WILSON AVE AND W. 22ND STREET
CHANGE ORDER NO. 1
CIP NO. 17-19 June 1, 2018
Contractor: PAL General Engineering Inc.
Reason/Purpose for this Change Order:
Additional grinding and disposal of asphalt was needed on Wilson Ave and W. 22nd street to have the
existing street meet the new curb/gutter grades. Under direction of the Engineer the Contractor proceeded
with the additional grinding and disposal.
The City of National City and Contractor agree to the following change to the original Contract:
The City and the Contractor agree that the Contractor shall proceed with additional grinding and disposal of
asphalt on Wilson Ave and W. 22nd Street. The agreed upon price for all costs associated with this work is
as stated on this Change Order. See Attachment "A" for cost breakdown.
Original Contract Amount $ 355,404.00
Net change by previously authorized Change Orders -
Subtotal 355,404.00
Amount of this change order 5,955.88
New contract amount $
Working days added: 0 Working days subtracted: 0 Percent change in Contract to date 1.68%
361,359.88
Submitted by:
Cf22)(lib
Date
Approved by:
City,Engineer
Date
City Manager, required for Change Orders >$24,999 Date
By signing this Change Order the Contractor confirms that he/she is completely familiar with its terms and conditions and has fairly negotiated its
price, terms and conditions. If this Change Order is approved, Contractor will provide all of the equipment, materials and labor necessary to provide a
complete work as described above at that the price stated herein. Additionally, Contractor confirms that the price is fair and complete and represents
all costs associated with the work, including but not limited to all equipment, materials, labor, supervision, overhead, fees, bonds, insurance, profit, etc.
and that there will be no further compensation. All of the terms and conditions of the original contract documents are incorporated herein.
Accepted and agreed to by PAL General Engineering Inc.:
Name: Pot. Date 49%2-z-A
Note to Contractor: If you do not agree with this Change rder you may be directed to proceed with this work under the terms of the contract and you
may proceed under protest. You must comply with the contract reauirements of submittina a written orotest to protect your claim.
Originals: City Clerk, Contractor cc: Engineering project file, Project Manager
1243 National City Boulevard, National City, CA91950
Telephone (619) 336-4380
1.
� - CALIFO I
NATIONArtt
Wilson and W. 22nd Street CHANGE ORDER NO.1
CIP NO. 17-19
DATE: June 1, 2018
WORK PERFORMED BY: PAL General Engineering Inc.
DESCRIPTION OF WORK: Additional grinding and disposal of asphalt on Wilson Ave and
W. 22nd Street
ACCOUNTING FOR TIME, MATERIALS, AND EQUIPMENT
LABOR
Unit
Qty
Wage
Total
1)
Laborer
hour
4.00
59.45
237.80
2)
Operator
hour
4.00
79.85
319.40
3)
Apprentice Laborer
hour
4.00
39.88
159.52
4)
Foreman
hour
4.00
95.00
380.00
Sub -Total Labor:
Labor Markup (20%):
TOTAL LABOR:
$ 1,096.72
$ 219.34
$ 1,316.06
MATERIALS
Unit
Qty
Rate
Total
1)
Asphalt Dump
LS
1.00
216.00
216.00
Sub -Total Materials:
Materials Markup (15%):
TOTAL MATERIALS:
$ 216.00
$ 32.40
$ 248.40
EQUIPMENT
Unit
Qty
Rate
Total
1)
2)
3)
Skid Steer
4' Grinder
Sweep Attachment
hour
hour
hour
4.00
1.00
0.50
50.00
2,800.00
200.00
200.00
2,800.00
100.00
4)
Trucking
hour
4.00
118.00
472.00
Sub -Total Equipment:
Equipment Markup (15%):
TOTAL EQUIPMENT:
$ 3,572.00
$ 535.80
SUB TOTAL:
BOND AND INSURANCE (5%):
GRAND TOTAL:
$ 4,107.80
$ 5,672.26
$283.61
$ 5,955.88
CALIFORNIA
NATIONAL CITY
nvy
INCORPORATE-
WILSON AVE AND W. 22ND STREET
CIP NO. 17-19
Contractor: PAL General Engineering Inc.
Reason/Purpose for this Change Order.
