HomeMy WebLinkAbout2015 CON San Diego Port District - National City Aquatic Center - Amendment #2 MOUNOTE TO FILE
01-29-18
IN THE MATTER OF: Resolution 2015-164, of the City of National
City rescinding Resolution No. 2015-142 approving Amendment
No. 2 to the amended and restated MOU with the San Diego
Unified Port District regarding the National City Aquatic Center.
Please note the following:
A FULLY EXECUTED ORIGINAL AMENDMENT NO. 2 MOU
WAS NEVER FILED WITH THE OFFICE OF THE CITY CLERK.
NOTE: RESCINDS RESOLUTION NO. 2015-142 ADOPTED ON 09-15-15.
ORIGINATING DEPARTMENT:
CDC Housing & Grants
City Attorney Human Resources
City Manager MIS
Community Svcs. Planning
X Engineering Police
Finance X Public Works
Fire
*11-10-15: Forwarded (2) partially executed original Amendments to Steve M. (ENG) to have Tirza process
for signatures.
NTF
AMENDMENT NO. 2 TO THE
AMENDED AND RESTATED
MEMORANDUM OF UNDERSTANDING
BETWEEN SAN DIEGO UNIFIED PORT DISTRICT
AND THE CITY OF NATIONAL CITY
REGARDING THE NATIONAL CITY AQUATIC CENTER
This AMENDMENT NO. 2 TO THE AMENDED AND RESTATED
MEMORANDUM OF UNDERSTANDING BETWEEN SAN DIEGO UNIFIED
PORT DISTRICT AND THE CITY OF NATIONAL CITY REGARDING THE
NATIONAL CITY AQUATIC CENTER is made and entered into this day of
, 201, by and between the SAN DIEGO UNIFIED PORT
DISTRICT, a public corporation, hereinafter called "District," and the CITY OF
NATIONAL CITY, a municipal corporation, hereinafter called "City".
WHEREAS, on August 13, 2013, the parties entered into The Amended
And Restated Memorandum Of Understanding Between San Diego Unified Port
District And The City Of National City Regarding The National City Aquatics
Center, on file in the Office of the District Clerk as Document No. 60744, related
to the National City Aquatic Center (Project); and
WHEREAS, the parties executed Amendment No. 1 To The Amended
And Restated Memorandum Of Understanding Between San Diego Unified Port
District And The City Of National City Regarding The National City Aquatics
Center, on file in the Office of the District Clerk as Document No. 63880.
WHEREAS, due to increased costs of the construction, City has
requested District increase the not -to -exceed amount of reimbursement under
this MOU.
NOW THEREFORE, the parties agree that the Amended And Restated
Memorandum Of Understanding Between San Diego Unified Port District And
The City Of National City Regarding The National City Aquatics Center be
amended as follows:
A. Paragraph 2 shall be replaced in its entirety with the following:
2. District agrees to contribute a total amount not to exceed
$4,633,110 to the Project for design and construction as follows:
(a) District shall transfer to City $830,000 to be used towards
design and/or construction costs. City acknowledges that this
obligation of the District has previously been satisfied in full by a
transfer on September 26, 2011.
1
(b) District shall reimburse City for Project construction costs in an
amount not to exceed $3,803,110 in accordance with and
subject to Section 5 herein.
B. Paragraph 3 shall be replaced in its entirety with the following:
3. City agrees to be solely responsible for any Project costs in excess
of the $4,633,110 contribution from the District. City shall not be
relieved of any obligations under this MOU due to increased
expenses or cost overruns.
C. Paragraph 5 shall be amended by adding new subparagraph (g) as follows:
g.
In addition to the other limitations on reimbursement herein, the
District shall not be obligated to reimburse City for the last
$223,110 of the maximum $4,633,110 until City has received all of
the following and provided copies to District: (1) unconditional
waivers and releases from all contractors, subcontractors, material
suppliers, equipment lessors, laborers, design professionals, other
persons or entities that provided work for the Project, and any other
person or entity that filed a stop work notice and/or preliminary
notice related to the Project; (2) a Certificate of Occupancy for the
Project; (3) Americans with Disabilities Act (ADA) inspection
approval for the Project; and (4) recordation of Notice of
Completion with the County.
D. All remaining terms shall remain in full force and effect.
SIGNATURE PAGE FOLLOWS
2
IN WITNESS WHEREOF, parties hereto have executed this Amendment No. 2
To Amended And Restated Memorandum Of Understanding Between San Diego
Unified Port District And The City Of National City Regarding The National City
Aquatics Center as of the day and the year first above written.
