HomeMy WebLinkAbout2018 CON Palm Engineering - Westside Mobility Improvements CIP No. 17-04 - Change Orders #29 through #34WESTSIDE MOBILITY IMPROVEMENTS
CIP NO. 17-04 March 22, 2018
Contractor. Palm Engineering Construction Company, Inc.
Reason/Purpose for this Change Order.
Ten trees in the parkway on 19th St behind Kimball Elementary were lifting and damaging adjacent sidewalk.
Under direction of the Engineer the Contractor proceeded with removing and disposing of the trees.
CHANGE ORDER NO. 29
The City of National City and Contractor agree to the following change to the original Contract:
The City and the Contractor agree that the Contractor shall proceed with removing and disposing of the ten
trees behind Kimball Elementary. The agreed upon price for all costs associated with this work is as stated
on this Change Order. See Attachments for cost breakdown.
Original Contract Amount
Net change by previously authorized Change Orders
1,780,325.57
134,767.59
Subtotal 1,915,093.16
Amount of this change order 4,590.00 oj
New contract amount S 1,919,683.16
Working days added: 0 Working days subtracted: 0 Percent change in Contract to date 7.83%
Submitted by:
ect Manaq
Date
Approved by:
ity ngineer
6/i9 ..49'
Date
City Manager, regaled for Charge Orders >satssg Date
By signing this Change Order the Contractor confirms that he/she is completely familiar with its terms and conditions and has fairly negotiated its
price, terms and conditions. If this Change Order is approved, Contractor will provide all of the equipment, materials and labor necessary to provide a
complete work as described above at that the price stated herein. Additionally, Contractor confirms that the price is fair and complete and represents
all costs associated with the work, including but not limited to all equipment, materials, labor, supervision, overhead, fees, bonds, insurance, profit, etc.
and that there will be no further compensation. All of the terms and conditions of the original contract documents are incorporated herein.
Accepted and agreed to by Palm Engineering Construction Company, Inc.
ilk
Name: p Date
Note iContractor: If you do not agree with this Change Order you may be directed to proceed with this work under the terms of the contract and you
may proceed under protest. You must comply with the contract reouirements of submitting a written protest to protect your claim.
Originals: City Clerk, Contractor cc: Engineering project file, Project Manager
1243 National City Boulevard, National City, CA 91950 Telephone (619) 336-4380
N; TIO INeA CITy
Z C6RPORATEt
WESTSIDE MOBILITY IMPROVEMENTS CHANGE ORDER NO. 29
CIP NO. 17-04
DATE: March 1, 2018
WORK PERFORMED BY: Palm Engineering
DESCRIPTION OF WORK: Removal of 10 Trees on 19th Street behind Kimball Elementary
ACCOUNTING FOR TIME, MATERIALS, AND EQUIPMENT
Unit
Qty
Wage
Total
1) Removal of 10 Trees j EA
10.00
450.00
4,500.00
TOTAL:
SUB TOTAL:
BOND AND INSURANCE (2%):
GRAND TOTAL:
4,500.00
4,500.00
$90.00
$4,,590.0
}- CALIFORNIA ,-t*
NATIONAL CflT
ORP�y1 I INCORPORATE
WESTSIDE MOBILITY IMPROVEMENTS
CIP NO. 17-04
Contractor: Palm Engineering Construction Company, Inc.
CHANGE ORDER NO. 30
May 21, 2018
Reason/Purpose for this Change Order.
The new pedestrian ramp grades created a edge in the parkways adjacent at the SE comer of W. 16th
Street and Hoover Ave. Under direction of the Engineer the Contractor proceeded under time and materials
with lowering the adjacent parkways, adjusting the irrigation, planting new sod and removing a tree to match
the new pedestrian ramp grades.
The City of National City and Contractor agree to the following change to the original Contract:
The City and the Contractor agree that the Contractor shall proceed with lowering the adjacent parkways
and removing a tree to match the new pedestrian ramp grades at the SE comer of W. 16th Street and
Hoover Ave. The agreed upon price for all costs associated with this work is as stated on this Change Order.
See Attachments for cost breakdown.
