HomeMy WebLinkAbout2017 CON Fordyce Construction - Las Palmas Pool / Camacho Gym / Fire Station 31 improvement Project SP 16-02 - Notice of CompletionPLEASE COMPLETE THIS INFORMATION
RECORDING REQUESTED BY:
City Engineer
City of National City
1243 National City Blvd.
National City, CA 91950
AND WHEN RECORDED MAIL TO:
City Engineer
City of National City
1243 National City Blvd.
National City, CA 91950
DOC# 2017-0199977
III I III I II III III 111111 III II 11
May 04, 2017 10:22 AM
OFFICIAL RECORDS
Ernest J. Dronenburg, Jr.,
SAN DIEGO COUNTY RECORDER
FEES: $0.00
PAGES: 2
THIS SPACE FOR RECORDER'S USE ONLY
(Note: This document is recorded on behalf of the City of National City, a municipal corporation, and is exempt
from Recorder's fees pursuant to Government Code Section 27383)
NOTICE OF COMPLETION:
LAS PALMAS PARK MUNICIPAL POOL, CAMACHO GYM AND FIRE STATION 31
IMPROVEMENTS PROJECT, CIP NO. 16-02
THIS PAGE ADDED TO PROVIDE ADEQUATE SPACE FOR RECORDING INFORMATION
(Additional recording fee applies)
RECORDING REQUESTED BY
WHEN RECORDED MAIL TO:
NAME: CITY OF NATIONAL CITY
ADDRESS: 243 NATIONAL CITY BOULEVARD
NATIONAL CITY, CA 91950
NOTICE OF COMPLETION
CALIFORNIA CIVIL CODE SECTION 3093
NOTICE IS HEREBY GIVEN of the completion on March 28, 2017 of Las Palmas Park Municipal
Pool, Camacho Gym and Fire Station 31 Improvements Project, CIP No. 16-02.
Work of improvement or portion of work of improvement under construction or alteration.
1800 E. 22nd St. National City CA 91950
2333 Euclid Ave. National City CA 91950
Street Address City State Zip Code
The undersigned owns the following interest or estate in said property:
Owner in fee
Nature of the interest or estate of owner (mortgagor, lessee, etc.)
Said work of improvement was performed on the property pursuant to a contract with
Fordyce Construction, Inc.
Name of Original Contractor
The following work and material were supplied:
Labor Provided: General Laborer. Materials: Lumber, Paint, Stucco, Drainage, Cabinets, Tile,
Roofing, Piping, Electrical, Mechanical. Equipment: Excavation Equipment.
General statement of kind of labor, services, equipment or materials
The names and addresses of co -owners are:
Dated: March 28, 2017;
N/A
tenants in common, or other owners
Signature of Owner
City of National City, 1243 National City Blvd., National City, CA 91950
I, the undersigned, say: I have read the foregoing Notice of Completion and know the contents
thereof; the same is true of my own knowledge. I declare under penalty of perjury that the forgoing
is true and correct.
Executed on M 8, 2017 at, National City, California.
Signature:
RON MORRISON, MAYOR
Noc16-02
RESOLUTION NO. 2017 — 70
RESOLUTION OF THE CITY COUNCIL OF THE CITY OF NATIONAL CITY
ACCEPTING THE WORK PERFORMED BY FORDYCE CONSTRUCTION, INC.,
FOR THE LAS PALMAS PARK MUNICIPAL POOL/CAMACHO GYM/ FIRE
STATION 31 IMPROVEMENTS PROJECT, APPROVING THE FINAL
CONTRACT AMOUNT OF $479,774.07, RATIFYING THE RELEASE
OF RETENTION IN THE AMOUNT OF $23,988.70, AND RATIFYING
THE FILING OF THE NOTICE OF COMPLETION FOR THE PROJECT
WHEREAS, the Engineering Department is satisfied that all work required to be
performed by Fordyce Construction, Inc., for the Las Palmas Park Municipal Pool/Camacho
Gym/Fire Station 31 Improvements Project (CIP No. 16-02; 2) has been completed.
NOW, THEREFORE, BE IT RESOLVED by the City Council of the City of
National City that the work performed by Fordyce Construction, Inc., for the Las Palmas Park
Municipal Pool/Camacho Gym/Fire Station 31 Improvements Project is accepted.
BE IT FURTHER RESOLVED that the City Council hereby ratifies the filing
Notice of Completion filed with the San Diego County Clerk on May 4, 2017, and the release of
retention in the amount of $23,988.70.
