HomeMy WebLinkAbout2019 CON Ameresco - Energy Services Agreement, CIP No. 17-03 - Change Order #6-- CALIFORNIA --
NATIOONAL CCM
S!3' f/
INCORPORATED
Ameresco Engergy Services Agreement
CIP No. 17-03
Contractor: Ameresco, Inc.
Reason/Purpose for this Change Order:
The attached Change Order Request No. 6 is for additional asbestos abatement activities that
were necessary to facilitate HVAC improvements in the Civic Center. This Change Order No. 6 also includes a deduction
for asbestos abatement completed by the City in the Civic Center Council Chambers and Large Conference Room, as a
result of a disturbance by Ameresco's subcontractor. Additionally, while removing one of the rooftop air handling units, a
sewer vent was discovered that needed to be extended through the penthouse roof.
CHANGE ORDER NO. 6
June 17, 2019
The City of National City and Contractor agree to the following change to the original Contract:
Unforseeen asbestos abatement and disposal in the Civic Center, a deduction for asbestos abatement
completed by the City in the Civic Center Council Chambers and Large Conference Room, and extending the
existing sewer vent from beneath the old Air Handling Unit #5 in the Civic Center roof.
Original Contract Amount $ 5,403,308.00
Net change by previously authorized Change Orders
Subtotal
31,368.41
5,434,676.41
Amount of this change order 5,859.13
New contract amount
Calendar days added:0 Working days subtracted: 0
Submitted by:
Project Manager
Approved by:
;City ngineer
8/1/2019
Date
8�t2//Z
Date
$ 5,440,535.54
Percent change in Contract to date 0.69%
City Project Manager Date
City Manager, required for Change Orders >$24,999 Date
By signing this Change Order the Contractor confirms that he/she is completely familiar with its terms and conditions and has fairly
negotiated its price, terms and conditions. If this Change Order is approved, Contractor will provide all of the equipment, materials and
labor necessary to provide a complete work as described above at that the price stated herein. Additionally, Contractor confirms that the
price is fair and complete and represents all costs associated with the work, including but not limited to all equipment, materials, labor,
supervision, overhead, fees, bonds, insurance, profit, etc. and that there will be no further compensation. All of the terms and conditions
of the original contract documents are incor.orated herein. (2 originals: 1 for City Clerk, 1 for Contractor)
Accepted and agreed to by AMERESCO Inc..
Na
Tv
contract
your claim.
Originals: City Clerk, Contractor
y/Si% i Date
witn tnis caanyeUrae-r you may- tie directea to proceed with thTt work and the term 61
you may proceed under protest. You must comply with the contract requirements of submitting a written protest to protect
cc: Engineering project file, Project Manager
sfiyia
1243 National City Boulevard, National City, CA 91950
Telephone (619) 336-4380
AMERESCO
Green • Clean • Sustainable
June 10, 2018
City of National City
1243 National City Blvd.
National City, CA 91950
Attention:
Regarding:
Dear Jose:
Jose Lopez
Project Manager
Change Order Request No. 6 for Varied Items
The attached Change Order Request No. 6 is proposed regarding several activities:
• Abating asbestos in the Civic Center from 8/25/19 until the present to facilitate HVAC work. None of
this abatement involved asbestos contaminated materials that were part of Ameresco's scope of
work; Ameresco paid separately for all abatement within its scope.
• A deduction within this change order for reimbursement from Ameresco to the City for Ameresco's
share of the City's payment to Central Valley Environmental to clean up asbestos in the City Council
Chambers and Large Conference Room per your e-mail of 1/24/19.
• Extending the existing sewer vent from beneath the old AHU 5 at the Civic Center. This vent was
located out of site beneath the air handler, and was discovered when the old unit was removed.
Ameresco engaged an engineer to design the work, and extended the vent up through the
penthouse roof.
Sewer vent was under old AHU-5
�. A
imiiir,,,,r"
. t dinimil ijii
135 S. State College Blvd, Suite 265, Brea, CA 92821
California State Contractor's License #817191 Class A, B, C10, C46
Jose Lopez
Change Order Request No. 6
June 10, 2019
Page 2
Cost
The total cost for this change order is $5,859.13, allocated as follows:
No.