Original Contract Amount $ 1,780,325.57
Net change by previously authorized Change Orders
Subtotal
Amount of this change order
New contract amount
Working days added: 0 Working days subtracted: 0
139,357.59
1,919,683.16
4,331.84
$ 1,924,015.00
Percent change in Contract to date 8.07%
Submitted by:
olect pager
SAV)Z
ate
Approved by:
.
Cites y�er
•
.d.4
Date
City Manager, required for Change Orders>$24,999
Date
By signing this Change Order the Contractor confirms that he/she is completely familiar with its terms and conditions and has fairly negotiated its
price, terms and conditions. If this Change Order is approved, Contractor will provide all of the equipment, materials and labor necessary to provide a
complete work as described above at that the price stated herein. Additionally, Contractor confirms that the price is fair and complete and represents
all costs associated with the work, including but not limited to all equipment, materials, labor, supervision, overhead, fees, bonds, insurance, profit, etc.
and that there will be no further compensation. All of the terms and conditions of the original contract documents are incorporated herein.
Accep, ed and agreed to by Palm Engineering Construction Company, Inc.
5 l -?5//8
Name: Date
Note to Contractor: If you do not agree with this Change Order you may be directed to proceed with this work under the terms of the contract and you
may proceed under protest. You must comply with the contract requirements of submitting a written protest to protect your claim.
Originals: City Clerk, Contractor cc: Engineering project file, Project Manager
1243 National City Boulevard, National City, CA91950
Telephone (619) 336-4380
+*- CALIFORNIA
NATIONAL, CJfl rV
INCORPORATED
WESTSIDE MOBILITY IMPROVEMENTS CHANGE ORDER NO. 30
CIP NO. 17-04
DATE: May 2, 2018
WORK PERFORMED BY: Palm Engineering
DESCRIPTION OF WORK: Additional grading, irrigation and landscaping at the SE corner
of W. 16th St and Hoover Ave
ACCOUNTING FOR TIME, MATERIALS, AND EQUIPMENT
1) Sanchez, Eleazar- Landscape Laborer
2)
Cruz, Vidal - Landscape Laborer
Unit
Hour
Hour
Qty
12.00
8.00
Wage
51.51
51.51
Total
618.12
412.08
3)
4
4)
Cruz, Vidal - Landscape Operator
Arriolla, Alfredo - Groundsman
Arriolla, Steven - Groundsman
Hour
Hour
4.00
4.00
Hour 4.00
62.91
20.00
16.60
251.64
80.00
66.40
1) Sod
Sub -Total Labor:
Labor surcharge (29.45%):
Labor Markup (20%): S 369.77
TOTAL LABOR:
Unit Qty Rate Total
LS 1.00 185.19 185.19
$ 420.62
$ 1,428.24
1)
1)
Sprinkler/Irrigation parts
Dump Fees
LS
LS
1.00
1.00
100.00
20.00
100.00
20.00
$ 305.19
Sub -Total Materials:
Materials Markup (15%): $ 45.78
TOTAL MATERIALS:
Unit
Qty
Rate
Total
1)
S171 Bobcat Skidskeer
Hour
4.00
29.69
118.76
2)
Tool Truck
Hour
12.00
32.48
389.76
3)
Removal of tree and stump grinding
LS
1.00
950.00
950.00
Sub -Total Equipment:
Equipment Markup (15%):
TOTAL EQUIPMENT:
$ 1,458.52
S 218.78
$ 1,677.301
SUB TOTAL: $ 7,27r 0
BOND AND INSURANCE (2%): $84.94
GRAND TOTAL: $4r 3L844
CALIFORNIA *K+
NATIONAL CITy
\— lNCORPORATE�
WESTSIDE MOBILITY IMPROVEMENTS
CIP NO. 17-04
Contractor: Palm Engineering Construction Company, Inc.
CHANGE ORDER NO. 31
May 21, 2018
Reason/Purpose for this Change Order:
Change in contract to use hot melt thermoplastic in lieu of preformed thermoplastic for a cost savings to the
city and still achieve the same goal. Under direction of the Engineer the Contractor proceeded with using
extruded hot melt thermoplastic.