PASSED and ADOPTED this 16th day of May, 2Q17
on Morrison, Mayor
ATTEST:jai
Q
Mic ael R. Dalla
ity
Clerk
APPROVED AS TO FORM:
(ity,...1 440
.ram/i��1
A i XI- rris-Jones
City Attorney
Passed and adopted by the Council of the City of National City, California, on May 16,
2017 by the following vote, to -wit:
Ayes: Councilmembers Cano, Mendivil, Morrison, Rios, Sotelo-Solis.
Nays: None.
Absent: None.
Abstain: None.
AUTHENTICATED BY: RON MORRISON
Mayor of the City of National City, California
/l).„4,,c14) i
City Clerk of the City of National City, California
By:
Deputy
I HEREBY CERTIFY that the above and foregoing is a full, true and correct copy of
RESOLUTION NO. 2017-70 of the City of National City, California, passed and adopted
by the Council of said City on May 16, 2017.
City Clerk of the City of National City, California
By:
Deputy
CITY OF NATIONAL CITY, CALIFORNIA
COUNCIL AGENDA STATEMENT
(Zane /l
MEETING DATE: May 16, 2017
AGENDA ITEM NO. 6
ITEM TITLE:
Resolution of the City Council of the City of National City: 1) accepting the work performed by Fordyce
Construction, Inc. for the Las Palmas Park Municipal Pool/Camacho Gym/ Fire Station 31
Improvements Project, CIP No. 16-02; 2) approving the final contract amount of $479,774.07; 3)
ratifying the release of retention in the amount of $23,988.70; and 4) ratifying the filing of the Notice of
Completion for the project.
PREPARED BY: Jose Lopez, Junior Engineer - Civil
PHONE: 619-336-4312
EXPLANATION:
See attached.
DEPARTMENT: Engineering/Public Works
APPROVED BY:
,•;/(2
-INANCIAL STATEMENT:
,ACCOUNT NO.
N/A
ENVIRONMENTAL REVIEW:
N/A
ORDINANCE: INTRODUCTION:
FINAL ADOPTION:
APPROVED:
APPROVED:
Finance
MIS
STAFF RECOMMENDATION:
Adopt Resolution accepting the work performed by Fordyce Construction, Inc. for the Las Palmas Park Municipal
Pool/Camacho Gym/ Fire Station 31 Improvements Project, CIP No. 16-02 and approving the final contract
amount of $479,774.07.
BOARD / COMMISSION RECOMMENDATION:
N/A
ATTACHMENTS:
1. Explanation
2. Notice of Completion
3. Final Contract Balance Report
4. Resolution
p,tcs0j31%0W O. ao'11-110
EXPLANATION
The project represented Phase I of refurbishments to the National City Municipal Pool,
Camacho Recreation Center and Fire Station 31.
On February 4, 2016, the bid solicitation was posted on PlanetBids, a free public electronic
bidding system for contractors. On February 8, 2016 and February 15, 2016, the bid
solicitation was advertised in local newspapers.
On March 1, 2016, three (3) bids were received electronically on PlanetBids by the
1:00 p.m. deadline. Bid results were available immediately after the 1:00 p.m. deadline.
Fordyce Construction, Inc. was the apparent lowest bidder with a total base bid plus
additive bid amount of $551,943.50, as the basis of bid award. Upon review of all
documents submitted and reference checks, Fordyce Construction, Inc.'s bid was found to
be responsive, and they were the lowest responsible bidder qualified to perform the work as
described in the project specifications.
On March 15, 2016, the City Council adopted Resolution No. 2016-40 awarding the contract
to Fordyce Construction, Inc. in the amount of $325,285.00 which included a combined
base bid amount of $261,275.00 and $64,010.00 in additive bids.
The Notice to Proceed with construction was issued on May 9, 2016, with a construction
start date of May 10, 2016.
On October 4, 2016 City Council adopted Resolution No. 2016-155 increasing the contract
with Fordyce Construction, Inc. in the not -to exceed amount of $120,000.00, to provide
additional repairs and facility improvements to address unforeseen conditions discovered
during construction. This amount was above and beyond the previously authorized 15%
contingency, resulting in a total not -to -exceed contract amount of $494,077.75.
Most of the funding requested was needed to address environmental compliance issues
involving mold at Fire Station 31 and hazardous building materials contained in the
bungalows located in the Pepper Park parking lot. As part of the FY 2017 budget, City
Council appropriated $500,000 in the Environmental Compliance Contract Services
expenditure account from the General Fund. This account was used to pay Fordyce
Construction, Inc. to remediate the environmental compliance issues identified during
construction.
The change orders issued for this project are detailed in the Final Contract Balance Report
(see attached). The change orders increased the contract by $171,135.00, while line item
adjustments decreased the contract by $16,645.93 for a final contract balance of
$479,774.07.
