HomeMy WebLinkAbout2019 CON DBX, Inc. - Highland Avenue and E. 28th Street Traffic Signal Improvements, CIP No 18-04 - Change Order #2CIP NO. 18-04
Contractor: DBX, Inc.
42024 Avenida Alvarado Ste. A
Temecula, CA 92590
CALIFORNIA —
NATIONAL CITY
INcouroltAT£fl
HIGHLAND AVE & 28th ST TRAFFIC SIGNAL IMPROVEMENTS (HSIP) CHANGE ORDER NO. 2
April 4, 2019
This Change Order modifies Contractor's and the City's obligations and rights under the
abovementioned contract. This change order is not effective until approved by the City.
Time adjustment:
Fifty-seven (57) working days are added to contract time due to unforeseen delays for the delivery of
traffic signal materials and equipment.
Cost of Change Order:
There is no cost change to the original contract amount.
$0.00
Recommended by Project Manager:
Y
Date: 4. 4. 2010(
By signing this Change Order the Contractor confirm that he/s e is completely familiar with and has fairly
negotiated its price, terms and conditions. If this Change Order is approved, Contractor will provide all of the
equipment, materials and labor necessary to provide a complete work as described above at that the price
stated herein. Contractor confirms that the price is fair and complete and represents all costs associated with
the work, including but not limited to all equipment, materials, labor, supervision, overhead, fees, bonds,
insurance, profit, etc. and that there will be no further compensation. All of the terms and conditions of the
original contract documents are incorporated herein. The signer for the Contractor confirms that he/she is
authorized to bind the Contractor to this Change Order.
Agreed and Accepted by Contractor:
Print Name and TitleJ
( )James C. Perry, Presik�nt
�-0
C.(:)-€M--,
Date: �/I (4 19
Approved by City Engineer: /�
/ /
—
Date: 4' I I i et
Approved by City Manager:
(Required for change orders $25,000 and above)
il
Date:
PROJECT PROFESSIONALS CORPORATION
CHANGE ORDER MEMORANDUM
April 4, 2019
To: Stephen Manganiello
Director of Engineering & Public Works/City Engineer
Engineering and Public Works Department
City of National City
From: Vinnie Aguelo
Project Manager
Project Professionals Corp
Project: Highland Ave and E. 28th St Traffic Signal Improvement
CIP No.: 18-04
Subject: Change Order No. 2
Change Order No. 2 provides for:
Addition of fifty-seven (57) working days to the contract time.
Supporting Information:
Additional working days were required to bring the project to completion due to unforeseen delays for the
delivery of the signal standards and mast arms. One of three signal equipment manufacturers went bankrupt
resulting in production delays from the remain two manufacturers. It has been determined that there was a
delay of fifty-seven (57) working days due to this manufacturing disruption.
Time Adjustment:
It is recommended that 57 working days be added to the contract time.
Cost Adjustment:
Since the intervening cause was not due to the City's action or inaction there will be no additional costs to
the City associated with the addition of these working days.
Project Mana. - I Date
CITY OF NATIONAL CITY
Office of the City Clerk
1243 National City Blvd., National City, California 91950-4397
619-336-4228
Michael R. Dalla, CMC - City Clerk
DBX, INC.
Change Order #2
Highland Ave. & E. 28th Street Traffic Signal Improvements,
CIP No. 18-04
Judith Hernandez (Engineering/Public Works) forwarded a duplicate original Cto DBX, Inc.