HomeMy WebLinkAbout2019 CON Bert W. Salas - Las Palmas Storm Drain Repair Project, CIP No. 17-16 - Change Order #1Las Palmas Storm Drain Repairs
CIP No: 17-16
Contractor: Bert W. Salas, Inc.
CHANGE ORDER NO. 1
February 22, 2019
Reason/Purpose for this Change Order:
The city has directed the contractor to repair an unknown lateral line hit during excavation.
The City of National City and Contractor agree to the following change to the original Contract:
The contractor was directed to repair an unknown lateral line hit during excavation of the main storm drain
repairs. The 18" line was replaced and reconnected to the new 36" RCP. A concrete lug was poured around
the new connection. All worked was performed on a T&M basis for the lump sum price listed below.
Original Contract Amount $ 334,056.00
Net change by previously authorized Change Orders
Subtotal
Amount of this change order
New contract amount
Working days added: 1
Working days subtracted: 0
334,056.00
4,656.84
$ 338, 712.84
Percery change in Contract to date 1.39%
Su
' ted by:
roj
Man er Date
Cit
ro) ct Ma-ager
3/t4'
Date
oved by:
Ci ngineer Date
City Manager, required for Change Orders>$24,999 Date
By signing this Change Order the Contractor confirms that he/she is completely familiar with its terms and conditions and has fairly
negotiated its price, terms and conditions. If this Change Order is approved, Contractor will provide all of the equipment, materials and
labor necessary to provide a complete work as described above at that the price stated herein. Additionally, Contractor confirms that the
price is fair and complete and represents all costs associated with the work, including but not limited to all equipment, materials, labor,
supervision, overhead, fees, bonds, insurance, profit, etc. and that there will be no further compensation. All of the terms and conditions
of the original contract documents are incorporated herein. (2 originals: 1 for City Clerk, 1 for Contractor)
Accepted and agreed to by Bert W. Salas, Inc.
Name:
a Date I�
Note to Contractor: If you do not agree with this Change Order you may be directed to proceed with this work under the terms of the
contract and you may proceed under protest. You must comply with the contract requirements of submitting a written protest to protect
your claim.
Originals: City Clerk, Contractor
cc: Engineering project file, Project Manager
1243 National City Boulevard, National City, CA 91950
Telephone (619) 336-4380
CITY OF NATIONAL CITY
Office of the City Clerk
1243 National City Blvd., National City, California 91950-4397
619-336-4228
Michael R. Dalla, CMC - City Clerk
BERT W. SALAS
Change Order #1
Las Palmas Storm Drain Repairs,
CIP No. 17-16
Judith Hernandez (Engineering/Public Works) forwarded a copy of the
Change Order to Bert. W. Salas.