HomeMy WebLinkAbout2018 CON Preman Roofing - City Hall Roof Replacement, CIP No. 18-08 - Change Orders #7 and 8PROJECT NAME: City Hall Roof Replacement
CIP NO. 18-08
Contractor: Preman
Reason/Purpose for this Change Onier.
During construction of the new mechanical penthouses by AMERESCO, the previously existing
counterflashing for the new TPO roof was removed. This change order is necessary to provide proper
waterproofing and roofing membrane termination along the perimeter of both penthouses.
CHANGE ORDER NO. 7
December 28, 2018
The City of National City and Contractor agree to the following change to the original Contract:
The City and the Contractor agree that the Contractor shall install new counterflashing appurtenant
waterproofing around the perimeter of the two mechanical penthouses located on the upper roof.
Original Contract Amount .,.. $ 304,410.00
Net change by previously authorized Change Orders ;
Subtotal
Amount of this change order .
New contract amount
16,482.00
320,892.00
2,388.00
323,280.00
............... r/9/it
ngineer Date City, Manag er,_regredfor Charm order.>$24,flss Date
By signing this Change Order the Contractor confirms that he/she is completely familiar with its terms and conditions and has fairly negotiated its
price, terms and conditions. If this Change Order is approved, Contractor will provide all of the equipment, materials and labor necessary to provide a
complete work as described above at that the price stated herein. Additionally, Contractor confirms that the price is fair and complete and represents
all costs associated with the work, including but not limited to all equipment, materials, labor, supervision, overhead, fees, bonds, insurance, profit, etc.
and that there will be no further compensation. All of the terms and conditions of the original contract documents are Incorporated herein.
Name:
Noteio�ontractor:
greed to b CONTRACTOR NAME: Preman
Date %^
not agree wiEffithange you may b ectedTt proceed with this work under ttneTerms o~f tTie con1?acf awn you
may Proceed under protest You must comr v with the contract reouirements of submitting a written protest to protect your claim.
Originals: City Clerk, Contractor cc: Engineering project file, Project Manager
� p ► �E11II�W
y
Owner's Name:
City of National City
Owner's City:
National City, CA
Owner's Zip Code:
91950
Owner's Address:
1243 National City Blvd.
Atten:
Luca Zappiello
Owner's Work Phone:
(619)336-4380
875 34th Street, San Diego, CA 92102
P: (619) 276-1700 F: (619) 276-1703
CA License No. 764917
Project Name & Address: - - - National City Library, 1401 National City Blvd., National City, CA 91950
Email:
Izappiel lo@ nationa lca.gov
a. Scope of Work: Preman Roofing Inc. hereby submits the following specifications and estimates:
PROPOSAL FOR TPO REPAIR FOR LIBRARY
This proposal is based on replacingsmall section on TPO roofover roof leak. Roof drainsareinfairshape,but membrane isburned outdueto
age.
SCOPE OF WORK:
#1. Remove and haul away 4' x 20' section of TPO near drain.
#2. Install newTPOas needed tying into existing roof, roof drain and parapet wall.
b. Not Included: This proposal does not include: Other than stated above.
c. WE PROPOSE to furnish material, equipment and labor in accor-
dance with the above specifications for the sum of:
$2,275.00 dollars
NOTE: This proposal may be withdrawn if not accepted within
30 days from 12-27-2018
date
Respectfully submitted by:
David Rodriguez
Company Representative
d. WE ACCEPT the prices, specifications, and terms as stated in this
bid proposal are approved. We authorize you to draw up all neces-
sary contract documents so work can begin.
approved and accepted (owner or owner's authorized agent) date
approved and accepted (second owner - if any) date,
Page ONE of 1 Total Pages
PROJECT PROFESSIONALS CORPORATION
TRANSMITTAL COVER
To: National City Engineering Department
Project Name: National City City Hall Roof Replacement
CIP No. 18-08
ITEMS DELIVERED:
1. Change Order #7 & #8
Delivered by: ikfrz Project Professionals Corporation
Received by:
Date: / / q `
PROJECT NAME: City Hall Roof Replacement
CIP NO. 18-08
Contractor: Preman . .