The City of National City and Contractor agree to the following change to the original Contract:
The City and the Contractor agree that the Contractor shall proceed using extruded hot melt thermoplastic
for a cost savings from lump sum line items 16, 33, 39, 42, and 56. The agreed upon puce for all costs
associated with this work is as stated on this Change Order. See Attachments for cost breakdown.
Original Contract Amount $ 1,780,325.57
Net change by previously authorized Change Orders
Subtotal
Amount of this change order
New contract amount
Working days added: 0 Working days subtracted: 0
Submitted by:
P Iect Ma qer
S/Z./1Q
Date
Approved by:
2.
City ngineer
.
Date
City Manager, required for Change Orders >$24,999
Date
By signing this Change Order the Contractor confirms that he/she is completely familiar with its terms and conditions and has fairly negotiated its
price, terms and conditions. If this Change Order is approved, Contractor will provide all of the equipment, materials and labor necessary to provide a
complete work as described above at that the price stated herein. Additionally, Contractor confirms that the price is fair and complete and represents
all costs associated with the work, including but not limited to all equipment, materials, labor, supervision, overhead, fees, bonds, insurance, profit, etc.
and that there will be no further compensation. All of the terms and conditions of the original contract documents are incorporated herein.
Acce d and agreed to by Palm Engineering Construction Company, Inc.
Name:
143,689.43
1,924,015.00
(23,880.00)
$ 1,900,135.00
Percent change in Contract to date 6.73%
Date
Note to ontractor: y o not agree wit ange er you may to proc is wor er the termse contract and you
may proceed under protest. You must comply with the contract requirements of submittino a written protest to protect your claim.
Originals: City Clerk, Contractor cc: Engineering project file, Project Manager
o
c
If you d
h this Ch
Ord
be directed
eedwithth
k and
f th
1243 National City Boulevard, National City, CA 91950
Telephone (619) 336-4380
:\\"1�
CALIFORNIA f''
N
I I O N A L CIiV
CORPORATCO
WESTSIDE MOBILITY IMPROVEMENTS
CIP NO. 17-04
DATE: May 21, 2018
CHANGE ORDER NO.31
WORK PERFORMED BY: Statewide Stripes, Inc.
DESCRIPTION OF WORK: Removal of preformed thermoplastic
ACCOUNTING FOR TIME, MATERIALS, AND EQUIPMENT
Unit
Qty
Wage
Total
Removal of preformed
1) thermoplastic
LS
1.00
23,880.00
23,880.00
TOTAL:
»- CAL:1001t'til
N,A,TIO T CIfiy
o3Q
WESTSIDE MOBILITY IMPROVEMENTS
CIP NO. 17-04
Contractor: Palm Engineering Construction Company, Inc.
CHANGE ORDER NO. 32
May 21, 2018
Reason/Purpose for this Change Order:
The sidewalk and pedestrian curb ramps to be removed and replaced on Sheets 34 and 35 of the plans did
not illustrate the survey monuments to be tied -out and re-established within these limits. Under direction of
the Engineer the Contractor proceeded with tieing out and re-establishing the survey monuments.
The City of National City and Contractor agree to the following change to the original Contract:
The City and the Contractor agree that the Contractor shall proceed with tieing out and re-establishing the
survey monuments on Sheets 34 and 35 of the plans. The agreed upon price for all costs associated with
this work is as stated on this Change Order. See Attachments for cost breakdown.
Original Contract Amount $ 1,780,325.57
Net change by previously authorized Change Orders
Subtotal
Amount of this change order
New contract amount
Working days added: 0 Working days subtracted: 0
119,809.43
1,900,135.00
22,491.00
$ 1,922,626.00
Percent change in Contract to date 7.99%
Submitted by:
P ect Ma er
Date
Approved by:
City ngineer
Date
City Manager, required for Change Orders>$24,999
Date
By signing this Change Order the Contractor confirms that he/she is completely familiar with its terms and conditions and has fairly negotiated its
price, terms and conditions. If this Change Order is approved, Contractor will provide all of the equipment, materials and labor necessary to provide a
complete work as described above at that the price stated herein. Additionally, Contractor confirms that the price is fair and complete and represents
all costs associated with the work, including but not limited to all equipment, materials, labor, supervision, overhead, fees, bonds, insurance, profit, etc.
and that there will be no further compensation. All of the terms and conditions of the original contract documents are incorporated herein.
