18th St. Pedestrian and Bicycle Enhancements Project CHANGE ORDER NO. 4
CIP No: 16-10 February 15, 2018
Contractor: Tri-Group Construction & Development, Inc.
Reason/Purpose for this Change Order:
Install electrical conduit for LED crossing at 18th and Lanoitan and remove and replace miscellaneous traffic
signal pull boxes. Also install 3" electrical conduit for SDG&E service.
The City of National City and Contractor agree to the following change to the original Contract:
The contractor has been directed to install the LED pedestrian crossing per the alternate bid item at 18th and
Lanoitan. The conduit work was not included with the alternate bid item and has been installed as extra work.
There were existing damaged traffic signal pull boxes at 18th and L and 18th and Newell. The contractor was
directed to remove and replace those pull boxes. The contractor was also directed to install a 3" conduit for
the SDG&E service. All work was performed on a T&M basis and this change order includes all labor,
materials and equipment necessary to complete the work as described.
Original Contract Amount $ 915,818.00
Net change by previously authorized Change Orders 24,068.00
Subtotal 939,886.00
Amount of this change order 5,345.31
New contract amount $ 945,231.31
Wor
Sub
days added: 5
Y.
Manager
ved by:
Cit ngineer
Working days subtracted: 0 Percent change in Contract to date 3.21 %
Date City Project Manager Date
/26A 8'
Date
City Manager, required for Change Orders>$24,999 Date
By signing this Change Order the Contractor confirms that he/she is completely familiar with its terms and conditions and has fairly
negotiated its price, terms and conditions. If this Change Order is approved, Contractor will provide all of the equipment, materials and
labor necessary to provide a complete work as described above at that the price stated herein. Additionally, Contractor confirms that the
price is fair and complete and represents all costs associated with the work, including but not limited to all equipment. materials, labor,
supervision, overhead, fees, bonds, insurance, profit, etc. and that there will be no further compensation. All of the terms and conditions
of the original contract documents are incorporated herein. (2 originals: 1 for City Clerk, 1 for Contractor)
Accepted and agreed to by (Contract is name):
Name:
Date
Note to Contractor: If you do not agree with this Change Order you may be directed to proceed with this work under the terms of the
contract and you may proceed under protest. You must comply with the contract requirements of submitting a written protest to protect
your claim.
Originals: City Clerk, Contractor cc: Engineering project file, Project Manager
1243 National City Boulevard, National City, CA 91950 Telephone (619) 336-4380
4— CALIFORNIA -e
NATIONAL L airy
� aJJ 1
(._ INCORPORATED
18th St. Pedestrian and Bicycle Enhancements Project
CIP No: 16-10
Contractor: Tri-Group Construction & Development, Inc.
Reason/Purpose for this Change Order:
No cost change order to add additional days to contract for the long lead LED crossing items, luminaires and
SDG&E Service.
CHANGE ORDER NO. 5
February 15, 2018
The City of National City and Contractor agree to the following change to the original Contract:
The contractor is being issues this no cost change order to add additional days to contract for the long lead
LED crossing items, luminaires and SDG&E service.
Original Contract Amount $ 915,818.00
Net change by previously authorized Change Orders
Subtotal
Amount of this change order
29,413.31
945,231.31
New contract amount $ 945,231.31
Working days added: 20 Working days subtracted: 0 Percent change in Contract to date 3.21%
Sub_tted by:
Manag- Date City Project Manager
pproved by:
Date
�1/2 6 /!
Date City Manager, required for Change Orders >$24,999 Date
By signing this Change Order the Contractor confirms that he/she is completely familiar with its terms and conditions and has fairly
negotiated its price, terms and conditions. If this Change Order is approved, Contractor will provide all of the equipment, materials and
labor necessary to provide a complete work as described above at that the price stated herein. Additionally, Contractor confirms that the
price is fair and complete and represents all costs associated with the work, including but not limited to all equipment, materials, labor,
supervision, overhead, fees, bonds, insurance, profit, etc. and that there will be no further compensation. All of the terms and conditions
of the original contract documents are incorporated herein. (2 originals: 1 for City Clerk, 1 for Contractor)
Accepted and agreed to by (Contractor's name):
br- 1 psst
Name:
3/2z1 tB
Date
Note to Contractor: If you do not agree with this Change Order you may be directed to proceed with this work under the terms of the
contract and you may proceed under protest. You must comply with the contract requirements of submitting a written protest to protect
your claim.
Originals: City Clerk, Contractor
cc: Engineering project file, Project Manager
1243 National City Boulevard, National City, CA 91950 Telephone (619) 336-4380
CITY OF NATIONAL CITY
Office of the City Clerk
1243 National City Blvd., National City, California 91950-4397
619-336-4228
Michael R. Dalla, CMC - City Clerk
TRI-GROUP CONSTRUCTION
18TH STREET PEDESTRIAN AND BICYCLE ENHANCEMENTS
CIP No. 16-10
Change Orders #4 and #5
Judy Hernandez (Engineering/Public Works) forwarded a copy of the
Change Orders to Tri-Group Construction, Inc.