Description
Amount
1.
Asbestos abatement for Civic Center second floor in September 2018.
Ameresco is not marking up the subcontractor's invoice.
$6,376.64
2.
Deduction for asbestos abatement by the City in the Civic Center Council
Chambers and the Large Conference Room per your e-mail of 1/24/19.
($4,180.40)
3.
Sewer vent extension from beneath AHU-5 in north penthouse.
$3,662.89
Total
$5,859.13
Extension of Time
No extension of time is requested for this change.
If you agree with this Change Order Request No. 6 as presented, please prepare the City's documents for
execution. If you would like to discuss this item, please contact me by e-mail, or by calling 510-684-7684.
Sincerely,
.14--Jasp-,
Scott Wentworth
Senior Project Manager
Attachments:
Change Order Request No. 6
C: Kevin Nissley
Kelsey Gormley
Dan Feld
135 S. State College Blvd, Suite 265, Brea, CA 92821
California State Contractor's License #817191 Class A, B, C10, C46
AMERESCO
Green • Clean • Sustainable
Change Order Request No. 6
Change Request Number: 6
Customer: City of National City
Project Number: 73456-20
Contract: Energy Services Agreement dated June 20, 2017
I. REQUEST DATE: June 10, 2019
1.
Requested By
Scott Wentworth, Senior Project Manager
2.
Description of Changes
Asbestos abatement by Ameresco's subcontractor, asbestos
cleanup by City's contractor, and sewer vent extension by
Ameresco's subcontractor, all at the Civic Center.
3.
Addition or Deduction from Contract Price
Addition
4.
Change to Contract Amount
$5,859.13
II. AMERESCO's AGREEMENT
With respect to all costs involved in this change, and subject to Section 8 of the Agreement, Ameresco proposes
to perform the work described in this Change Order, in accordance with the provisions of the Agreement and
in exchange for the payment specified below.
Payment shall be made on the basis of:
(X) Lump Sum for in the amount of:
Contract Time will be Increased by:
III. CONTRACT ADJUSTMENT
Contract Award
Previous Additions (Cos 1, 2, 3 & 5)
This Change
Total Contract Amount
$ 5,859.13
Zero calendar days
$ 5,403,308.00
$ 31,368.41
$ 5,859.13
$ 5,440,535.54
No changes to the Substantial Completion Date are included in this Change Order; however such
changes were approved under Change Order Request No. 1.
From: Jose Lopez
To: Wentworth. Scott;
Supporting details for Change Order No. 6 Item 1 regarding
ACM abatement in Civic Center 2nd FI. Although CO No 5 was
referenced below, ultimately this work is covered by Change
Order Reauest No. 6
Cc: grturoanationalcitvca.gov; Caruso. John; Gerdes, Eric
Subject: RE: Abating Asbestos at Civic Center Second Floor for HVAC
Date: Tuesday, September 25, 2018 5:22:48 PM
Caution - External Email
Scott,
I have spoken to our City Engineer, and the quote to complete the asbestos abatement is
acceptable. Please proceed with scheduling the work, and follow up with a formal change order
request #5.
Thanks,
Jose Lopez, PE
Assistant Engineer - Civil
City of National City
Engineering & Public Works Department
1243 National City Blvd
National City, CA 91950
Office: (619) 336-4380
Direct: (619) 336-4312
Fax: (619) 339-4397
E-mail: jlopezPnationalcityca.gov
The City of National City is open Monday through Thursday from 7:00 a.m.-6:00 p.m.; Offices are closed on Fridays.
For more information, please visit www.nationalcityca.gov. For more information regarding Capital Projects, please
visit www.nationalcityprojects.com
CAI.IFORUTA -*
NATIONAL CITY
iMCOR1011 At to
From: Wentworth, Scott [mailto:swentworth@ameresco.com]
Sent: Monday, September 24, 2018 4:52 PM
To: Jose Lopez <jlopez@nationalcityca.gov>
Cc: Arturo Gonzalez <arturog@nationalcityca.gov>; Caruso, John <jcaruso@ameresco.com>; Gerdes,
Eric <egerdes@ameresco.com>
Subject: Abating Asbestos at Civic Center Second Floor for HVAC
Jose,
May we have your approval by reply e-mail to have Ameresco's subcontractor abate asbestos on the
Civic Center's second floor at the locations indicated in the attached annotated drawing M1.3?
