HomeMy WebLinkAbout2018 CON Preman Roofing - City Hall Roof Replacement, CIP No. 18-08 - Change Orders #1 through #4...CORPORATES)
PROJECT NAME: City Hall Roof Replacement
CIP NO. 18-08
Contractor: Preman
CHANGE ORDER NO. 1
August 28, 2018
Reason/Purpose for this Change Order:
Existing 4 cast iron drains on the lower roof deck are too high in elevation for the new roofing system to allow
for proper drainage.
The City of National City and Contractor agree to the following change to the original Contract:
The City and the Contractor agree that the Contractor shall proceed with the removal of the 4 existing drains
and installation of 4 new TPO Thunderbird roof drains that will be flush mounted and connected to the
existing piping to allow for proper drainage throughout the lower roof deck.
Original Contract Amount $ 304,410.00
Net change by previously authorized Change Orders
Subtotal
Amount of this change order
New contract amount $
no days added: 0 Working days subtracted: 0
304,410.00
4,800.00
Percent change in Contract to date 1.58%
309,210.00
Submi ed
anager
0..,6
Date
Appr
e y:
City
gi eer(
City Manager, required for Change Orders>$24,999
Date
Silll ft
Date
By signing this Chatcjl Order the Contractor confirms that he/she is completely familiar with its terms and conditions and has fairly negotiated its
price, terms and conditions. If this Change Order is approved, Contractor will provide all of the equipment, materials and labor necessary to provide a
complete work as described above at that the price stated herein. Additionally, Contractor confirms that the price is fair and complete and represents
all costs associated with the work, including but not limited to all equipment, materials, labor, supervision, overhead, fees, bonds, insurance, profit, etc.
and that there will be no further compensation. All of the terms and conditions of the original contract documents are incorporated herein.
CONTRACTOR NAME: Preman
Date
Note to Contractor: If you .. not agree with this Change Order you may be directed to proceed with this work under the terms of the contract and you
may proceed under protest. You must comply with the contract reauirements of submittina a written protest to protect your claim.
Originals: City Clerk, Contractor cc: Engineering project file, Project Manager
1243 National City Boulevard, National City, CA 91950
Telephone (619) 336-4380
p ► PREMAN
ROOFING -SOLAR
Owner's Name:
City of National City
Owner's City:
National City, CA
Owner's Zip Code:
91950
Owner's Address:
1243 National City Blvd.
Atten:
LucaZappiello
Owner's Work Phone:
(619)336-4380
BID PROPOSAL
875 34th Street, San Diego, CA 92102
P: (619) 276-1700 F: (619) 276-1703
CA License No. 764917
Project Name & Address:
City Hall, 1243 National City Blvd., National City, CA 91950
Email:
Izappiello@nationalca.gov
a. Scope of Work: Preman Roofing Inc. hereby submits the following specifications and estimates:
PROPOSAL FOR ROOF DRAINS
#1. Remove (4) existing cast iron drains and install (4) newTPOThunderbird roof drains on lower deck.
#2. Drains will be Bottom Mount 2"roof drains with rubber No -Hub coupling connecting to existing piping underneath. Existing piping will have
to modified to properly align with new drains.
b. Not Included: This proposal does not include: Otherthan stated above.
c. WE PROPOSE to furnish material, equipment and labor in accor-
dance with the above specifications for the sum of:
$4,800.00 dollars
NOTE: This proposal may be withdrawn if not accepted within
30 days from 8-21-2018
date
Respectfully submitted by: David Rodriguez
Company Representative
d. WE ACCEPT the prices, specifications, and terms as stated in this
bid proposal are approved. We authorize you to draw up all neces-
sary contract documents so work can begin.
approved and accepted (owner or owner's authorized agent)
date
approved and accepted (second owner - if any)
date
Page ONE of 1 Total Pages
-►- CALIFORNIA ..i.
' — IFCCO
bBPOki6Ts°
PROJECT NAME: City Hall Roof Replacement
CIP NO. 18-08
Contractor: Preman
CHANGE ORDER NO. 2
August 28, 2018
Reason/Purpose for this Change Order.