APPROVED AS TO FORM AND LEGALITY SAN DIEGO UNIFIED PORT DISTRICT
By By
Deputy General Counsel
Karen G. Porteous
EVP, Administration
APPROVED aS TO FORM: CITY OF NATIONAL CITY
By�/lam_
Clau • is G. ilva Ron Morrison
ity ° ttorney Mayor
3
RESOLUTION NO. 2015 — 164
RESOLUTION OF THE CITY COUNCIL OF THE CITY OF NATIONAL CITY
RESCINDING RESOLUTION 2015-142 APPROVING AMENDMENT NO. 2
TO THE AMENDED AND RESTATED MEMORANDUM OF UNDERSTANDING
BETWEEN THE SAN DIEGO UNIFIED PORT DISTRICT AND THE CITY OF
NATIONAL CITY REGARDING THE NATIONAL CITY AQUATIC CENTER
(RENAMED AS THE WATERFRONT ADVENTURE CENTER); AUTHORIZING
THE MAYOR TO EXECUTE A REVISED AMENDMENT NO. 2 TO
THE AMENDED AND RESTATED MEMORANDUM OF UNDERSTANDING
WHEREIN THE PORT DISTRICT AGREES TO CONTRIBUTE AN
ADDITIONAL $223,110 TOWARDS COMPLETION OF THE PROJECT,
BASED ON ADDITIONAL LANGUAGE REQUESTED AND APPROVED
BY THE BOARD OF PORT COMMISSIONERS AT THEIR PUBLIC MEETING
HELD ON OCTOBER 6, 2015; AND AUTHORIZING THE APPROPRIATION
OF $223,110 TO THE PROJECT, WHICH WILL BE REIMBURSED
BY THE PORT DISTRICT SUBJECT TO THE TERMS OF THE AMENDMENT
WHEREAS, on August 6, 2013, the City Council adopted Resolution No. 2013-
119 entering into an Amended and Restated Memorandum of Understanding ("MOU") related to
the National City Aquatic Center (renamed the Waterfront Adventure Center) between the San
Diego Unified Port District and the City of National City; and
WHEREAS, at the October 27, 2014 Port District Capital Improvement Program
Workshop, the Board of Port Commissioners approved the City's request for an additional
$500,000 to complete the Project; and
WHEREAS, on December 16, 2014, the City Council adopted Resolution No.
2014-175 entering into Amendment No. 1 of the Amended and Restated MOU increasing the
Port District's contribution to the Project by $500,000; and
WHEREAS, on September 15, 2015, the City Council adopted Resolution No.
2015-142, authorizing the Mayor to execute Amendment No. 2 to the Amended and Restated
Memorandum of Understanding wherein the Port District agreed to contribute an additional
$223,110 towards completion of the Project; and
WHEREAS, at a public meeting on October 6, 2015, the Board of Port
Commissioners unanimously approved the additional $223,110, but revised Amendment No. 2
to add conditions to the reimbursement of the $223,110, as follows:
The District shall not be obligated to reimburse City for the last
$223,110 of the maximum $4,633,110 until City has received all of
the following and provided copies to District: (1) unconditional
waivers and releases from all contractors, subcontractors, material
suppliers, equipment lessors, laborers, design professionals, other
persons or entities that provided work for the Project, and any other
person or entity that filed a stop work notice and/or preliminary
notice related to the Project; (2) a Certificate of Occupancy for the
Project; (3) Americans with Disabilities Act (ADA) inspection
approval for the Project; and (4) recordation of Notice of Completion
with the County.
; and
Resolution No. 2015 — 164
Page Two
WHEREAS, staff takes no exception to these conditions added to Amendment
No. 2. and requests that the City Council rescind Resolution 2015-142, which adopted the
original Amendment No. 2, and authorize the Mayor to execute the revised Amendment No. 2;
and
WHEREAS, an appropriation of $223,110 to the Project is necessary, which will
be reimbursed by the Port District subject to the terms of Amendment No. 2.
NOW, THEREFORE, BE IT RESOLVED that the City Council of the City of
National City hereby rescinds Resolution No. 2015-142, adopted on September 15, 2015.
BE IT FURTHER RESOLVED that the City Council authorizes the Mayor to
execute a revised Amendment No. 2 to the Amended and Restated Memorandum of
Understanding related to the National City Aquatic Center (renamed the Waterfront Adventure
Center) between the San Diego Unified Port District and the City of National City wherein the
Port District agrees to contribute an additional $223,110 towards completion of the Project
based on additional language requested and approved by the Board of Port Commissioners at
their public meeting held on October 6, 2015.