Item 1 support continued
Removing this asbestos contaminated material is essential to sustaining progress of the HVAC work
in the Civic Center.
The cost to the City for abating the material that is outside Ameresco's scope, which is all indicated
on Detail 1 of Sheet M1.3, is $7,500. Ameresco is not marking up the subcontractor's cost. With your
approval, we will process a change order requesting a reimbursement in the near future.
At this time, we do not know of other abatement that would be needed on the Civic Center second
floor.
If you approve this work promptly, we will schedule the abatement activities for Friday 9/28 and
Friday 10/5.
I've just returned from vacation today and am getting caught up on the all that's transpired. At the
moment I've focused on this particularly time -sensitive item. I'm available at 510-684-7684 if a
conversation would be useful.
With Best Regard,
Scott
Scott Wentworth
Sr. Project Manager
Ameresco
510.684.7684 cell
AMERESCO
Green • Clean • Sustanratrte
***NOTE: This e-mail may contain PRIVILEGED and CONFIDENTIAL information and is
intended only for the use of the specific individual(s) to which it is addressed. If you are not an
intended recipient of this e-mail, you are hereby notified that any unauthorized use,
dissemination or copying of this e-mail or the information contained in it or attached to it is
strictly prohibited. If you have received this e-mail in error, please delete it and immediately
notify the person named above by reply e-mail. Thank you.***
*** AMERESCO NOTICE *** Please send all suspicious email including spam, phishing or
anything you are unsure of to suspicious@ameresco.com
DATE: December 4, 2018
Item 1 support continued
west coast Air
Conditioning Co., Inc.
CHANGE ORDER REQUEST #013
PROJECT: National City HVAC Upgrade Project
Various Locations
BELOW IS A SUMMARY OF THE ATTACHED ITEMS REQUESTED FOR A FORMAL CHANGE ORDER
Acoustic spray above ceiling tile, see enclosed Janus Corporation
change order request.
WCA:
Colin M. Fisher, CEO
Ameresco, Inc.:
Scott Wentworth
5,490.00
COR Total 5,490.00
O&P 15% 823.50
Sub Total
Bond 1%
Grand Total
6,313.50
63.14
6,376.64
WEST COAST AIR CONDITIONING CO., INC. 1155 PIONEER WAY, SUITE 101 EL CAJON, CA 92020 PH.619-561-8000
Item 1 support continued
JANUS
CORPORATION
JANUS CHANGE ORDER (JCO) REQUEST #
DATE: 12/3/2018
TO: West Coast Air
1155 Pioneer Way, Suite 101
El Cajon, CA. 92020
DESCRIPTION OF WORK:
PROJECT: National City Civic Center
JOB #: 317349
CONTACT: Parker Crist
EMAIL: Parker Crist
RFI #: Ameresco 09/28/18 DRAWING:
Ameresco acoustic spray above ceiling tile 09/28/18
ROUGH ORDER OF MAGNITUDE:
LABOR
RATE
HOURS
TOTAL
DEMO
3A Sup.
$0.00
$0.00
3A
$0.00
$0.00
1A
$0.00
$0.00
ASB
SPEC II
$0.00
$0.00
Journeyman
$105.00
45
$4,725.00
Air Monitoric
Oversight
$85.00
9
$765.00
SUBTOTAL LABOR
$5,490.00
TOTAL $ 5,490.00
ista, CA 92081 • (760) 598-7374 • Fax (760) 598-8294 • don@januscorp,com
From: Jose Lopez
To: Wentworth. Scott
Cc: Caruso. John
Subject: RE: Civic Center Asbestos Cleanup Cost
Date: Thursday, January 24, 2019 11:53:33 AM
Attachments: Invoice #5434 Job #SD18270.odf
Item 2 supporting
documentation
Caution - External Email
Scott,
See attached invoice. I received the breakdown for the work this morning.
Invoice Total: $5,972.00
1) Containment Cost: $2,687.40
2) HEPA Vac: $1,493.00
3) Scrapping: $1,791.60
Ameresco is obligated for
$4,180.40 of these costs
Ameresco is responsible for Items No. 1 & 2. The City will pay for Item No. 3 as that was the
abatement cost, not associated with the disturbed asbestos.
