CIP NO. 18-07
Contractor: WHILLOCK CONTRACTING
CHANGE ORDER NO. 9
April 17, 2019
Reason/Purpose for this Change Order:
The existing fence on the north side of the project near the site office at 302 W. 19th Street was being
utilized as a site perimiter control. The contractor was mobilized and working with handling and removing
impacted soil adjacent to the existing fence, at that time it was determined that it would be cost efficient to
have the contractor perform the following work; demo the existing perimiter fence, remove and grade the
existing slope to match impacted soil elevations and install temporary construction fence and windscreen
along the entrance of the site.
The City of National City and Contractor agree to the following change to the original Contract:
The City and the Contractor agree that the Contractor shall proceed with demoing the existing fence,
grading the slope and installing temporary fence with windscreen along the northern end of the project site.
This work is agreed by the City and the contractor to proceed under T&M and not to exceed $6,000. The
additional grading and removal of soil is under agreement by the City and the Contractor to be paid for as a
line item adjustment under Bid Line Item #11 Impacted Soil Handling (Export). The additional temporary
fence and windscreen is under agreement by the City and the contractor to be paid for as a line item
adjustment under Bid Line Item #15 Temporary Construction Fencing with Windscreen.
Amount of this change order
Working days added: 1 Working days subtracted: 0
3,192.68
Submitted by:
��i� l y
Dat
4)
11
Prbi Manager
Approved b :
Cit ngineer
f....
Date
?
City Manager, required for Charge Orders>$24,999 Date
By signing this Change Order the Contractor confirms that he/she is completely familiar with its terms and conditions and has fairly negotiated its
price, terms and conditions. If this Change Order is approved, Contractor will provide all of the equipment, materials and labor necessary to provide a
complete work as described above at that the price stated herein. Additionally, Contractor confirms that the price is fair and complete and represents
all costs associated with the work, including but not limited to all equipment, materials, labor, supervision, overhead, fees, bonds, insurance, profit, etc.
and that there will be no further compensation. All of the terms and conditions of the original contract documents are incorporated herein.
y WHILLOCK CONTRACTING:
Name:
r7f7
Date
Note to Contractor: If you do not agr - - - ith this Change Order you may be directed to proceed with this work under the terms of the contract and you
may proceed under protest. Y. ust comply with the contract reauirements of submittina a written protest to protect your claim.
Originals: City Clerk, C. tractor cc: Engineering project file, Project Manager
1243 National City Boulevard, National City, CA 91950 Telephone (619) 336-4380
CALIFORNIA
ubmitted
Al
`Ii'It()NfAL cnry
( INCORPORATE1
Paradise Creek Park Site Remediation & Improvements CHANGE ORDER NO. 10
CIP NO. 18-07 April 11, 2019
Contractor: WHILLOCK CONTRACTING
Reason/Purpose for this Change Order:
Prior to importing clean soil and placing the 3 foot cap over the impacted soil area, there is a need to survey,
locate, and excavate where the new lights will be installed for the park. Excavating and removing the
impacted soil in these 18 locations will allow for no impacted soil handling in the follow on project.
The City of National City and Contractor agree to the following change to the original Contract:
The City and the Contractor agree that the Contractor shall proceed with surveying, staking, and excavating
the new 18 light locations at an agreed lump sum price of $2,037. Approximately additional 40 Cubic Yards
will be excavated and handled, this will be paid for as an agreement between the City and the contractor as
a line item adjustment under Bid Line Item #11 Impacted Soil Handling (Export).
mount of this change order
rking days added: 1
by
1-1/7//c/
Proje'ctyivlanager Date
Working days subtracted: 0
Approved by:
Engineer
2,037.00
Date City Manager, required for Change Orders>$24,999 Date
By signing this Change Order the Contractor confirms that he/she is completely familiar with its terms and conditions and has fairly negotiated its
price, terms and conditions. If this Change Order is approved, Contractor will provide all of the equipment, materials and labor necessary to provide a
complete work as described above at that the price stated herein. Additionally, Contractor confirms that the price is fair and complete and represents
all costs associated with the work, including but not limited to all equipment, materials, labor, supervision, overhead, fees, bonds, insurance, profit, etc.
and that there will be no further compensation. All of the terms and conditions of the original contract documents are incorporated herein.
Accepted and agreed to by WHILLOCK CONTRACTING:
Name: Date
Note to Contractor: If you do not agree with this Change Order you may be directed to proceed with this work under the terms of the contract and you
may proceed under protest. You must comply with the contract requirements of submitting a written protest to orotect your claim.
Originals: City Clerk, Contractor cc: Engineering project file, Project Manager
1243 National City Boulevard, National City, CA91950 Telephone (619) 336-4380
OJECT PROFESSIONALS CORPORATION
TRANSMITTAL COVER
To: National City Engineering Department
Project Name: Paradise Creek Park Phase III
CIP No.: 18-07
ITEMS DELIVERED:
1. Invoice #5
2. Change Order #9 & #10
Delivered by: A
Received by:
Date:
Project Professionals Corporation
CITY OF NATIONAL CITY
Office of the City Clerk
1243 National City Blvd., National City, California 91950-4397
619-336-4228
Michael R. Dalla, CMC - City Clerk
WHILLOCK CONTRACTING
Change Orders #9 and #10
Paradise Creek Park Site Remediation and Improvements,
CIP No. 18-07
Judith Hernandez (Engineering/Public Works) forwarded a copy of the
Change Orders to Whillock Contracting.