The designed grades for the curb/gutter from stations 13+76 to 15+95 on Wilson avenue were not matching
existing conditions and had to be redesigned. Under direction of the Engineer the Contractor proceeded
with reforming the curb/gutter between stations 13+76 to 15+95 with the new adjusted grades.
CHANGE ORDER NO. 2
June 12, 2018
The City of National City and Contractor agree to the following change to the original Contract:
The City and the Contractor agree that the Contractor shall proceed with reforming the curb/gutter on Wilson
Avenue between stations 13+76 to 15+95. The agreed upon price for all costs associated with this work is
as stated on this Change Order. See Attachment "A" for cost breakdown.
Original Contract Amount $ 355,404.00
Net change by previously authorized Change Orders
Subtotal
Amount of this change order
New contract amount $
Working days added: 0 Working days subtracted: 0
5,955.88
361,359.88
4,098.36
Percent change in Contract to date 2.83%
365,458.24
Submitted by:
P, iect qer
Date
pprove y:
Clt n ineer
g .
Date
City Manager, required for ChargeOrders >$24,999
Date
By signing this Change Order the Contractor confirms that he/she is completely familiar with its terms and conditions and has fairly negotiated its
price, terms and conditions. If this Change Order is approved, Contractor will provide all of the equipment, materials and labor necessary to provide a
complete work as described above at that the price stated herein. Additionally, Contractor confirms that the price is fair and complete and represents
all costs associated with the work, including but not limited to all equipment, materials, labor, supervision, overhead, fees, bonds, insurance, profit, etc.
and that there will be no further compensation. All of the terms and conditions of the original contract documents are incorporated herein.
Accepted and agreed to by PAL General Engineering Inc.
Name: piavt 0- i'tlLA Date 6/1Z -�—
Note to Contractor: If you do not agree with this Change Order you may be directed to proceed with this work under the terms of the contract and you
may proceed under protest. You must comply with the contract requirements of submitting a written protest to protect vour claim.
Originals: City Clerk, Contractor cc: Engineering project file, Project Manager
1243 National City Boulevard, National City, CA 91950 Telephone (619) 336-4380
NAFIION ° clay
�.� �a �.:.\...
r INc6*
Wilson and W. 22nd Street CHANGE ORDER NO. 2
CIP NO. 17-19
DATE: May 9, 2018
WORK PERFORMED BY: PAL General Engineering Inc.
DESCRIPTION OF WORK: Reforming curb/gutter from stations 13+75 to 15+95
ACCOUNTING FOR TIME, MATERIALS, AND EQUIPMENT
LABOR
Unit
Qty
Wage
Total
1)
Foreman
hour
5.00
88.33
441.65
2)
Cement Mason (6)
hour
30.00
66.02
1,980.60
Sub -Total Labor:
Labor Markup (20%):
TOTAL LABOR:
$ 2,422.25
$ 484.45
$ 2,906.70
MATERIALS
Unit
Qty
Rate
Total
1)
Concrete (Superior Ready Mix)
CY
7.00
114.85
803.95
Sub -Total Materials:
Materials Markup (15%):
TOTAL MATERIALS:
$ 803.95
$ 120.59
$ 924.54
EQUIPMENT
Unit
Qty
Rate
Total
1)
Pickup truck with Trailer
hour
5.00
32.48
162.40
Sub -Total Equipment:
Equipment Markup (15%):
TOTAL EQUIPMENT:
$ 162.40
$ 24.36
SUB TOTAL:
BOND AND INSURANCE (2%):
GRAND TOTAL:
$ 186.76
$ 4,018.00
$80.36
$ 4,098.36
LIF ONNIA ^�
WILSON AVE AND W. 22ND STREET
CIP NO. 17-19
Contractor: PAL General Engineering Inc.
CHANGE ORDER NO. 3
June 12, 2018
Reason/Purpose for this Change Order:
Remove and replace crosswalk striping at 18th Street and Coolidge Avenue and remove and replace raised
crosswalks striping on 18th Street at Coolidge Avenue and Hoover Avenue. Under direction of the Engineer
the Contractor proceeded with removing and replacing the crosswalks at the above mentioned locations.