Accepted,dl9d agreed to by Palm Engineering Construction Company, Inc.
Name:
Date
N
ote to ontractor: y o not agree wit ange er you may to proc is wor e terms e contract and you
may proceed under protest. You must comply with the contract requirements of submittino a written protest to protect your claim.
Originals: City Clerk, Contractor cc: Engineering project file, Project Manager
C
If you d
h this Ch
Ord
be directed
eed with th
k under th
of th
1243 National City Boulevard, National City, CA 91950
Telephone (619) 336-4380
43 * CALIFORNIA +-
NATIONAL CHIT
C
INCORPORATED
WESTSIDE MOBILITY IMPROVEMENTS CHANGE ORDER NO. 32
CIP NO. 17-04
DATE: May 21, 2018
WORK PERFORMED BY: Palm Engineering
DESCRIPTION OF WORK: Tie -out and re-establish survey monuments on sheets 34 and 35
ACCOUNTING FOR TIME, MATERIALS, AND EQUIPMENT
Unit Qty Wage Total
1) Survey Monuments EA 49.00 450.00 22,050.00
TOTAL:
SUB TOTAL:
BOND AND INSURANCE (2%):
r
�-- CALIFORNIA-0
NATIONAL CHM
orcoRAOAA7tu
WESTSIDE MOBILITY IMPROVEMENTS
CIP NO. 17-04
Contractor: Palm Engineering Construction Company, Inc.
CHANGE ORDER NO. 33
May 24, 2018
Reason/Purpose for this Change Order.
Root grinding was needed at 18 locations throughout the westside to properly install the new sidewalk and
preventing it from raising in the future. Under direction of the Engineer the Contractor proceeded with root
grinding the 18 locations.
The City of National City and Contractor agree to the following change to the original Contract:
The City and the Contractor agree that the Contractor shall proceed root grinding with 18 locations. The
agreed upon price for all costs associated with this work is as stated on this Change Order. See
Attachments for cost breakdown.
Original Contract Amount $ 1,780,325.57
Net change by previously authorized Change Orders
Subtotal
Amount of this change order
New contract amount
Working days added: 0 Working days subtracted: 0
1,922,626.00 dd
4,590.00
1,927,216.00
Submitted by:
P ect Man ger
S/29-//t
Date
Approved by:
City n ineer
.
Date
City Manager, required for Change Orders>$24,999
Date
By signing this Change Order the Contractor confirms that he/she is completely familiar with its terms and conditions and has fairly negotiated its
price, terms and conditions. If this Change Order is approved, Contractor will provide all of the equipment, materials and labor necessary to provide a
complete work as described above at that the price stated herein. Additionally, Contractor confirms that the price is fair and complete and represents
all costs associated with the work, including but not limited to all equipment, materials, labor, supervision, overhead, fees, bonds, insurance, profit, etc.
and that there will be no further compensation. All of the terms and conditions of the original contract documents are incorporated herein.
Accepted anc agreed to by Palm Engineering Construction Company, Inc.
Name:
5/
Date
/lg
N
142,300.43
Percent change in Contract to date 8.25%
ote to ontractor: you do not agree with t ange er you may directto proc with this wor er the terms of the contract and you
may proceed under protest. You must comply with the contract reauirements of submitting a written protest to protect your claim.
Originals: City Clerk, Contractor cc: Engineering project file, Project Manager
C
If
his Ch
Ord
be
ed
eed
k and
1243 National City Boulevard, National City, CA 91950
Telephone (619) 336-4380
eALtFORNt4
NATIONAfL CITy
iNcoitipostAosv
WESTSIDE MOBILITY IMPROVEMENTS CHANGE ORDER NO. 33
CIP NO. 17-04
DATE: May 21, 2018
WORK PERFORMED BY: Palm Engineering
DESCRIPTION OF WORK: Root grinding at 18 locations throughout westside
1) Root orindin
ACCOUNTING FOR TIME, MATERIALS, AND EQUIPMENT
Unit
EA
Qty
18.00
Wage
250.00
Tota I
4 500.00
TOTAL:
SUB TOTAL:
BOND AND INSURANCE (2%):
GRAND TOTAL:
4,500.00
4,500.00
$90.00
4,590.00
WESTSIDE MOBILITY IMPROVEMENTS
CIP NO. 17-04
Contractor: Palm Engineering Construction Company, Inc.