Moisture in the southeast comer of the Library roof is being found due to a defective roof drain.
The City of National City and Contractor agree to the following change to the original Contract:
The City and the Contractor agree that the Contractor shall proceed with the repair of the existing defective
roof drain and in addition the contractor will procure and install Twenty (20) one way TPO vents on the
southeast section of the Library building to mitigate future moisture under the TPO membrane.
Original Contract Amount $
Net change by previously authorized Change Orders
Subtotal
Amount of this change order
New contract amount
Working days added: 4 Working days subtracted: 0
304,410.00
4,800.00
309,210.00
7,262.00
Percent change in Contract to date 3.96%
316,472.00
omit
d
I
rolec
anager
Date
SH‘
Appro djby::
tfritti
Cit(,Enine Date City Manager, required for Change Orders>$24.999 Date:
By signing this C nge Order the Contractor confirms that he/she is completely familiar with its terms and conditions and has fairly negotiated its
price, terms and conditions. If this Change Order is approved, Contractor will provide all of the equipment, materials and labor necessary to provide a
complete work as described above at that the price stated herein. Additionally, Contractor confirms that the price is fair and complete and represents
all costs associated with the work, including but not limited to all equipment, materials, labor, supervision, overhead, fees, bonds, insurance, profit, etc.
and that there will be no further compensation. All of the terms and conditions of the original contract documents are incorporated herein.
y CONTRACTOR NAME: Preman
Name: Date
Note to C. actor: If do not agree with this Change Order you may be directed to proceed with this work under the terms of the contract and you
may proceed under protest. You must comply with the contract requirements of submittina a written protest to protect your claim.
Originals: City Clerk, Contractor cc: Engineering project file, Project Manager
1243 National City Boulevard, National City, CA 91950
Telephone (619) 336-4380
'
AIL
.
,
PREIVIAll
ROOFING-SOURP:
CHANGE ORDER NO.
875 34t Street, San Diego, CA 92102
(619) 276-1700 F: (619) 276-1703
CA License No. 764917
Owner's Name:
City of National City
Owner's Address:
1243 National City Blvd.
Owner's City:
National City, CA
Owner's Zip Code:
91950
Atten:
Luca Zappiello
Owner's Work Phone:
(619) 336-4380
Project Name & Address:
City Hall, 1243 National City Blvd. & Library 1401 National City Blvd., National City, CA 91950
Email:
Iappiello@nationalcityca.gov
In conformance with and as a part of the existing contract dated 6-21-18 Preman Roofing Inc. is hereby authorized by the
OWNER or OWNERS AUTHORIZED AGENT to make change (s) to the above project and/or order any additional labor and
supplies and other items listed below and/or otherwise needed to complete the requirements of the scope of work of this
a. Scope of the extra work or changes
materials, services,
change order.
Install (20)OneWayTPO ventson southeast roof section onthe Library Building: $7,262.00 -_ __—. _..______-__.
_._ _ _
nstall(2Q)OneWayTPOvents_on_ontheCityHallBuilding: $7,500 00
Extend curb around communication cables and install 24 ga uge galvanized cap: $300.00
b. Payments for this order to be made as follows and will effect the schedule of progress payments as follows:
PREVIOUS contract total amount prior to this Change Order: $304,410.00
Date of completion as set forth in the existing
This Change Order will result in a DEDUCTION to the
original contract price in the lump sum amount of•
contract is hereby extended 4 days
because of the time necessary to complete this
This Change Order will result in an INCREASE to the
original contract price in the lump sum amount of• $15,062.00
Change Order.
REVISED contract total amount including this Change Order: $319,472.00
OWNER ACCEPTANCE: This change order shall be performed under the same conditions as specified in the existing contract. Your
signature below signifies your agreement and approval of this change order.
By: Date:
(signature of owner or authorized agent) (date of signing of this change order)
CONTRACTOR ACCEPTANCE: Preman Roofing Inc., agrees to perform this change order in accordance with the above conditions,
specifications and stated price.