As a result of satisfactory completion of the project, staff recommends that City Council: 1)
accept the work of Fordyce Construction, Inc. for the Las Palmas Park Municipal
Pool/Camacho Gym/Fire Station 31 Improvements Project, CIP No. 16-02; 2) approve the
final contract amount of $479,774.07; 3) ratify the release of retention in the amount of
$23,988.70; and 4) ratify the filing of the Notice of Completion for the project.
The Notice of Completion was filed with the San Diego County Recorder's Office on May 4,
2017.
PLEASE COMPLETE THIS INFORMATION
RECORDING REQUESTED BY:
City Engineer
City of National City
1243 National City Blvd.
National City, CA 91950
$LND WHEN RECORDED MAIL TO:
City Engineer
City of National City
1243 National City Blvd.
National City, CA 91950
DOC# 2017-0199977
IIIIII IIII I1II III IIII IIII I IIIII IIIII IIII IIIII III I IIII IIII II
May 04, 2017 10:22 AM
OFFICIAL RECORDS
Ernest J. Dronenburg, Jr.,
SAN DIEGO COUNTY RECORDER
FEES: $0.00
PAGES: 2
THIS SPACE FOR RECORDER'S USE ONLY
(Note: This document is recorded on behalf of the City of National City, a municipal corporation, and is exempt
from Recorder's fees pursuant to Government Code Section 27383)
NOTICE OF COMPLETION:
LAS PALMAS PARK MUNICIPAL POOL, CAMACHO GYM AND FIRE STATION 31
IMPROVEMENTS PROJECT, CIP NO. 16-02
THIS PAGE ADDED TO PROVIDE ADEQUATE SPACE FOR RECORDING INFORMATION
(Additional recording fee applies)
-1-
RECORDING REQUESTED BY
WHEN RECORDED MAIL TO:
NAME: CITY OF NATIONAL CITY
ADDRESS: 243 NATIONAL CITY BOULEVARD
NATIONAL CITY, CA 91950
NOTICE OF COMPLETION
CALIFORNIA CIVIL CODE SECTION 3093
NOTICE IS HEREBY GIVEN of the completion on March 28, 2017 of Las Palmas Park Municipal
Pool, Camacho Gym and Fire Station 31 Improvements Project, CIP No. 16-02.
Work of improvement or portion of work of improvement under construction or alteration.
1800 E. 22nd St. National City CA 91950
2333 Euclid Ave. National City CA 91950
Street Address City State Zip Code
The undersigned owns the following interest or estate in said property:
Owner in fee
Nature of the interest or estate of owner (mortgagor, lessee, etc.)
Said work of improvement was performed on the property pursuant to a contract with
Fordyce Construction, Inc.
Name of Original Contractor
The following work and material were supplied:
Labor Provided: General Laborer. Materials: Lumber, Paint, Stucco, Drainage, Cabinets, Tile,
Roofing, Piping, Electrical, Mechanical. Equipment: Excavation Equipment.
General statement of kind of labor, services, equipment or materials
The names and addresses of co -owners are:
Dated: March 28, 2017;
N/A
tenants in common, or other owners
Signature of Owner
City of National City, 1243 National City Blvd., National City, CA 91950
I, the undersigned, say: I have read the foregoing Notice of Completion and know the contents
thereof; the same is true of my own knowledge. I declare under penalty of perjury that the forgoing
is true and correct.
Executed on M8, 2017 at, National City, California.
Signature:
RON MORRISON, MAYOR
Noc16-02
-2-
FINAL CONTRACT BALANCE
DATE: March 30, 2017
PROJECT: Las Palmas Park Municipal Pool/Camacho Gym/Fire Station 31 Improvements Project
FY 16
CIP No. 16-02
TO:
Fordyce Construction, Inc.
9932 Prospect Avenue #138
Santee, CA 92071
ORIGINAL CONTRACT AMOUNT:
START DATE:
COMPLETION DATE:
ORIGINAL CONTRACT LENGTH:
EXTENTION OF WORK DAYS:
TOTAL CONTRACT TIME:
FINAL CONTRACT AMOUNT:
DESCRIPTION:
$325,285.00
May 10, 2016
March 27, 2017
40 Working Days
180 Working Days
220 Working Days
$479,774.07
The Final Contract Balance reports final line item amounts and summarizes all change orders to produce
a final contract amount.
CHANGE ORDERS AND LINE ITEM ADJUSTMENTS:
Change Order #1 provided for cabinetry work at the council chambers. This Change Order total amount
is $ 44,255.00.