CHANGE ORDER NO. 34
May 25, 2018
Reason/Purpose for this Change Order:
Westside Pedestrian Plaza improvements per Spuriock plans dated April 20th, 2018.
The City of National City and Contractor agree to the following change to the original Contract:
The City and the Contractor agree that the Contractor shall proceed with the Westside Pedestrian Plaza
Improvements. The agreed upon price for all costs associated with this work is as stated on this Change
Order. See Attachments for cost breakdown.
Original Contract Amount $ 1,780,325.57
Net change by previously authorized Change Orders
Subtotal
Amount of this change order
New contract amount $ 1,970,678.20
Working days added: 0 Working days subtracted: 0
Percent change in Contract to date 10.69%
146,890.43
1,927,216.00 ds
43,462.20
Submitted by:
Da e
P tect Ma ger
Approved y:
,
City ngineer
:Oder
Date
City Manager, required for Change Orders>$24,999
Date
By signing this Change Order the Contractor confirms that he/she is completely familiar with its terms and conditions and has fairly negotiated its
price, terms and conditions. If this Change Order is approved, Contractor will provide all of the equipment, materials and labor necessary to provide a
complete work as described above at that the price stated herein. Additionally, Contractor confirms that the price is fair and complete and represents
all costs associated with the work, including but not limited to all equipment, materials, labor, supervision, overhead, fees, bonds, insurance, profit, etc.
and that there will be no further compensation. All of the terms and conditions of the original contract documents are incorporated herein.
Accet ted .nd ,greed to alm Engineering Construction Company, Inc.
3-tri
Date
of to Contractor: If you do not agree with this Change Order you may be directed to proceed with this work under the terms of the contract and you
m .v proceed under Protest. You must comply with the contract reauirements of submitting a written protest to protect your claim.
Originals: City Clerk, Contractor
cc: Engineering project file, Project Manager
1243 National City Boulevard, National City, CA 91950 Telephone (619) 336-4380
WESTSIDE MOBILITY IMPROVEMENTS
CIP NO. 17-04
DATE: May 25, 2018
CHANGE ORDER NO. 34
WORK PERFORMED BY: Palm Engineering
DESCRIPTION OF WORK: Westside Pedestrian Plaza
ACCOUNTING FOR TIME, MATERIALS, AND EQUIPMENT
Unit
Qty
Wage
Total
1)
Demo Asphalt Concrete
LS
1.00
5,000.00
5,000.00
3,250.00
2)
Provide and install Natural
Gray Concrete
LS
1.00
3,250.00
3)
Provide and install San Diego
Buff Concrete
LS
1.00
7,500.00
7,500.00
4)
Provide and install
Decomposed Granite
LS
1.00
2,800.00
2,800.00
5)
Two 2'H x4' Diameter
Extension Pipe
EA
1.00
1,800.00
1,800.00
6)
Provide and install Two Citrus
Aurantifolia
EA
2.00
485.00
970.00
7)
Power wash Trash Enclosure
LS
1.00
650.00
650.00
8)
Provide and install Trellis
LS
1.00
19,800.00
19,800.00
9)
Permitting
LS
1.00
840.00
840.00
TOTAL
,.,6 0.001
SUB TOTAL:
BOND AND INSURANCE (2%):
GRAND TOTAL:
$ 42,610.00
$852.20
43,462. 2Q
.....111Tge
CITY OF NATIONAL CITY
Office of the City Clerk
1243 National City Blvd., National City, California 91950-4397
619-336-4228
Michael R. Dalla, CMC - City Clerk
WESTSIDE MOBILITY IMPROVEMENTS
PALM ENGINEERING CONSTRUCTION COMPANY, INC.
CIP No. 17-04
Change Orders #29 through #34
Judith Hernandez (Engineering/Public Works) forwarded copies of the Change Orders to
Palm Engineering Construction Company.