By: Date:
(signature of contractor or authorized agent) (date of signing of this change order)
«— cAUFORNIA;-+
NATIONALCIT?�
+xcbarose.
PROJECT NAME: City Hall Roof Replacement
CIP NO. 18-08
Contractor: Preman
CHANGE ORDER NO. 3
August 28, 2018
Reason/Purpose for this Change Order:
On the west side of the south penthouse of the upper roof there are 4 weather heads in a conduit box that
are to be protected in place for potential future use. Existing abandon 800 mHZ antenna cable was in need
of removal. Due to excessive corrosion on the existing cap, a new 24-gauge galvanized cap is to be
installed.
The City of National City and Contractor agree to the following change to the original Contract:
The City and the Contractor agree that the Contractor shall proceed with removal and replacement of a new
24-gauge galvanized cap.
Original Contract Amount $ 304,410.00
Net change by previously authorized Change Orders
Subtotal
12,062.00
316,472.00
Amount of this change order 300.00
New contract amount $ 316,772.00
Working days added: 4 Working days subtracted: 0 Percent change in Contract to date 4.06%
Date
Apv:dby.
.
eirifts
Date
City Manager, reqr.afor Charm orders >s2a.ssa Date
:' igning his ange Order the Contractor confirms that he/she is completely familiar with its terms and conditions and has fairly negotiated its
price, terms and conditions. If this Change Order is approved, Contractor will provide all of the equipment, materials and labor necessary to provide a
complete work as described above at that the price stated herein. Additionally, Contractor confirms that the price is fair and complete and represents
all costs associated with the work, including but not limited to all equipment, materials, labor, supervision, overhead, fees, bonds, insurance, profit, etc.
and that there will be no further compensation. All of the terms and conditions of the original contract documents are incorporated herein.
►'CONTRACTOR NAME: Preman
Name' / %/ Date
Note to r � yr�f onot agree with this Change Order you may be directed to proceed with this work under the terms of the contract an you
may proceed under protest. You must comply with the contract reouirements of submittina a written protest to protect your claim.
Originals: City Clerk, Contractor cc: Engineering project file, Project Manager
1243 National City Boulevard, National City, CA 91950 Telephone (619) 336-4380
MIRAN CHANGE ORDER NO. 1
ROOIFI
G"' 875 34th Street, San Diego, CA 92102
--,�° '_<�> "t P: (619) 276-1700 F: (619) 276-1703
CA License No. 764917
owner's Name:
City of National City
Owner's Address:
1243 National City Blvd.
Owner's City:
National City, CA
Owner's Zip Code:
91950
Atten:
Luca Zappiello
Owner's Work Phone:
(619) 336-4380
Project Name & Address:
City Hall, 1243 National City Blvd. & Library 1401 National City Blvd., National City, CA 91950
Email:
Iappiello@nationalcityca.gov
In conformance with and as a part of the existing contract dated 6-21-18 Preman Roofing Inc. is hereby authorized by the
OWNER or OWNERS AUTHORIZED AGENT to make change (s) to the above project and/or order any additional labor and materials, services,
supplies and other items listed below and/or otherwise needed to complete the requirements of the scope of work of this change order.
a. Scope of the extra work or changes :
Fxtend ritrh arnlind communication rabies and install 74 gaugegalvani7ed rap•
b. Payments for this order to be made as follows and will effect the schedule of progress payments as follows:
PREVIOUS contract total amount prior to this Change Order: $304,410.00
Date of completion as set forth in the existing
4
This Change Order will result in a DEDUCTION to the
original contract price in the lump sum amount of•
contract is hereby extended days
because of the time necessary to complete this
Change Order.
This Change Order will result in an INCREASE to the
original contract price in the lump sum amount of• $15,062.00
REVISED contract total amount including this Change Order: $319,472.00
OWNER ACCEPTANCE: This change order shall be performed under the same conditions as specified in the existing contract. Your
signature below signifies your agreement and approval of this change order.
By: Date•
(signature of owner or authorized agent) (date of signing of this change order)
CONTRACTOR ACCEPTANCE: Preman Roofing Inc., agrees to perform this change order in accordance with the above conditions,
specifications and stated price.
