18th St. Pedestrian and Bicycle Enhancements Project CHANGE ORDER NO. 1
CIP No: 16-10 October 12, 2017
Contractor: Tri-Group Construction & Development, Inc.
Reason/Purpose for this Change Order:
To remove and replace an existing catch basin deck that is aged and in need of repair.
The City of National City and Contractor agree to the following change to the original Contract:
The contractor has been direct to sawcut and remove the existing catch basin deck on the south west corner
of 18th and N. Ave, use protective BMP's as needed, haul off and properly dispose of all waste and
reconstruct using a radiused angle and vertical bars per SDRSD D-12, dowel into the existing concrete and
place rebar, and include all other materials and work needed including traffic control to complete
reconstruction of the catch basin deck. The work described above and any other work or related costs has
been authorized at the agreed lump sum price listed below.
Original Contract Amount... $ 915,818.00
Net change by previously authorized Change Orders
Subtotal 915,818.00
Amount of this change order 7,988.00
New contract amount $ 923,806.00
Wo g days added: 0 Working days subtracted: 0 Percent change in Contract to date 0.87%
Sulied by:
t anage
ved by:
r
City 2hgineer
Date
City Project Manager Date
Date City Manager, required for Change Orders s$24,999 Date
By signing this Change Order the Contractor confirms that he/she is completely familiar with its terms and conditions and has fairly
negotiated its price, terms and conditions. If this Change Order is approved, Contractor will provide all of the equipment, materials and
labor necessary to provide a complete work as described above at that the price stated herein. Additionally, Contractor confirms that the
price is fair and complete and represents all costs associated with the work, including but not limited to all equipment, materials, labor,
supervision, overhead, fees, bonds, insurance, profit, etc. and that there will be no further compensation. All of the terms and conditions
of the original contract documents are incorporated herein. (2 originals: 1 for City Clerk, 1 for Contractor)
Accepted and agreed to by (Contractor's name):
Name:
/4 \ /" .“ CV/2 (Oa
Date
Note to Contractor: If you do not agree with this Change Order you may be directed to proceed with this work under the terms of the
contract and you may proceed under protest. You must comply with the contract requirements of submitting a written protest to protect
your claim.
Originals: City Clerk, Contractor cc: Engineering project file, Project Manager
1243 National City Boulevard, National City, CA 91950 Telephone (619) 336-4380
TRI-GROUP
Construction and Development, Inc.
Lic. No. 792159
August 29, 2017
Mr. Sean Gill
City of National City
1243 national City Blvd
National City CA 91950
Reference: 18th Street Pedestrian & Bicycle Enhancements
Subject: REVISED Cost Proposal for the NW corner of 18th & N Inlet
Tri-Group proposes to :
Set-up Traffic Control at N & 18th
Protect Inlet from any pollutant during construction with BMP's.
Saw -cut concrete
Demo top of inlet
Remove, haul, dispose of concrete with rebar debris
Dowel rebar into existing
Place rebar for the new top of Inlet
Form for the new top of the inlet
Pour new Top of Inlet
Apply curing compound
Strip forms
Cleanup
Remove BMP's
Remove Trafiic Control
For a Lump Sum of $7,988 and 3 days added to contract.
Cost Break Down;
Labor $4,984.00 (laborers 56 hrs at $71, Operator 8 hr at $98 Driver 8 hrs at $28)
Labor markup $ WAIVED
Material: $1,525 (concrete CY $675, Forms $250, Rebar $350 Cure $50 Dowels $100 Other $100)
Material Markup $ WAIVED
Equipment $1,716 less $316 discount = $1,400 (work truck 28 hrs, Breaker 8 hrs, d Truck 8 hrs)
Equipm Markup $ WAIVED
Bond $ 79
Sincerely
Hani Assi
9580 Black Mountain Rd, Suite L • San Diego, CA 92126 • Offiee` (858) 689-0058 • Fax (858) 689-1594
\\
CALIFORNIA
NATIO CITY
INCORPORATED
18th St. Pedestrian and Bicycle Enhancements Project
CIP No: 16-10
Contractor: Tri-Group Construction & Development, Inc.