BE IT FURTHER RESOLVED that the City Council authorizes the appropriation
of $223,110 to the Project, which will be reimbursed by the Port District subject to the terms of
the Amendment.
PASSED and ADOPTED this 3rd day of November, 2015.
Morrison, Mayor
ATTEST:
ael R. Dalla, City Clerk
APPROVED AS TO FORM:
Clau•ia acitu. Silva
City Attorn: y
Passed and adopted by the Council of the City of National City, California, on
November 3, 2015 by the following vote, to -wit:
Ayes: Councilmembers Cano, Mendivil, Morrison, Rios, Sotelo-Solis.
Nays: None.
Absent: None.
Abstain: None.
AUTHENTICATED BY:
RON MORRISON
Mayor of the City of National City, California
City City
Jerk of the
4)
ational City, California
By:
Deputy
I HEREBY CERTIFY that the above and foregoing is a full, true and correct copy of
RESOLUTION NO. 2015-164 of the City of National City, California, passed and
adopted by the Council of said City on November 3, 2015.
City Clerk of the City of National City, California
By:
Deputy
CITY OF NATIONAL CITY, CALIFORNIA
COUNCIL AGENDA STATEMENT
MEETING DATE: November 3, 2015
AGENDA ITEM NO. 4
TEM TITLE:
A resolution of the City Council of the City of National City, 1) rescinding Resolution 2015-142 authorizing the
Mayor to execute Amendment No. 2 to the Amended and Restated Memorandum of Understanding (MOU)
between the San Diego Unified Port District and the City of National City regarding the National City Aquatic
Center (renamed as the Waterfront Adventure Center) wherein the Port District agrees to contribute an
additional $223,110 towards completion of the Project; 2) authorizing the Mayor to execute a revised
Amendment No. 2 based on additional language requested and approved by the Board of Port Commissioners
at their public meeting held on October 6, 2015; and 3) authorizing the appropriation of $223,110 to the Project,
to be reimbursed by the Port District via the terms of the Amendment.
PREPARED BY: Stephen Manganiello
PHONE: 336-4382
EXPLANATION:
See attached.
DEPARTMENT: Engineering/Public Works
APPROVED BY:
FINANCIAL STATEMENT:
ACCOUNT NO. APPROVED: MIS
Appropriate $223,110 to Account No. 001-409-500-598-3816
APPROVED: Finance
ENVIRONMENTAL REVIEW:
N/A
ORDINANCE: INTRODUCTION:
FINAL ADOPTION:
STAFF RECOMMENDATION:
Adopt the Resolution
BOARD I COMMISSION RECOMMENDATION:
N/A
ATTACHMENTS:
1. Explanation
2. Amendment No. 2
3. Resolution
k0t3 No. rd0%5-�6y
EXPLANATION
On August 13, 2013, the San Diego Unified Port District and the City of National City
entered into an Amended and Restated MOU (on file in the Office of the District Clerk
as Document No. 607444) related to the National City Aquatic Center, which has since
been renamed as the Waterfront Adventure Center.
At the October 27, 2014 Port District Capital Improvement Program Workshop, the
Board of Port Commissioners approved the City's request for an additional $500,000 to
complete the Project. Both parties subsequently executed Amendment No. 1 to the
Amended and Restated MOU (on file in the Office of the District Clerk as Document No.
63880), thereby increasing the Port District's contribution to the Project by $500,000.
On September 15, 2015, per City Council Resolution 2015-142, the City Council
authorized the Mayor to execute Amendment No. 2 to the Amended and Restated
Memorandum of Understanding (MOU) between the San Diego Unified Port District and
the City of National City regarding the National City Aquatic Center wherein the Port
District agrees to contribute an additional $223,110 towards completion of the Project.
On October 6, 2015, Port District staff presented Amendment No. 2 to the Board of Port
Commissioners at their public meeting. The Board unanimously approved the
Amendment with the following conditions:
"The last $223,110 of the maximum $4,633,110 until City has received all of the
following and provided copies to District: (1) unconditional waivers and releases from all
contractors, subcontractors, material suppliers, equipment lessors, laborers, design
professionals, other persons or entities that provided work for the Project, and any other
person or entity that filed a stop work notice and/or preliminary notice related to the
Project; (2) a Certificate of Occupancy for the Project; (3) Americans with Disabilities
Act (ADA) inspection approval for the Project; and (4) recordation of Notice of
Completion with the County."
