HomeMy WebLinkAbout2018 CON Dick Miller, Inc. - Citywide Alley Improvements, CIP 16-11 - - Notice of CompletionPLEASE COMPLETE THIS INFORMATION
RECORDING REQUESTED BY:
City Engineer
City of National City
1243 National City Blvd.
National City, CA 91950
AND WHEN RECORDED MAIL TO:
City Engineer
City of National City
1243 National City Blvd.
National City, CA 91950
DOC# 2018-0523560
111 I IU 011 111 III I I III II IIII10011 II
Dec 21, 2018 10:24 AM
OFFICIAL RECORDS
Ernest J. Dronenburg, Jr.,
SAN DIEGO COUNTY RECORDER
FEES: $0.00 (SB2 Atkins: $0.00)
THIS SPACE FOR RECORDER'S USE ONLY
PAGES: 4
(Note: This document is recorded on behalf of the City of National City, a municipal corporation, and is exempt
from Recorder's fees pursuant to Government Code Section 27383)
NOTICE OF COMPLETION:
CITYWIDE ALLEY IMPROVEMENTS , CIP No. 16-11
THIS PAGE ADDED TO PROVIDE ADEQUATE SPACE FOR RECORDING INFORMATION
(Additional recording fee applies)
RECORDING REQUESTED BY
WHEN RECORDED MAIL TO:
NAME: CITY OF NATIONAL CITY
ADDRESS: 243 NATIONAL CITY BOULEVARD
NATIONAL CITY, CA 91950
NOTICE OF COMPLETION
CALIFORNIA CIVIL CODE SECTION 3093
NOTICE IS HEREBY GIVEN of the completion on June 18, 2018 of the:
Citywide Alley Improvements Project, CIP No. 16-11
Work of improvement or portion of work of improvement under construction or alteration.
The project included 11 alleys citywide in National City, CA 91950
Street Address City State Zip
Code
The undersigned owns the following interest or estate in said property:
Owner in fee
Nature of the interest or estate of owner (mortgagor, lessee, etc.)
Said work of improvement was performed on the property pursuant to a contract with
Dick Miller, Inc
Name of Original Contractor
The following work and material were supplied:
Labor provided: General Laborer. Materials: Concrete, aggregate base, asphalt, Equipment:
excavation and paving equipment.
General statement of kind of labor, services, equipment or materials
The names and addresses of co -owners are: N/A
Dated: June 18, 2018;
Joint ten nants in common, or other owners
'gnat re of Owner
City of National City, 1243 National City Blvd., National City, CA 91950
I, the undersigned, say: I have read the foregoing Notice of Completion and know the contents
thereof; the same is true of my own knowledge. I declare under penalty of perjury that the forgoing
is true and correct.
Executed on June ' 018 at, National City, California.
Signature:
MORRISON, MAYOR
Noc 16-11
RESOLUTION NO. 2018 — 175
RESOLUTION OF THE CITY COUNCIL OF THE CITY OF NATIONAL CITY
ACCEPTING THE WORK PERFORMED BY DICK MILLER, INC. FOR
THE CITYWIDE ALLEY IMPROVEMENTS PROJECT, APPROVING THE FINAL
CONTRACT AMOUNT OF $987,241.97, AUTHORIZING THE RELEASE OF
RETENTION IN THE AMOUNT OF $49,362.10 FROM DICK MILLER INC.'S
ESCROW ACCOUNT, AND AUTHORIZING THE MAYOR TO EXECUTE
THE NOTICE OF COMPLETION FOR THE PROJECT
BE IT RESOLVED by the City Council of the City of National City as follows:
It appearing to the satisfaction of the Engineering Department that all work
required to be done by Dick Miller, Inc., for the total final contract amount of $987,241.97, for the
Citywide Alley Improvements Project (CIP No. 16-11; 2) has been completed, the City Council
of National City hereby accepts said work, ratifies the release of the retention in the amount of
$49,362.10 from Dick Miller Inc.'s escrow account, authorizes the Mayor to execute the Notice
of Completion, and orders that payment for said work be made in accordance with said contract.
PASSED and ADOPTED this 16th day of October, 2018.
ATTEST:
r-L9-1
Michael R. f alla, City Clerk
APPROVED AS TO FORM:
orr s-Jones
y Attorney
Passed and adopted by the Council of the City of National City, California, on
October 16, 2018 by the following vote, to -wit:
Ayes: Councilmembers Cano, Mendivil, Morrison, Rios, Sotelo-Solis.
Nays: None.
Absent: None.
Abstain: None.
AUTHENTICATED BY: RON MORRISON
Mayor of the City of National City, California
MICHAEL R. DALLA
City Clerk of the City of National City, California
By:
Deputy
I HEREBY CERTIFY that the above and foregoing is a full, true and correct copy of
RESOLUTION NO. 2018-175 of the City of National City, California, passed and
adopted by the Council of said City on October 16, 2018.