The City of National City and Contractor agree to the following change to the original Contract:
The City and the Contractor agree that the Contractor shall proceed with removing and replacing crosswalk
striping at 18th Street and Coolidge Avenue and removing and replacing raised crosswalk striping on 18th
Street at Coolidge Avenue and Hoover Avenue. The agreed upon price for all costs associated with this
work is as stated on this Change Order. See Attachment "A" for cost breakdown.
Original Contract Amount $ 355,404.00
Net change by previously authorized Change Orders
Subtotal
Amount of this change order
New contract amount $
Working days added: 0 Working days subtracted: 0
10,054.24
365,458.24
7,338.49
Percent change in Contract to date 4.89%
372,796.73
Submitted by:
' elect M ager
a
Date
pproved by:
City2
9 ineer
Date
City Manager, required
v g �
Change orders>$2a999
Date
By signing this Change Order the Contractor confirms that he/she is completely familiar with its terms and conditions and has fairly negotiated its
price, terms and conditions. If this Change Order is approved, Contractor will provide all of the equipment, materials and labor necessary to provide a
complete work as described above at that the price stated herein. Additionally, Contractor confirms that the price is fair and complete and represents
all costs associated with the work, including but not limited to all equipment, materials, labor, supervision, overhead, fees, bonds, insurance, profit, etc.
and that there will be no further compensation. All of the terms and conditions of the original contract documents are incorporated herein.
Accepted and agreed to by PAL General Engineering Inc.:
Date Z
Note to Contractor: I you do not agree with this •nge s re - you may bedirectedto proceed with this work under the terms of the contract a y
may Proceed under protest. You must comply with the contract reouirements of submitting a written protest to protect your claim.
Originals: City Clerk, Contractor cc: Engineering project file, Project Manager
Name: )s'Uiz iSut
1243 National City Boulevard, National City, CA 91950
Telephone (619) 336-4380
L1FOR
CiTy
rztooNRp� ° _7
c34r
Wilsonn and W. 22nd Street CHANGE ORDER NO. 3
CIP NO. 17-19
DATE: June 12, 2018
WORK PERFORMED BY: PAL General Engineering Inc.
DESCRIPTION OF WORK: Remove and replace crosswalk striping on 18th Street at Coolidge
Ave and Hoover Ave
ACCOUNTING FOR TIME, MATERIALS, AND EQUIPMENT
Unit
Qty
Wage
Tota I
1)
Install yellow continental
crosswalks and chevrons in
extruded thermoplastic and
remove conflict markings
LS
1.00
6,852.00
6,852.00
SUB TOTAL:
PRIME CONTRACTOR MARKUP (5%):
BOND (2%):
GRAND TOTAL:
$ 6,852.00
$ 342.60
$ 143.89
$ 7,338.49
WILSON AVE AND W. 22ND STREET
CIP NO. 17-19
Contractor: PAL General Engineering Inc.
CHANGE ORDER NO. 4
June 19, 2018
Reason/Purpose for this Change Order:
A section of the plans was deleted on W. 22nd Street from stations 102+70 to 104+20 with the future plans
of a park coming through. Under direction of the Engineer the Contractor proceeded with the deletion of
work from sections 102+70 to 104+20. This work includes but not limited to clearing/grubbing the
demolition of sidewalk, driveway, curb/gutter and the installation of irrigations and trees/shrubs.
The City of National City and Contractor agree to the following change to the original Contract:
The City and the Contractor agree that the Contractor shall proceed with the deletion of work on W. 22nd
Street from stations 102+70 to 104+20. The agreed upon price for the cost reduction associated with this
work is as stated on this Change Order. See Attachment "A" for cost breakdown.
Original Contract Amount $ 355,404.00
Net change by previously authorized Change Orders
Subtotal
Amount of this change order
New contract amount $
Working days added: 0 Working days subtracted: 0
17,392.73
372,796.73
(3,153.91)
Percent change in Contract to date 4.01 %
369,642.82
Submitted by:
/
Date
leg t ager
Approve by:
Cit ngineer
Date
City Manager, required for Charge Orders>$24,999
Date
By signing this Change Order the Contractor confirms that he/she is completely familiar with its terms and conditions and has fairly negotiated its
price, terms and conditions. If this Change Order is approved, Contractor will provide all of the equipment, materials and labor necessary to provide a
complete work as described above at that the price stated herein. Additionally, Contractor confirms that the price is fair and complete and represents
all costs associated with the work, including but not limited to all equipment, materials, labor, supervision, overhead, fees, bonds, insurance, profit, etc.
and that there will be no further compensation. All of the terms and conditions of the original contract documents are incorporated herein.