Thanks,
Jose Lopez, PE
Associate Engineer - Civil
City of National City
Engineering & Public Works Department
1243 National City Blvd
National City, CA 91950
Office: (619) 336-4380
Direct: (619) 336-4312
Fax: (619) 339-4397
E-mail: jlopezPnationalcityca.gov
The City of National City is open Monday through Thursday from 7:00 a.m.-6:00 p.m.; Offices are closed on Fridays.
For more information, please visit www.nationalcitvca.gov. For more information regarding Capital Projects, please
visit www.nationalcityprojects.com
-- CALIFORM)Q:...
NATIONAL CITY
tail
2MC416.0N Al KU
From: Wentworth, Scott [mailto:swentworth@ameresco.com]
Sent: Wednesday, January 23, 2019 4:49 PM
To: Jose Lopez <jlopez@nationalcityca.gov>
Cc: Caruso, John <jcaruso@ameresco.com>
Subject: Civic Center Asbestos Cleanup Cost
Hi Jose,
Item 2 support continued
Do you have the Civic Center Council Chambers & Large Conference Room asbestos cleanup price
and documentation from December? I'd like to package that into the change order I'm creating in
the next several days.
Thank you,
Scott
Scott Wentworth
Sr. Project Manager
Ameresco
510.684.7684 cell
AMERESCO
Green • Ctear.. .,i;tainaale
***NOTE: This e-mail may contain PRIVILEGED and CONFIDENTIAL information and is
intended only for the use of the specific individual(s) to which it is addressed. If you are not an
intended recipient of this e-mail, you are hereby notified that any unauthorized use,
dissemination or copying of this e-mail or the information contained in it or attached to it is
strictly prohibited. If you have received this e-mail in error, please delete it and immediately
notify the person named above by reply e-mail. Thank you.***
*** AMERESCO NOTICE *** Please send all suspicious email including spam, phishing or
anything you are unsure of to suspicious@ameresco.com
Item 2 support continued
CENTRAL VALLEY
ENVIRONMENTAL
135 Utility Court, Suite A Rohnert Park, (':% 94928
Tax LD.# 45-4398710
Bill To
Rely Environmental
Attn: Accounting
3276 Rosecrans Street #201
San Diego CA 92110
PO # CVE Job #
Description
SD 18270
Claim #
Date
Invoice
Invoice #
1/9/2019
5434
Terms
Rep
JWB
Due Date
Net 30
2/8/2019
Curr %
Prior %
Amount
Job Site: National City: City Hall Conference Room
Asbestos Decontamination & Cleanup
Plea, r la p men t : Corporate
Central Valley Environmental 4 N eiie d Avg
Phone # Fax #
E-ma
100.00%
5,972.00
Total
Payments/Credits
559-222-1122
559-222-1174
tiffanyf@cvecorp.com
$5,972.00
$0.00
Balance Due $5,972.00
Now accepting the following credit cards as an alternative payment method:
Visa, Master Card, American Express, Discover, JCB and Diners Club International
All payments made by credit card will receive a 3% convenience fee of the entire amount of the invoice.
Item 3 supporting documentation
west coast Air
Conditioning Co., Inc.
CHANGE ORDER REQUEST #01 5
DATE: January 11, 2019
PROJECT: National City HVAC Upgrade Project
Various Locations
BELOW IS A SUMMARY OF THE ATTACHED ITEMS REQUESTED FOR A FORMAL CHANGE ORDER
Additional services and material to relocate the sewer vent at the Civic
Center, see attached for breakdown.
WCA: n-t_
Colin M. Fisher, CEO
Ameresco, Inc.:
Scott Wentworth
3,153.59
COR Total 3,153.59
O&P 15% 473.04
Sub Total
Bond 1%
Grand Total
3,626.63
36.27
3,662.89
WEST COAST AIR CONDITIONING CO., INC. 1155 PIONEER WAY, SUITE 101 EL CAJON, CA 92020 PH.619-561-8000
Item 3 support continued
7360 Carroll Rd
Suite #100
San Diego, Ca 92121
(858) 578-3270, (858) 578-3273 fax
Bill To
West Coast Air
1155 Pioneer Way, Suite 101
El Cajon, CA 92020
Ulf"
E N G 1 N E E R S
P.O. No.