By• Date:
(signature of contractor or authorized agent) (date of signing of this change order)
PROJECT NAME: City Hall Roof Replacement
CIP NO. 18-08
Contractor: Preman
Reason/Purpose for this Change Order:
The City of National City has a separate contract with Ameresco to install solar equipment on the upper roof.
To preserve the warranty of the new TPO roof system, additional slip sheets are needed for the ballast
system of the solar equipment to rest on.
CHANGE ORDER NO. 4
August 28, 2018
The City of National City and Contractor agree to the following change to the original Contract:
The City and the Contractor agree that the Contractor shall proceed with providing 320 2'x3' TPO slip sheets
to The City. The City will fumish the materials to Ameresco, who will install the slip sheets as necessary.
Original Contract Amount
Net change by previously authorized Change Orders
Subtotal
Amount of this change order
304,410.00
12,362.00
316,772.00
3,380.00
New contract amount $ 320,152.00
Working days added: 4 Working days subtracted: 0 Percent change in Contract to date 5.17%
ubmit -d
Ap. o -/by:
Date T
8/zq li
Dale
fr
CS
City Manager, required for Change Orders>$24,999 Date
By signing this Ch e Order the Contractor confirms that he/she is completely familiar with its terms and conditions and has fairly negotiated its
price, terms and co itions. If this Change Order is approved, Contractor will provide all of the equipment, materials and labor necessary to provide a
complete work as described above at that the price stated herein. Additionally, Contractor confirms that the price is fair and complete and represents
all costs associated with the work, including but not limited to all equipment, materials, labor, supervision, overhead, fees, bonds, insurance, profit, etc.
and that there will be no further compensation. All of the terms and conditions of the original contract documents are incorporated herein.
CONTRACTOR NAME: Preman
Date
ote to Contractor: I(you .o not - • with t is ange •rder you may . - .erect-. to proc--. wit t is work un. -r t e terms o
may proceed under protest. You must comply with the contract reauirements of submittina a written protest to protect your claim.
Originals: City Clerk, Contractor cc: Engineering project file, Project Manager
1243 National City Boulevard, National City, CA91950
Telephone(619) 336-4380
PREMAN
w
Owner's Name:
Cityof National City
Owner's City:
National City, CA
Owner's Zip Code:
91950
Owner's Address:
1243 National City Blvd.
Atten:
LucaZappiello
Owner's Work Phone:
(619)336-4380
BID P
875 34th Street, San Diego, CA 92102
P: (619) 276-1700 F: (619) 276-1703
CA License No. 764917
Project Name & Address:
City Hall, 1243 National City Blvd., National City, CA 91950
Email:
Izappiello@nationalca.gov
a. Scope of Work: Preman Roofing Inc. hereby submits the following specifications and estimates:
PROPOSAL FOR SLIP SHEETS
#1. Provide (320) 2'x3'TPO slip sheetsforAmeresco.
b. Not Included: This proposal does not include: Otherthanstatedabove.
c. WE PROPOSE to furnish material, equipment and labor in accor-
dance with the above specifications for the sum of:
$3,380.00 dollars
NOTE: This proposal may be withdrawn if not accepted within
30 days from 8-23-2018
date
Respectfully submitted by: David Rodriguez
Company Representative
d. WE ACCEPT the prices, specifications, and terms as stated in this
bid proposal are approved. We authorize you to draw up all neces-
sary contract documents so work can begin.
approved and accepted (owner or owner's authorized agent) date
approved and accepted (second owner - if any) date
Page ONE of 1 Total Pages
CITY OF NATIONAL CITY
Office of the City Clerk
1243 National City Blvd., National City, California 91950-4397
619-336-4228
Michael R. Dalla, CMC - City Clerk
PREMAN ROOFING AND SOLAR
CITY HALL ROOF REPLACEMENT, CIP NO. 18-08
CHANGE ORDERS #1 THROUGH #4
Judy Hernandez (Engineering/Public Works) forwarded copies of the
Change Orders to Preman Roofing and Solar.