Staff takes no exception to these conditions. Since this new language has been added
to Amendment No. 2, staff requests that City Council rescind Resolution 2015-142,
which adopted the original Amendment No. 2, and authorize the Mayor to execute the
revised Amendment No. 2. Any exceptions taken to the new language or subsequent
changes directed by City Council would require taking the item back to the Board of Port
Commissioners for their consideration.
Staff also requests the appropriation of $223,110 to the Project, to be reimbursed by the
Port District via the terms of the Amendment.
AMENDMENT NO. 2 TO THE
AMENDED AND RESTATED
MEMORANDUM OF UNDERSTANDING
BETWEEN SAN DIEGO UNIFIED PORT DISTRICT
AND THE CITY OF NATIONAL CITY
REGARDING THE NATIONAL CITY AQUATIC CENTER
This AMENDMENT NO. 2 TO THE AMENDED AND RESTATED
MEMORANDUM OF UNDERSTANDING BETWEEN SAN DIEGO UNIFIED
PORT DISTRICT AND THE CITY OF NATIONAL CITY REGARDING THE
NATIONAL CITY AQUATIC CENTER is made and entered into this day of
, 201, by and between the SAN DIEGO UNIFIED PORT
DISTRICT, a public corporation, hereinafter called "District," and the CITY OF
NATIONAL CITY, a municipal corporation, hereinafter called "City".
WHEREAS, on August 13, 2013, the parties entered into The Amended
And Restated Memorandum Of Understanding Between San Diego Unified Port
District And The City Of National City Regarding The National City Aquatics
Center, on file in the Office of the District Clerk as Document No. 60744, related
to the National City Aquatic Center (Project); and
WHEREAS, the parties executed Amendment No. 1 To The Amended
And Restated Memorandum Of Understanding Between San Diego Unified Port
District And The City Of National City Regarding The National City Aquatics
Center, on file in the Office of the District Clerk as Document No. 63880.
WHEREAS, due to increased costs of the construction, City has
requested District increase the not -to -exceed amount of reimbursement under
this MOU.
NOW THEREFORE, the parties agree that the Amended And Restated
Memorandum Of Understanding Between San Diego Unified Port District And
The City Of National City Regarding The National City Aquatics Center be
amended as follows:
A. Paragraph 2 shall be replaced in its entirety with the following:
2. District agrees to contribute a total amount not to exceed
$4,633,110 to the Project for design and construction as follows:
(a) District shall transfer to City $830,000 to be used towards
design and/or construction costs. City acknowledges that this
obligation of the District has previously been satisfied in full by a
transfer on September 26, 2011.
1
(b) District shall reimburse City for Project construction costs in an
amount not to exceed $3,803,110 in accordance with and
subject to Section 5 herein.
B. Paragraph 3 shall be replaced in its entirety with the following:
3. City agrees to be solely responsible for any Project costs in excess
of the $4,633,110 contribution from the District. City shall not be
relieved of any obligations under this MOU due to increased
expenses or cost overruns.
C. Paragraph 5 shall be amended by adding new subparagraph (g) as follows:
g.
In addition to the other limitations on reimbursement herein, the
District shall not be obligated to reimburse City for the last
$223,110 of the maximum $4,633,110 until City has received all of
the following and provided copies to District: (1) unconditional
waivers and releases from all contractors, subcontractors, material
suppliers, equipment lessors, laborers, design professionals, other
persons or entities that provided work for the Project, and any other
person or entity that filed a stop work notice and/or preliminary
notice related to the Project; (2) a Certificate of Occupancy for the
Project; (3) Americans with Disabilities Act (ADA) inspection
approval for the Project; and (4) recordation of Notice of
Completion with the County.
D. All remaining terms shall remain in full force and effect.
SIGNATURE PAGE FOLLOWS
2
IN WITNESS WHEREOF, parties hereto have executed this Amendment No. 2
To Amended And Restated Memorandum Of Understanding Between San Diego
Unified Port District And The City Of National City Regarding The National City
Aquatics Center as of the day and the year first above written.