City Clerk of the City of National City, California
By:
CITY OF NATIONAL CITY, CALIFORNIA
COUNCIL AGENDA STATEMENT
cZo/--51
MEETING DATE: October 16, 2018
AGENDA ITEM NO. 6
,'EM TITLE:
Resolution of the City Council of the City of National City: 1) accepting the work performed by Dick
Miller, Inc. for the Citywide Alley Improvements Project, CIP No. 16-11; 2) approving the final contract
amount of $987,241.97; 3) authorizing the release of retention in the amount of $49,362.10 from the
Dick Miller Inc.'s escrow account; and 4) authorizing the Mayor to sign the Notice of Completion for the
project.
PREPARED BY: Jose Lopez,
PHONE: 619-336-4312
EXPLANATION:
See attached.
ssistant Engineer - Civil DEPARTMENT: Engineering/Public Works
APPROVED BY:
NANCIAL STATEMENT:
ACCOUNT NO.
N/A
ENVIRONMENTAL REVIEW:
N/A
ORDINANCE: INTRODUCTION:
FINAL ADOPTION:
APPROVED:
APPROVED:
Finance
MIS
STAFF RECOMMENDATION:
Adopt Resolution accepting the work performed by Dick Miller, Inc. for the Citywide Alley Improvements
Project, CIP No. 16-11 and approving the final contract amount of $987,241.97.
BOARD / COMMISSION RECOMMENDATION:
N/A
ATTACHMENTS:
1. Explanation
2. Notice of Completion
3. Final Contract Balance Report
4. Resolution
,b + ylo. P1k-14S
EXPLANATION
The project included reconstructing eight existing alleys subject to drainage issues with
new concrete alleys, recompacting / soil stabilization for two dirt alleys (see Locations
10 and 11 on the attached project location map), and installation of pedestrian curb
ramps for American with Disabilities Act (ADA) compliance. One additional alley was
recompacted and stabilized under Change Order #2.
On August 2, 2017, the bid solicitation was posted on PlanetBids, a free public
electronic bidding system for contractors. On August 3, 2017 and August 10, 2017, the
bid solicitation was advertised in local newspapers.
On August 22, 2017, six (6) bids were received electronically on PlanetBids by the
11:00 a.m. deadline. Bid results were available immediately after the 11:00 a.m.
deadline. Dick Miller, Inc. was the apparent lowest bidder with a total bid amount of
$939,939.93 as the basis of award. Upon review of all documents submitted, Dick
Miller, Inc.'s bid was deemed responsive, and they were the lowest responsible bidder
qualified to perform the work as described in the project specifications.
On September 5, 2017, the City Council adopted Resolution No. 2017-169 awarding the
contract to Dick Miller, Inc., in the not -to -exceed amount of $939,939.93.
Construction started on November 9, 2017 and was completed on June 15, 2018.
The change orders issued for this project are detailed in the Final Contract Balance
Report (see attached). The change orders increased the contract by $51,834.24, while
line item adjustments decreased the contract by $4,532.20 for a net contact increase of
$47,302.04. This results in a 5% contract increase for a final contract balance of
$987,241.97.
As a result of satisfactory completion of the project, staff recommends that City Council,
1) accept the work of Dick Miller, Inc. for the Citywide Alley Improvements Project, CIP
No. 16-11; 2) approve the final contract amount of $987,241.97; 3) authorize the release
of retention in the amount of $49,362.10 from Dick Miller Inc.'s escrow account; and 4)
authorize the Mayor to sign the Notice of Completion for the project.
The Notice of Completion will be filed with the San Diego County Recorder's Office.
-1-
RECORDING REQUESTED BY
WHEN RECORDED MAIL TO:
NAME: CITY OF NATIONAL CITY
ADDRESS: 243 NATIONAL CITY BOULEVARD
NATIONAL CITY, CA 91950
NOTICE OF COMPLETION
CALIFORNIA CIVIL CODE SECTION 3093
NOTICE IS HEREBY GIVEN of the completion on June 18, 2018 of the:
Citywide Alley Improvements Project, CIP No. 16-11
Work of improvement or portion of work of improvement under construction or alteration.
The project included 11 alleys citywide in National City, CA 91950
Street Address City State Zip
Code
The undersigned owns the following interest or estate in said property:
Owner in fee
Nature of the interest or estate of owner (mortgagor, lessee, etc.)
Said work of improvement was performed on the property pursuant to a contract with
Dick Miller, Inc
Name of Original Contractor
The following work and material were supplied:
Labor provided: General Laborer. Materials: Concrete, aggregate base, asphalt, Equipment:
excavation and paving equipment.
General statement of kind of labor, services, equipment or materials
The names and addresses of co -owners are: N/A
Dated: June 18, 2018;
Joint tenants, tenants in common, or other owners
Signature of Owner
City of National City, 1243 National City Blvd., National City, CA 91950
I, the undersigned, say: I have read the foregoing Notice of Completion and know the contents
thereof; the same is true of my own knowledge. I declare under penalty of perjury that the forgoing
is true and correct.
Executed on June 18, 2018 at, National City, California.