Reason/Purpose for this Change Order:
To install 23 traffic detector loops on 18th St. at the intersections of Newell and Euclid not previously show on
the plans.
The City of National City and Contractor agree to the following change to the original Contract:
The contractor has been directed to install 23 additional traffic detection loops on 18th St. at the intersections
of Newell and Euclid per the email dated 9/19/17. All work was not previously shown on the plans and is
needed due to the grind and overlay proposed to the existing asphalt on this project. All work and related
costs has been authorized at the agreed lump sum price listed below.
Original Contract Amount $ 915,818.00
Net change by previously authorized Change Orders
Subtotal
Amount of this change order
New contract amount
Wor ' ; days added: 5
Sub itt-. by:
7,988.00
923,806.00
15,089.00
$ 938,895.00
rking days subtracted: 0 Percent change in Contract to date 2.52%
//21k
Cingineer , Date City Manager, required for Change Orders>$24,999 Date
By signing this Change Order the Contractor confirms that he/she is completely familiar with its terms and conditions and has fairly
negotiated its price, terms and conditions. If this Change Order is approved, Contractor will provide all of the equipment, materials and
labor necessary to provide a complete work as described above at that the price stated herein. Additionally, Contractor confirms that the
price is fair and complete and represents all costs associated with the work, including but not limited to all equipment, materials, labor,
supervision, overhead, fees, bonds, insurance, profit, etc. and that there will be no further compensation. All of the terms and conditions
of the original contract documents are incorporated herein. (2 originals: 1 for City Clerk, 1 for Contractor)
Accepted and agreed to by (Contractor's name):
City Project Manager
Date
cs
Name: / /_ / Date —
Note to Contractor: If you do not agree with this Change Order you may be directed to proceed with this work under the terms of the
contract and you may proceed under protest. You must comply with the contract requirements of submitting a written protest to protect
your claim.
CHANGE ORDER NO. 2
October 12, 2017
P b� t
Originals: City Clerk, Contractor
/12/t3
cc: Engineering project file, Project Manager
%/aq/2g
1243 National City Boulevard, National City, CA 91950 Telephone (619) 336-4380
TRI-GROUP
Construction and Development, Inc.
Lic. No. 792159
October 10, 201 i
Mr. Sean Gill
City of National city
1243 National City Blvd
National City CA 91950
Re: 18th Street Pedestrian & Bicycle Enhancements No. 16-10
Subject: Detection Loops Cost Proposal
Tri-Group proposes to furnish and install 23 DETECTION LOOPS with traffic control at a Lump Sum price of
$95,089.00
Please add 5 working days to the contract (about 5 loops a day) .
Cost Break Down:
A) Subcontract Work (see attached) $9,200.00
B) Subcontractor's markup 5% $ 460.00
C) Labor (Traffic Control: 1 Laborer Group 4 40 hrs at $72.63 / hr) .... $2,905.00
D) Labor Markup 20% $ 581.00
E) Equipment.: (TC Truck 40 hr at $27, TC devices 40 hrs at $12 / hr) $1,560.00
F) Equipment Markup 15% $ 234.00
G) Bond 1 % $ 149.00
Conditions:
1) Valid until 10/20/2017
2) Extra Charges may apply for additional material
3) Based on Prevailing wages
4) Work to be performed in one move -In. Additional move -ins at $300 / move -in
5) Excludes Night work, Permit Fees and plans, Surveying, and weekend work
6) Excludes a new TC plan and permit. If needed, add $1,200 for North County TC to generate one.
9580 Black Mountain Rd, Suite L • San Diego, CA 92126 • Office (858) 689-0058 • Fax (858) 689-1594
ELE�RfC
National City 18th Street
Perry Electric Job #792 RFC #1 Loops
Company: Tri Group 9/20/2017
9580 Black Mountain Rd Suite L
Address: San Diego CA 92126
Phone:
ATTN:
Qty Item Description Ext
23 Vehicle Detection Loops
Exclusions
All original Contract exclusions Apply
Valid for thirty days from date of quote
Extra charges may apply for additional material
Contractors License 9 747931(C-10)
Per Cty Request @ $400 each
Excludes Night or Weekend Work, Traffic Control
Permits or Plans, Stubouts.