APPROVED AS TO FORM AND LEGALITY SAN DIEGO UNIFIED PORT DISTRICT
By By
Deputy General Counsel Karen G. Porteous
EVP, Administration
APPROVED AS TO FORM: CITY OF NATIONAL CITY
By By
Claudia G. Silva
City Attorney
3
Ron Morrison
Mayor
RESOLUTION NO. 2015 —
RESOLUTION OF THE CITY COUNCIL OF THE CITY OF NATIONAL CITY
RESCINDING RESOLUTION 2015-142 APPROVING AMENDMENT NO. 2
TO THE AMENDED AND RESTATED MEMORANDUM OF UNDERSTANDING
BETWEEN THE SAN DIEGO UNIFIED PORT DISTRICT AND THE CITY OF
NATIONAL CITY REGARDING THE NATIONAL CITY AQUATIC CENTER
(RENAMED AS THE WATERFRONT ADVENTURE CENTER); AUTHORIZING
THE MAYOR TO EXECUTE A REVISED AMENDMENT NO. 2 TO
THE AMENDED AND RESTATED MEMORANDUM OF UNDERSTANDING
WHEREIN THE PORT DISTRICT AGREES TO CONTRIBUTE AN
ADDITIONAL $223,110 TOWARDS COMPLETION OF THE PROJECT,
BASED ON ADDITIONAL LANGUAGE REQUESTED AND APPROVED
BY THE BOARD OF PORT COMMISSIONERS AT THEIR PUBLIC MEETING
HELD ON OCTOBER 6, 2015; AND AUTHORIZING THE APPROPRIATION
OF $223,110 TO THE PROJECT, WHICH WILL BE REIMBURSED
BY THE PORT DISTRICT SUBJECT TO THE TERMS OF THE AMENDMENT
WHEREAS, on August 6, 2013, the City Council adopted Resolution No. 2013-
119 entering into an Amended and Restated Memorandum of Understanding ("MOU") related to
the National City Aquatic Center (renamed the Waterfront Adventure Center) between the San
Diego Unified Port District and the City of National City; and
WHEREAS, at the October 27, 2014 Port District Capital Improvement Program
Workshop, the Board of Port Commissioners approved the City's request for an additional
$500,000 to complete the Project; and
WHEREAS, on December 16, 2014, the City Council adopted Resolution No.
2014-175 entering into Amendment No. 1 of the Amended and Restated MOU increasing the
Port District's contribution to the Project by $500,000; and
WHEREAS, on September 15, 2015, the City Council adopted Resolution No.
2015-142, authorizing the Mayor to execute Amendment No. 2 to the Amended and Restated
Memorandum of Understanding wherein the Port District agreed to contribute an additional
$223,110 towards completion of the Project; and
WHEREAS, at a public meeting on October 6, 2015, the Board of Port
Commissioners unanimously approved the additional $223,110, but revised Amendment No. 2
to add conditions to the reimbursement of the $223,110, as follows:
The District shall not be obligated to reimburse City for the last
$223,110 of the maximum $4,633,110 until City has received all of
the following and provided copies to District: (1) unconditional
waivers and releases from all contractors, subcontractors, material
suppliers, equipment lessors, laborers, design professionals, other
persons or entities that provided work for the Project, and any other
person or entity that filed a stop work notice and/or preliminary
notice related to the Project; (2) a Certificate of Occupancy for the
Project; (3) Americans with Disabilities Act (ADA) inspection
approval for the Project; and (4) recordation of Notice of Completion
with the County.
; and
Resolution No. 2015 —
Page Two
WHEREAS, staff takes no exception to these conditions added to Amendment
No. 2. and requests that the City Council rescind Resolution 2015-142, which adopted the
original Amendment No. 2, and authorize the Mayor to execute the revised Amendment No. 2;
and
WHEREAS, an appropriation of $223,110 to the Project is necessary, which will
be reimbursed by the Port District subject to the terms of Amendment No. 2.
NOW, THEREFORE, BE IT RESOLVED that the City Council of the City of
National City hereby rescinds Resolution No. 2015-142, adopted on September 15, 2015.
BE IT FURTHER RESOLVED that the City Council authorizes the Mayor to
execute a revised Amendment No. 2 to the Amended and Restated Memorandum of
Understanding related to the National City Aquatic Center (renamed the Waterfront Adventure
Center) between the San Diego Unified Port District and the City of National City wherein the
Port District agrees to contribute an additional $223,110 towards completion of the Project
based on additional language requested and approved by the Board of Port Commissioners at
their public meeting held on October 6, 2015.
BE IT FURTHER RESOLVED that the City Council authorizes the appropriation
of $223,110 to the Project, which will be reimbursed by the Port District subject to the terms of
the Amendment.
PASSED and ADOPTED this 3rd day of November, 2015.
Ron Morrison, Mayor
ATTEST:
Michael R. Dalla, City Clerk
APPROVED AS TO FORM:
Claudia Gacitua Silva
City Attorney