Reason/Purpose for this Change Order:
Subsequent to the repairs authorized by Change Order 2, additional repars to the Library upper roof drains
were found necessary. This change order is for the removal and replacemet of 80 square feet of TPO
roofing membrane at the existing tripple roof drain location with welded seams at the parapet wall and
sloped circular roof area.
CHANGE ORDER NO. 8
December 28, 2018
The Cfty of National City and Contractor agree to the following change to the o►iginal Contract:
The City and the Contractor agree that the Contractor shall install new TPO membrane and appurtenant
waterproofing around the perimeter of the tripple roof drain area located on the upper circular sloped roof.
Original Contract Amount
Net change by previously authorized Change Orders
Subtotal
Amount of this change order
304,410.00
18,870.00
323,280.00
2,275.00
ew contract amount $ 325,555.00
ng days subtracted: 0 Percent change in Contract to date 6.95%
City.Lngineer / Date City Manager, required for Change orden> ,999 Date
By signing this Change Order the Contractor confirms that he/she Is completely familiar with its terms and conditions and has fairly negotiated its
price, terms and conditions. If This Change Order is approved, Contractor will provide all of the equipment, materials and labor necessary to provide a
complete work as described above at that the price stated herein. Additionally, Contractor confirms that the price is fair and complete and represents
all costs associated with the work, including but not limited to all equipment, materials, labor, supervision, overhead, fees, bonds, insurance, profit, etc.
and that there will be no further compensation. All of the terms and conditions of the original contract documents are Incorporated herein.
NTRACTOR NAME: Preman
Name: "�" Date /- /
N`oteTo Con rt a tE r 1f not agree wit1hthIi Change Order you may be directed to proceed Wiff iis work under tTie terms of the contra— you
may proceed under protest. You must condo with the contract requirements of submitting a written protest to protect your claim.
Originals: City Clerk, Contractor cc: Engineering project file, Project Manager
All 116.
��p ► PREMAN
ROOFING -SOLAR
w
Owner's Name:
City of National City
Owner's City:
National City, CA
Owner's Zip Code:
91950
Owner's Address:
1243 National City Blvd.
Atten:
Luca Zappiello
Owner's Work Phone:
(619)336-4380
BID PROP ' . L
875 34th Street, San Diego, CA 92102
P: (619) 276-1700 F: (619) 276-1703
CA License No. 764917
Project Name & Address:
City Hall, 1243 National City Blvd., National City, CA 91950
Email:
Izappiello@nationalca.gov
a. Scope of Work: Preman Roofing Inc. hereby submits the following specifications and estimates:
PROPOSAL FOR COUNTERFLASHINGSATPENTHOUSES
This proposal is based on installing new 24 gauge galvanized skirt flashing underthe curbflashingthatwas installed duringthe penthouse
modifications.
SCOPE OF WORK:
#1. Install 4" 24 gauge galvanized counterflashingwith hem & drip, set in waterblockcaulking underneath penthouse drip metal.
#2. Secure with screws and neoprene washers.
b. Not Included: This proposal does not include: Otherthanstatedabove.
c. WE PROPOSE to furnish material, equipment and labor in accor-
dance with the above specifications for the sum of:
$2,388.00 dollars
NOTE: This proposal may be withdrawn if not accepted within
30 days from 12-20-2018
date
Respectfully submitted by: David Rodriguez
Company Representative
d. WE ACCEPT the prices, specifications, and terms as stated in this
bid proposal are approved. We authorize you to draw up all neces-
sary contract documents so work can begin.
approved and accepted (owner or owner's authorized agent)
approved and accepted (second owner - if any)
date
date
Page ONE of 1 Total Pages
CITY OF NATIONAL CITY
Office of the City Clerk
1243 National City Blvd., National City, California 91950-4397
619-336-4228
Michael R. Dalla, CMC - City Clerk
PREMAN
City Hall Roof Replacement,
CIP No. 18-08
Judith Hernandez (Engineering/Public Works) forwarded a duplicate original Agreement
to Preman.