Reason/Purpose for this Change Order:
1. Public Library Wattstopper System Repairs: The City asked Ameresco for a scope and price to repair and improve the
existing Wattstopper lighting control system at the Public Library; 2. MLK Community Center Temperature Sensor
Additions: During wireless thermostat construction at the MLK Community Center, Ameresco discovered that the placement
of three wall -mounted thermostats was not good for proper system operation. At the City's direction, Ameresco added three
duct -mounted sensors to address the issue; 3. Extension of Time: The City and Ameresco mutually agreed in March 2018
that it was in the City's best interest for the City to re -roof the Civic Center and Police Station before Ameresco installed solar
power systems on the two buildings. The City and Ameresco agreed in principal that Ameresco would extend the duration of
its work at no additional cost to the City, provided that the City would extend the project completion date.
The City of National City and Contractor agree to the following change to the original Contract:
1) Public Library Wattstopper System Repairs - Attachment E; 2) MLK Community Center Temperature Sensor
Additions - Attachment F; 3) Extension of Time. See attached Change Order Request No. 1 Revision 2 dated
August 14, 2018 for backup. Contract completion has been extended to January 3, 2019.
Original Contract Amount $ 5,403,308.00
Net change by previously authorized Change Orders
Subtotal 5,403,308.00
Amount of this change order 6,124.00
New contract amount
Calendar days added: 142 Working days subtracted: 0 Percent change in Contract to date 0.11%
Submitted by: n ,
Project Manager
Date !City Pect Ma er
erfiglie
Date
Approved by:
•
=Citngineer Date City Manager, required for Change Orders>$24,999 Date
By signing this Change Order the Contractor confirms that he/she is completely familiar with its terms and conditions and has fairly
negotiated its price, terms and conditions. If this Change Order is approved, Contractor will provide all of the equipment, materials and
labor necessary to provide a complete work as described above at that the price stated herein. Additionally, Contractor confirms that the
price is fair and complete and represents all costs associated with the work, including but not limited to all equipment, materials, labor,
supervision, overhead, fees, bonds, insurance, profit, etc. and that there will be no further compensation. All of the terms and conditions of
the original contract d. - -n s are incorpora e. • erein. (2 originals: 1 for City Clerk, 1 for Contractor)
Accepte
dagreedtob u
Nam . Date
Note o Lontrac . '. i .. of agree with tniS Change urger you may oe directed to proceed wan tms work under the terms ofthe
contract and you may proceed under protest. You must comply with the contract requirements of submitting a written protest to protect your
claim.
Originals: City Clerk, Contractor cc: Engineering project file, Project Manager
9/t7/,c
1243 National City Boulevard, National City, CA 91950
Telephone (619) 336-4380
AMERESCO
Green • Clean • Sustainable
Attachment A - Change Order Request No. 1, Revision 2
Change Request Number: 1, Revision 2
Customer: City of National City
Project Number: 73456-20
Contract: Energy Services Agreement dated June 20, 2017
I. REQUEST DATE: August 14, 2018
1.
Requested By
Scott Wentworth, Senior Project Manager
2.
Description of Changes
Public Library Wattstopper System Repairs — Att. E
MLK Community Center Temperature Sensor Additions — Att. F
Extension of Time
3.
Addition or Deduction from Contract Price
Addition
4.
Change to Contract Amount
$ 6,124
II. AMERESCO's AGREEMENT
With respect to all costs involved in this change, and subject to Subsection 8 of the Agreement, Ameresco
proposes to perform the work described in this Change Order, in accordance with the provisions of the
Agreement and in exchange for the payment and extension of time specified below, and Ameresco certifies
that the attached cost data is accurate, complete and current, and mathematically correct.
Payment shall be made on the basis of:
(X) Lump sum "not -to -exceed" increase:
$ 6,124
Contract Time will be Increased by: 142 calendar days
III. CONTRACT ADJUSTMENT
Contract Award $ 5,403,308.00
Previous Additions $ 0.00
Previous Deductions $ 0.00
Net Total $ 5,403,308.00
This Change $ 6,124.00
Total Contract Amount $ 5,409,432.00
Amer
Original Substantial Completion Date
Additional Days for Completion
Revised • • - • Date
11
Date:
August 14, 2018
142 calendar days
January 3, 2019
City of National City:
By:
Title:
Date:
AMERESCO
GT • Clean • Si.stainabie
Change Order Request #1
Attachment E - Wattstopper Upgrade for Public Library Lighting
Controls
General Description
> ECM Summary
Ameresco was asked to propose upgrades to the existing Wattstopper lighting control panel at the Public
Library because several circuits were no longer functioning. In some cases, the panel's relays had failed
and prior maintenance staff bypassed the relays and hard -wired the system to enable the lighting
continuously. For example, the parking lot fixtures run continuously. In other cases, clock system
maintenance is necessary to properly schedule the control's timing.
