PROJECT NAME: Project Plaza Blvd Pedestrian Enhancements CHANGE ORDER NO. 3
CIP NO. 17-12 March 14, 2019
Contractor. L. C. Paving & Sealing
Reason/Purpose for this Change Order.
During construction, the team identified that no work for a concrete driveway was called out in the original bid
plans, however there was a bid line item for a commercial concrete driveway. The City elected to delete line
item #16 Concrete Driveway (SDRSD G-14D) and proceed with additional asphalt paving to repair the poor
paving in the area of the new crosswalk.
The City of National City and Contractor agree to the following change to the original Contract:
The City and the Contractor agree that the Contractor shall proceed with installing additional asphalt paving
at an agreed price of $3,040.00.
Amount of this change order 3,040.00
Working days added: Workin days subtracted: 0
Submitted by:
1
Pio]ect Manager
Approved by:
V/7
....�-��..... .
C/Engineer % Date City Manager. rvaradfQa111g.ormr.>rx4,ae® Date
By signing this Change Order the Contractor confirms that he/she is completely familiar with its terms and conditions and has fairly negotiated its
price, terms and conditions. If this Change Order is approved, Contractor will provide all of the equipment, materials and labor necessary to provide a
complete work as described above at that the price stated herein. Additionally, Contractor confirms that the price is fair and complete and represents
all costs associated with the work, including but not limited to all equpment, materials, labor, supervision, overhead, fees, bonds, insurance, profit, etc.
and that there will be no further compensation. All of the terms and conditions of the original contract documents are incorporated herein.
CONTRACTOR NAME: Plaza Blvd Pedestrian Enhancements
3/./.gh..9
Name: �!` Date
to Contractor: If you do agree with this Change Order you may be directed to proceed with thus work under the terms of the contract and you
may txoceed under protest. You must comdv with the contract reauirements of submittira a written oratest to protect your claim.
Originals: City Clerk, Contractor cc: Engineering project file, Project Manager
1243 National City Boulevard, National City, CA 91950 Telephone (619) 336-4380
Iy'R/YlNATED
ikRuuD mitA \\���\•
CITY OF NATIONAL CITY
Office of the City Clerk
1243 National City Blvd., National City, California 91950-4397
619-336-4228
Michael R. Dalla, CMC - City Clerk
L.C. PAVING & SEALING
Change Order #3
Plaza Blvd. Pedestrian Enhancements,
CIP No. 17-12
Judith Hernandez (Engineering/Public Works) forwarded a copy of the
Change Order to L.C. Paving & Sealing.