orders
Total:
$ (136,332.00)
1
- • \
Nat i 11_.i
- irlf , . ..
c.-...--,-. 8 8 7 ...„....-,..,
iNconponATEL, , ../
PLAZA BLVD WIDENING "N" AVENUE TO 1-805
Specification No. 16-01
Contractor: Dick Miller, Inc.
CHANGE ORDER NO. 50
September 27, 2017
Reason/Purpose for thls Change Order:
The 2" grind and overlay per Contract would not be sufficient to repair the failing sections of asphalt along Plaza
Blvd from N Avenue to the 1-805. To provide a stable structural street section under direction of the Engineer the
Contractor proceeded to remove and replace an additional 6" of asphalt within the failing sections.
The City o f National City and Contractor agree to the following change to the original Contract:
The City and the Contractor agree that the Contractor shall proceed with removing and replacing an additional 6"
of asphalt within the failing sections along Plaza Blvd from N Avenue to the 1-805. The agreed upon price for all
costs associated with this work is as stated on this Change Order. See Attachment for cost breakdown.
Original Contract Amount
Net change by previously authorized Change Orders
Subtotal
Amount of this change order
New contract amount
Working days added: 42 Working days subtracted: 0
Submitted by:
City.'Engineer
/14
4
Percent change in contract to date 17.26%
• •
1,894,498.10
143,788.22
2,038,286.32
183,135.00
2,221,421,32
Date City Manager, required for Change Orden >$24.999 Date
By signing this Change Order the Contractor confirms that he/she is completely familiar with its terms and conditions and has fairly negotiated
its price, terms and conditions. If this Change Order is approved, Contractor will provide all of the equipment, materials and labor necessary to
provide a complete work as described above at that the price stated herein. Additionally, Contractor confirms that the price is fair and complete
and represents all costs associated with the work, including but not limited to all equipment, materials, labor, supervision, overhead, fees,
bonds, insurance, profit, etc. and that there will be no further compensation. All of the terms and conditions of the original contract documents
are incorporated herein.
Accepted and-
ed to by Dick Miller, Inc.:
•
Narr_ VALAcciAL ; Date 1% rt (11
Note to Contractor if you do not agree with this Change Order you may be directed to proceed with this work under the terms of the contract
and you may proceed under protest. You must comply with the contract requirements of submitting a written protest to protect your claim.
Originals: City Clerk, Contractor cc: Engineering project file, Project Manager
1243 National City Boulevard, National City, CA 91950
Telephone (619) 336-4380
NN\\\
GAL'I RNIA *-�+
NAT'11'fl?
liaitt
5NCORPO ATED
PLAZA BLVD WIDENING "N" AVENUE TO 1-805
Specification # 16-01
DATE: September 27, 2017
CHANGE ORDER NO.50
WORK PERFORMED BY: DMI and SRM
DESCRIPTION OF WORK: 6" Deep Iift asphalt repairs
Item
Unit
Qty
Rate
Total
1)
6" Deep Iift asphalt repairs
TON
1,263.00
145.00
183,135.00
TOTAL:
$ 183,135.00
PROJECT PROFESSIO
LS CORP ■ RATION
TRANSMITTAL COVER
To: National City Engineering Department
Project Name: Plaza Blvd Widening "N" Avenue to 1-805
Spec No 16-01
ITEMS DELIVERED:
Change Orders #49 and #50
Delivered by:
Received by:
Project Professionals Corporation
Date: \/tSli1-
1
N�kIOkATEDAA��`Np�•
CITY OF NATIONAL CITY
Office of the City Clerk
1243 National City Blvd., National City, California 91950-4397
619-336-4228
Michael R. Dalla, CMC - City Clerk
DICK MILLER, INC.
Change Orders #49 through #50
Plaza Blvd. Widening — "N" Ave. to 1-805
Sp. No. 16-01
Judy Hernandez (Engineering/Public Works) Forwarded
Copy of Change Orders to Dick Miller, Inc.