Signature:
RON MORRISON, MAYOR
Noc 16-I I
-2-
FINAL CONTRACT BALANCE
DATE: September 7, 2018
PROJECT: Citywide Alley Project
FY 16-17
CIP No. 16-11
TO:
Dick Miller
930 Boardwalk, Suite H
San Marcos, CA 92078
ORIGINAL CONTRACT AMOUNT:
START DATE:
COMPLETION DATE:
ORIGINAL CONTRACT LENGTH:
EXTENTION OF WORK DAYS:
WORKING DAYS SUSPENDED:
TOTAL CONTRACT TIME:
DESCRIPTION:
$939,939.93
November 9, 2017
June 15, 2018
80 Working Days
37 Working Days
31 Working Days
148 Working Days
The Final Contract Balance reports final line item amounts and summarizes all change orders to produce
a final contract amount.
CHANGE ORDERS AND LINE ITEM ADJUSTMENTS:
Change Order #1 directed the contractor to excavate unsuitable material from alley 9, place Tensar Triax
geo fabric and then place additional base to stabilize grade for placement on concrete per contract. All
work was performed on a T&M basis. This Change Order total amount was $ 19,119.36.
Change Order #2 directed the contractor to clear and grub the alley south of 27th St. between A and B
Ave., field engineer and grade for positive water flow, process grade and recompact with soil binder as
identified in the project specifications. All soil binder work shall be completed at the contract unit price
and all additional work related to clearing, grubbing and grading shall be completed at an agreed lump
sum cost. Inclusive of all costs, the work was performed at an agreed price. This Change Order total
amount was $ 27,349.88.
Change Order #3 directed the contractor to delete the originally designed rip -rap at the end of Alley5
and replace it with a 12"x12" NDS catch basin and install PVC piping down the slope and outlet the PVC
pipe under the sidewalk and through the curb. The NDS catch basin will be surrounded with a small
-3-
FINAL CONTRACT BALANCE
Citywide Alley Project
CIP No. 16-11
3'x3' concrete slab with a curb on three sides to direct the water flow into the basin. All work was
performed at an agreed price. This Change Order total amount was $ 5,365.00.
All Change Orders listed above increased the total contract amount by $ 51,834.24.
Numerous contract line item adjustments per the attached FINAL BILLING STATEMENT resulted in a total
decrease of $ 4,532.20. Including change orders and line item adjustments, the total contract resulted
in an increase of $ 47,302.04.
CONTRACT ADJUSTMENT:
As a result of the above change orders and line item adjustments, the contract price is adjusted as
follows:
1. The final contract price is adjusted to $ 987,241.97.
2. As a result of the satisfactory completion of said project, a retention amount of $ 49,362.10 is
set to be processed and released from the contractor's escrow account upon the receipt of
signatures and City Council's ratification of this agreement and the Notice of Completion.
This document and its purpose to balance payment shall be considered full compensation for furnishing
and installing the materials, labor, tools and equipment, profit, overhead, and all incidentals for
performing the work described above. Dick Miller will not be entitled to damages or additional payment
for delays as described in the 2015 edition of the Standard Specifications for Public Works Construction,
Section 6-6.3, for performing the work as described above.
-4-
RESOLUTION NO. 2018 —
RESOLUTION OF THE CITY COUNCIL OF THE CITY OF NATIONAL CITY
ACCEPTING THE WORK PERFORMED BY DICK MILLER, INC. FOR
THE CITYWIDE ALLEY IMPROVEMENTS PROJECT, APPROVING THE FINAL
CONTRACT AMOUNT OF $987,241.97, AUTHORIZING THE RELEASE OF
RETENTION IN THE AMOUNT OF $49,362.10 FROM DICK MILLER INC.'S
ESCROW ACCOUNT, AND AUTHORIZING THE MAYOR TO EXECUTE
THE NOTICE OF COMPLETION FOR THE PROJECT
BE IT RESOLVED by the City Council of the City of National City as follows:
It appearing to the satisfaction of the Engineering Department that all work
required to be done by Dick Miller, Inc., for the total final contract amount of $987,241.97, for the
Citywide Alley Improvements Project (CIP No. 16-11; 2) has been completed, the City Council
of National City hereby accepts said work, ratifies the release of the retention in the amount of
$49,362.10 from Dick Miller Inc.'s escrow account, authorizes the Mayor to execute the Notice
of Completion, and orders that payment for said work be made in accordance with said contract.
PASSED and ADOPTED this 16th day of October, 2018.
Ron Morrison, Mayor
ATTEST:
Michael R. Dalla, City Clerk
APPROVED AS TO FORM:
Angil P. Morris -Jones
City Attorney
CITY OF NATIONAL CITY
Office of the City Clerk
1243 National City Blvd., National City, California 91950-4397
619-336-4228
Michael R. Dalla, CMC - City Clerk
DICK MILLER
Citywide Alley Improvements Project,
CIP No. 16-11
Notice of Completion
Judith Hernandez (Engineering/Public Works) forwarded a copy of the Notice of
Completion to Dick Miller.