Accepted and agreed to by PAL General Engineering Inc.:
Name:
%Kh �lJh Date G 2z/
fr-
Note to Contractor: If ou do not agree with this Change Or you may be directed to proceed with this work under the terms of the contract and you
may proceed under protest. You must comply with the contract reauirements of submitting a written orotest to protect your claim.
Originals: City Clerk, Contractor cc: Engineering project file, Project Manager
1243 National City Boulevard, National City, CA 91950
Telephone (619) 336-4380
CALIFORNIA -t-
AT'ION ' LLtflry
ai i
WCORPORATEP
Wilson and W. 22nd Street CHANGE ORDER NO. 4
CIP NO. 17-19
DATE: June 19, 2018
WORK PERFORMED BY: PAL General Engineering Inc.
DESCRIPTION OF WORK: Deletion of work on 22nd street from Stations 102+70 to 104+20
ACCOUNTING FOR TIME, MATERIALS, AND EQUIPMENT
Unit
Qty
Wage Total
Sidewalk demolition/disposal
SF
120.00
1.56 187.20
2)
3)
4)
Driveway demolition/disposal
Curb/gutter demolition/disposal
Clearing and grubbing
(landscaping)
SF
LF
SF
250.00
47.00
380.00
2.00 500.00
3.13 147.11
0.47 178.60
5)
Irrigation
LS
1.00
800.00 800.00
6)
7)
Ulmus "True Green" (24" Box
Tree)
Leymus Condensatus (5 Gallon
Plant)
EA
EA
1.00
86.00
158.00 158.00
12.50 1,075.00
8)
Miscanthus Transmorrisonensis
(5 Gallon Plant)
EA
8.00
13.50 108.00
Sub -Total : $ 3,153.91
TOTAL:
(3,153.91)
ill //.
*- CALIFORNIA,�
NATIONAL Mr
�ffCORPORATED
WILSON AVE AND W. 22ND STREET
CIP NO. 17-19
Contractor: PAL General Engineering Inc.
CHANGE ORDER NO. 5
June 19, 2018
Reason/Purpose for this Change Order:
The new back of sidewalk grades on W. 22nd Street created an existing wall foundation to be exposed. A 6"
curb was added to the back of sidewalk to cover the foundation and tie into the existing wall. Under direction
of the Engineer the Contractor proceeded with the adding 110 linear feet of 6" curb at the back of sidewalk.
The City of National City and Contractor agree to the following change to the original Contract:
The City and the Contractor agree that the Contractor shall proceed with the adding 110 linear feet of 6"
curb at the back of sidewalk on W 22nd Street. The agreed upon price for all costs associated with this work
is as stated on this Change Order. See Attachment "A" for cost breakdown.
Original Contract Amount $
Net change by previously authorized Change Orders
Subtotal
Amount of this change order
New contract amount
Working days added: 0 Working days subtracted: 0
355,404.00
14,238.82
369,642.82
4,936.80
Percent change in Contract to date 5.40%
374,579.62
Submitted by:
• iect Ma
er
Date
Approved by:
Cityngineer
9
Date
CityManager, required
4 , e9
Orders> a999
�e � .
Date
By signing this Change Order the Contractor confirms that he/she is completely familiar with its terms and conditions and has fairly negotiated its
price, terms and conditions. If this Change Order is approved, Contractor will provide all of the equipment, materials and labor necessary to provide a
complete work as described above at that the price stated herein. Additionally, Contractor confirms that the price is fair and complete and represents
all costs associated with the work, including but not limited to all equipment, materials, labor, supervision, overhead, fees, bonds, insurance, profit, etc.
and that there will be no further compensation. All of the terms and conditions of the original contract documents are incorporated herein.
Acce • ted and a • reed to by PAL General Engineering Inc.:
Name: t�ta.. t& ¢tf
ote to Contractor: I you do not agree with this Change you may directs to proceed wit this work under the terms
may proceed under protest. You must comply with the contract reouirements of submittina a written protest to protect your claim.