In the course of evaluating this opportunity, we met David Johnson, the person who originally installed
the Wattstopper system. David has the original records for the system and can use them as a tool when
planning the retrofits with Ameresco and the City. David maintains a lot of Wattstopper panels similar to
the system at the Public Library, and he has seen many analog controllers (like the product at the Public
Library) fail due to age. These analog controllers are obsolete and no longer manufactured.
Recommended Modifications
Ameresco will replace the existing analog controllers with new digital hardware and associated software.
This equipment will be accessible via the internet
Product literature is included in Attachment G.
All of these retrofits will comply with the 2016 California Energy Code requirements for lighting controls.
Detailed Project Scope
The following is included in the Wattstopper controller upgrade scope of work:
• Survey the configuration of the existing controls.
• Review the controller operation with City staff and jointly determine the configuration and settings of
the controller.
• Retrofit existing analog controller with a Wattstopper LIA-WEB controller using the City's stated
sequence of operations.
• Repair inoperable ancillary controls within the Wattstopper panel.
• Reconnect wiring that is currently disconnected inside the controller according to the jointly agreed
configuration.
• Provide internet interface and associated graphics.
• Start up and commission the system according to Wattstopper directions included in Change Order
documentation.
2
AMERESCO
Green • Clean • Sustainable
Change Order Request #1
• Cleanup work area and dispose of any construction debris in Ameresco-supplied waste bins and
remove from site.
• On site training at a time after the modifications, on a mutually agreeable date.
> Exclusions
• Asbestos or lead sampling, testing or removal.
• Repair of existing damaged or faulty electrical equipment and wiring outside of the existing
Wattstopper controller panel.
• Electrical distribution system upgrades required to meet current electrical codes.
• Engineering or modification of fire alarm or life safety equipment.
• Stamped and signed engineering plans and specifications.
Assumptions
Assumptions made in the development of this proposal include:
• All work surfaces are free of asbestos and other hazardous materials. CNC is responsible for any
hazardous material abatement.
• The cost of the project does not include any repair or upgrades of existing electrical distribution
systems that are not up to current codes.
Utility Interruptions
Interruptions of lighting system operation will occur, however, they will be isolated to the area of work
and their duration minimized through carefully planned installation phasing. Installation schedules will be
coordinated with site personnel to minimize the impact on building occupants.
Other
> Equipment Service Life
The equipment service life for the major components includes:
• Replacement relays - 40,000 operations.
> Warranty
Ameresco provides a 1-year warranty for materials and labor for the retrofit.
3
AMERESCO
Green • Clean • Sustainable
Change Order Request #1
Attachment F — MLK Community Center Temperature Sensor Additions
General Description
> ECM Summary
Early in the operation of the wireless temperature controls Work at the MLK Community Center, the City
and Ameresco realized that existing thermostat locations were not supporting temperature control. After
discussing options, the City directed Ameresco to add three temperature sensors to return air ducts.
Modifications
Add three temperature sensors, integrated into the wireless temperature controls Work.
Detailed Project Scope
The following Work was provided:
• Add a duct mounted temperature sensor to HP-02.
• Add a duct mounted temperature sensor to HP-09.
• Add a duct mounted temperature sensor to HP-10.
• Integrate details related to these sensors into the training and operations & maintenance manuals.
> Exclusions
• Asbestos or lead sampling, testing or removal.
• Electrical distribution system upgrades required to meet current electrical codes.
• Engineering or modification of fire alarm or life safety equipment
• Stamped and signed engineering plans and specifications
Assumptions
Assumptions made in the development of this proposal include:
• All work surfaces are free of asbestos and other hazardous materials. CNC is responsible for any
hazardous material abatement.
• The cost of the project does not include any repair or upgrades of existing electrical distribution
systems that are not up to current codes.
Utility Interruptions
All known utility interruptions have occurred.
Other
> Warranty
Ameresco provides a 1-year warranty for materials and labor for the retrofit.
4
AMERESCO
Green • Clean • Sustainable
Attachment H - Cost Breakouts
Change Order Request #1
Change Order Item
Additional Cost
Public Library Wattstopper System Repairs per Attachment E •
$4,652
MLK Community Center Temperature Sensor Additions Per Attachment F
$1,472
Extension of Time
$0
Total for This Change Order
$6,124
5
CITY OF NATIONAL CITY
Office of the City Clerk
1243 National City Blvd., National City, California 91950-4397
619-336-4228
Michael R. Dalla, CMC - City Clerk
AMERESCO
AMERESCO ENERGY SERVICES AGREEMENT,
CIP No. 17-03
Change Order #1
Judy Hernandez (Engineering/Public Works) forwarded
a copy of the Change Order to Ameresco.