NATIO1AL CITY
INCORPORATED
Citywide Pedestrian Midblock Crossing Enhancements
CIP No: 17-05
Contractor: Eagle Paving Company, Inc.
CHANGE ORDER NO. 15
August 29, 2018
Reason/Purpose for this Change Order:
The city directed the contractor to perform temporary striping on 16th.
The City of National City and Contractor agree to the following change to the original Contract:
The city directed the contractor to perform temporary striping on 16th from Highland Ave. to D St. The original
striping was to be removed and replaced, however, due to the deterioration of the existing roadway surface
the city has decided to delete the contract work, place temporary striping completing this portion of the
contract work. The temporary striping will be performed per the revised striping plan sheet 18 of 20 dated 2-
14-18 and plan sheet 19 of 20 dated 7/26/17. All work will be performed a the agreed lump sum price listed
below.
Original Contract Amount $ 1,158,297.70
Net change by previously authorized Change Orders 128,137.92
Subtotal 1,286,435.62
Amount of this change order 4,690.56
New contract amount $ 1,291,126.18
Working days added: 1
•tted by:
t Manager
roved by:
City%ngineer
rking days subtracted: 0
Date
Date
Percent change in Contract to date 11.47%
City Manager, required for Change Orders >$24,999 Date
By signing this Change Order the Contractor confirms that he/she is completely familiar with its terms and conditions and has fairly
negotiated its price, terms and conditions. If this Change Order is approved, Contractor will provide all of the equipment, materials and
labor necessary to provide a complete work as described above at that the price stated herein. Additionally, Contractor confirms that the
price is fair and complete and represents all costs associated with the work, including but not limited to all equipment, materials, labor,
supervision, overhead, fees, bonds, insurance, profit, etc. and that there will be no further compensation. All of the terms and conditions
of the original contract documents are incorporated herein. (2 originals: 1 for City Clerk, 1 for Contractor)
ted and agreed to by Eagle Paving Company, Inc:
Cf P
Date
Note to Contractor: If you do not agree with this Change Order you may be directed to proceed with this work under the terms of the
contract and you may proceed under protest. You must comply with the contract requirements of submitting a written protest to protect
your claim.
Originals: City Clerk, Contractor cc: Engineering project file, Project Manager
1243 National City Boulevard, National City, CA 91950
Telephone (619) 336-4380