Originals: City Clerk, Contractor cc: Engineering project file, Project Manager
1243 National City Boulevard, National City, CA 91950
Telephone (619) 336-4380
1R rtWpf
NATIONAL ONAL CITY
.ca‘ci0 0
Wilson and W. 22nd Street
CIP NO. 17-19
CHANGE ORDER NO. 5
DATE: June 19, 2018
WORK PERFORMED BY: PAL General Engineering Inc.
DESCRIPTION OF WORK: Additional 6" curb at back of sidewalk
ACCOUNTING FOR TIME, MATERIALS, AND EQUIPMENT
Unit
Qty
Wage
Total
1)
6" curb at back of sidewalk
LS
110.00
44.00
4,840.00
Sub -Total :
$ 4,840.00
TOTAL:
BOND (2%):
$ 4,840.00
$ 96.80
GRAND TOTAL:
$ 4,936.80
•
WILSON AVE AND W. 22ND STREET
CIP NO. 17-19
Contractor: PAL General Engineering Inc.
Reason/Purpose for this Change Order.
National City police department, fire department and construction management team had to respond to a
gas leak from the subcontractor, ACE Electric, damaging an existing gas lateral with an excavator. The gas
lateral was properly marked out, therefore, the Contractor is responsible for the costs incurred for the
emergency response. See attached City Ordinance No. 2010-2341.
The City of National City and Contractor agree to the following change to the original Contract:
The City and the Contractor agree that the Contractor is reponsible for the costs incurred by the City for the
emergency response team and construction management team for the damaged gas lateral. The agreed
upon price for the cost associated with this work is as stated on this Change Order. See Attachment "A" for
cost breakdown.
Original Contract Amount $ 355,404.00
Net change by previously authorized Change Orders
Subtotal
Amount of this change order
New contract amount
Working days added: 0 Working days subtracted: 0
19,175.62
374,579.62
(1,472.50)
Percent change in Contract to date 4.98%
373,107.12
Submitted by:
le lect ager
//
Dat
//
Approved by:
2 ..
CheerDate>
Y 9
City Manager, required
$24,999
Date
By signing this Change Order the Contractor confirms that he/she is completely familiar with its terms and conditions and has fairly negotiated its
price, terms and conditions. If this Change Order is approved, Contractor will provide all of the equipment, materials and labor necessary to provide a
complete work as described above at that the price stated herein. Additionally, Contractor confirms that the price is fair and complete and represents
all costs associated with the work, including but not limited to all equipment, materials, labor, supervision, overhead, fees, bonds, insurance, profit, etc.
and that there will be no further compensation. All of the terms and conditions of the original contract documents are incorporated herein.
Accepted and agreed to by PAL General Engineering Inc.:
CHANGE ORDER NO. 6
June 19, 2018
Date 61u%d
Note to Contractor: you do not agree with this Change r you may be irected to proceed with this work under the terms of the contract and you
may proceed under protest. You must comply with the contract requirements of submittina a written protest to protect your claim.
Originals: City Clerk, Contractor cc: Engineering project file, Project Manager
Name:
f
1243 National City Boulevard, National City, CA 91950 Telephone (619) 336-4380
+)... CALIFORNIA *�+
NATIONAL CITY
C,ORPORATED
Wilson and W. 22nd Street CHANGE ORDER NO. 6
CIP NO. 17-19
DATE: June 19, 2018
WORK PERFORMED BY: National City Emergency Response Team
DESCRIPTION OF WORK: Responding to gas lateral break
ACCOUNTING FOR TIME, MATERIALS, AND EQUIPMENT
Unit
Qty
Wage
Total
1)
Level 2 - Pipeline Incidents
LS
1.00
1,000.00
1,000.00
2)
PW - Inspector
HR
2.50
135.00
337.50
3)
Project Manager II
HR
1.00
135.00
Sub -Total :
135.00
$ 1,472.50
TOTAL:
$ (1,472.50)
CITY OF NATIONAL CITY
Office of the City Clerk
1243 National City Blvd., National City, California 91950-4397
619-336-4228
Michael R. Dalla, CMC - City Clerk
PAL GENERAL ENGINEERING
WILSON AVE AND 22ND STREET, CIP NO. 17-19
CHANGE ORDERS #1 THROUGH #6
Judy Hernandez (Engineering/Public Works) forwarded copies of the
Change Orders to PAL General Engineering.