Change Order #2 was issued to provide a mold investigation at Fire Station 31 and added soffit repairs at
the Las Palmas Pool office. This Change Order total amount was $ 7,459.
Change Order #3 authorized the contractor to provide an additional sink cabinet and replacement rain
gutters at Fire Station 31 and additional framing and stucco repair that were not anticipated during bid.
This Change Order total amount was $ 13,061.00.
Change Order #4 addressed the removal and replacement of skylights at Camacho Gym, replacement of
gas piping in the pool chemical room and new drainage around the Gym. This Change Order total
amount was $ 19,028.00
Changer Order #5 provided for installation of volleyball sleeves in the gym floor, a hazardous building
material survey at the Pepper Park bungalows, a sewer cleanout cover in the parking lot at Fire Station
31 and added electrical work at Las Palmas Pool and Fire Station 31. This Change Order total amount
was $ 15,488.00.
-3-
FINAL CONTRACT BALANCE
Las Palmas Pool, Camacho Gym and Fire Station 31
Specification No. 16-02
Change Order #6 provided for a stucco repair and paint to the exterior planter at Fire Station 31. This
Change Order total amount is $ 2.194.00.
Change Order #7 directed the Contractor to remove and properly dispose of lead and asbestos from the
Pepper Park bungalows prior to demolition. This Change Order total amount was $ 50,835.00.
Change Order #8 directed the contractor to provide additional kitchen cabinets and tile work in the
shower at Fire Station 31. This Change Order total amount was $ 13,367.00.
Change Order #9 was issued to accommodate a change to the additional cabinetry at the council
chambers. This Change Order total amount was $ 5,448.00.
All Change Orders listed above increased the total contract amount $171,135.00.
Line item adjustments per the FINAL BILLING STATEMENT resulted in a total decrease of $16,645.93.
CONTRACT ADJUSTMENT:
As a result of the above change orders, the contract price is adjusted as follows:
1. The final contract price is adjusted to $ 479,774.07.
2. As a result of the satisfactory completion of said project, a retention amount of $ 23,988.70 is
set for invoice processing and payment upon the receipt of signatures and City Council's
ratification of this agreement and the Notice of Completion.
This document and its purpose to balance payment shall be considered full compensation for furnishing
and installing the materials, labor, tools and equipment, profit, overhead, and all incidentals for
performing the work described above. EC Constructors will not be entitled to damages or additional
payment for delays as described in the 2012 edition of the Standard Specifications for Public Works
Construction, Section 6-6.3, for performing the work as described above.
-4-
RESOLUTION NO. 2017 —
RESOLUTION OF THE CITY COUNCIL OF THE CITY OF NATIONAL CITY
ACCEPTING THE WORK PERFORMED BY FORDYCE CONSTRUCTION, INC.,
FOR THE LAS PALMAS PARK MUNICIPAL POOL/CAMACHO GYM/ FIRE
STATION 31 IMPROVEMENTS PROJECT, APPROVING THE FINAL
CONTRACT AMOUNT OF $479,774.07, RATIFYING THE RELEASE
OF RETENTION IN THE AMOUNT OF $23,988.70, AND RATIFYING
THE FILING OF THE NOTICE OF COMPLETION FOR THE PROJECT
WHEREAS, the Engineering Department is satisfied that all work required to be
performed by Fordyce Construction, Inc., for the Las Palmas Park Municipal Pool/Camacho
Gym/Fire Station 31 Improvements Project (CIP No. 16-02; 2) has been completed.
NOW, THEREFORE, BE IT RESOLVED by the City Council of the City of
National City that the work performed by Fordyce Construction, Inc., for the Las Palmas Park
Municipal Pool/Camacho Gym/Fire Station 31 Improvements Project is accepted.
BE IT FURTHER RESOLVED that the City Council hereby ratifies the filing
Notice of Completion filed with the San Diego County Clerk on May 4, 2017, and the release of
retention in the amount of $23,988.70.
PASSED and ADOPTED this 16`h day of May, 2017.
ATTEST:
Michael R. Dalla, City Clerk
APPROVED AS TO FORM:
Angil P. Morris -Jones
City Attorney
Ron Morrison, Mayor
CITY OF NATIONAL CITY
Office of the City Clerk
1243 National City Blvd., National City, California 91950-4397
619-336-4228
Michael R. Dalla, CMC - City Clerk
FORDYCE CONSTRUCTION, INC.
Notice of Completion
Las Palmas Park Municipal Pool, Camacho Gym and Fire Station 31
Improvements Project (CIP No. 16-02)
Judy H. (Engineering/Public Works) Forwarded
Copy of Notice of Completion to Fordyce Construction, Inc..