$ 9,200.00
Grand Total $ 9,200.00
PO Box 710130 Santee, CA 92072 (619) 449-0045 / (619) 449.0511 fax
CALIFORNIA
NATIONAL airy
i ai
INCORPORATED
18th St. Pedestrian and Bicycle Enhancements Project
CIP No: 16-10
Contractor: Tri-Group Construction & Development, Inc.
Reason/Purpose for this Change Order:
Pay SDSG&E service point fee for St. lights at 18th and Lanoitan.
CHANGE ORDER NO. 3
November 3, 2017
The City of National City and Contractor agree to the following change to the original Contract:
The contractor has been directed to pay the SDG&E service point permit fees directly to SDG&E in order to
expedite underground inspection. The contractor shall be reimbursed for those fees at the agreed lump sum
price listed below.
Original Contract Amount $ 915,818.00
Net change by previously authorized Change Orders
Subtotal
23,077.00
938,895.00
Amount of this change order 991.00
New contract amount
Working days added: 10 Working days subtracted: 0
Sub :: - d by:
Date
•
Ci ngineer / Date City Manager, required for Change Orders>$24,999 Date
By signing this Change Order the Contractor confirms that he/she is completely familiar with its terms and conditions and has fairly
negotiated its price, terms and conditions. If this Change Order is approved, Contractor will provide all of the equipment, materials and
labor necessary to provide a complete work as described above at that the price stated herein. Additionally, Contractor confirms that the
price is fair and complete and represents all costs associated with the work, including but not limited to all equipment, materials, labor,
supervision, overhead, fees, bonds, insurance, profit, etc. and that there will be no further compensation. All of the terms and conditions
of the original contract documents are incorporated herein. (2 originals: 1 for City Clerk, 1 for Contractor)
Accepted and agreed to by (Contractor's name):
Q"tr
Percent change in Contract to date 2.63%
City Project Manager
939,886.00
Date
Name:
f- 12_—t v
Date
Note to Contractor: If you do not agree with this Change Order you may be directed to proceed with this work under the terms of the
contract and you may proceed under protest. You must comply with the contract requirements of submitting a written protest to protect
your claim.
Originals: City Clerk, Contractor
cc: Engineering project file, Project Manager
1243 National City Boulevard, National City, CA 91950 Telephone (619) 336-4380
56819
TRI GROUP CONSTRUCTION
AND DEVELOPMENT, INC.
9550 Black Mountain Rd. Suite L
San Diego, CA 92126
555-689-0055
UNION BANK OF CALIFORNIA, N.A.
18680 BERNARDO CENTER DR
SAN DIEGO. CA 92128
16-49/1220
10/19/2017
PAY TO THE San Diego Gas & Electric "991.00
ORDER OF $
Nine Hundred Ninety -One and 00/100
San Diego Gas & Electric
PO Box 25111
Santa Ana, CA 92799
18th
00 568 L90 L 2 20001,961:00 2 L 26968 31°
TRI GROUP CONSTRUCTION
AND DEVELOPMENT, INC.
San Diego Gas & Electric
New UG SVC PT
10/19/2017
DOLLA
9R_1<
UBOC Checking 18th 991.00
TRI GROUP CONSTRUCTION
AND DJan uiego C�TasN
& Electric
UBOC Checking 18th
New UG SVC PT
10/19/2017
5681
991.00
991 00
0
�,' � t.
o lam_ -T
CITY OF NATIONAL CITY
Office of the City Clerk
1243 National City Blvd., National City, California 91950-4397
619-336-4228
Michael R. Dalla, CMC - City Clerk
TRI-GROUP CONSTRUCTION & DEVELOPMENT, INC.
18TH ST. PEDESTRIAN AND BICYCLE ENHANCEMENTS PROJECT
Change Orders #1 through #3, CIP No. 16-10
Judy Hernandez (Engineering/Public Works) Forwarded