Invoice #
10? J 4003
17290
Date
Terms
12/18/2018
Net 30
Project
5240 - National City Civic Center
Description
Contract
Prior %
Current %
Total %
Amount
Civic Center
45,000.00
100.00%
0.00%
100.00%
0.00
Police Building
11,700.00
100.00%
0.00%
100.00%
0.00
MLK Community Center
11,700.00
100.00%
0.00%
100.00%
0.00
Arts Center
7,200.00
100.00%
0.00%
100.00%
0.00
Casa de Salud
7,200.00
100.00%
0.00%
100.00%
0.00
Public Works
7,200.00
100.00%
0.00%
100.00%
0.00
Additional Services for Electrical Services
3,250.00
100.00%
0.00%
100.00%
0.00
Additional Services for Design of New Roof Enclosures
5,500.00
100.00%
0.00%
100.00%
0.00
Additional Services for Sewer Vent Relocation
750.00
100.00%
100.00%
750.00 ,.
DEC Engineers, Inc. - "Thank You for your Business"
7360 Carroll Road Ste 100
P 858-578-3270, F 858-578-3273
Total $750.00
Item 3 support continued
0 FERGUSON°
WOLSELEY
3280 MARKET STREE
SAN DIEGO, CA 92102
DEC 18 2018
Please contact with Questions: 909 -613-1740
2543 1 AB 0.408 E0082X 10140 04330263184 S2 P5975548 0001:0001
IIIIIIIIiIIIiIIiiiuiuiIIIIuIIIIiIIiIIIIIIiiIIIiiI'IIIIIIuiI111II1
WEST COAST AIR COND CO INC
1155 PIONEER WAY STE 101
EL CAJON CA 92020-1964
INVOKE NUMBER
TOTAL DUE
CUSTOMER
PAGE
6916456
$754.48
1001078
1 of 1
PLEASE REFER TO INVOICE NUMBER WHEN
MAKING PAYMENT AND REMIT TO:
FERGUSON ENTERPRISES INC #1350
PO BOX 740827
LOS ANGELES, CA 90074-0827
SHIP TO:
COUNTER PICK UP
3280 MARKET STREET
SAN DIEGO, CA 92102
SHIP
WHSE.
667
SELL
WHSE.
667
TAX CODE
CA37
CUSTOMER ORDER NUMBER
,A0102
SALESMAN
SLT
JOB NAME
A0102
INVOICE DATE
12/11/18
BATCH
10
439548
ORDERED
SHIPPED
ITEM NUMBER
DESCRIPTION
UNIT PRICE
UM
AMOUNT
3
2
20
2
ITEM CODE
CDWV4M
CDWV9M
...3,
• 2.
20.
2:
-CUW V444..
CQVI/V9111 .
-•GI]WVTM20
ENIACda 6Y03,12
DESCRIPTION
3 DWV WROT CXC 45
3 DWV WROT CXC 90
3 ()WY. WROT GXC 45 ELL
3 DWV WROT CXC "90 EEL
' 3 X 20 FT DWV COP TUBE
2,118 QD PLTD CUSH TUBE STRUT CLMP
INVOICE SUB -TOTAL
TAX
NOTICE
ELL <I> WARNING: Cancer and
www.P65wamings.ca.gov
ELL <I> WARNING: Cancer and
www.P65wamings.ca.gov
22.540•
33.200.....EA
O�5,240Q
10.488
San Diego
Reproductive Harm
Reproductive Harm
.EA
C..•.
EA-
-.�iy
-
-, 62162*
r 6640
t83iO4.
2E1.3.8.4
700.20
54.28
J7"i
TAK 0/64 57
FNW7816Y03'
2
3-1/8 OD PLTD CUSH TUBE
STRUT CLMP <I> WARNING: Cancer and
www.P65Warnings.ca.gov
Reproductive Harm
–
Tow�'l
�' ��" i.!'
LEAD LAW WARNING:
US FEDERAL OR
PRODUCTS WTH'NP
NON -POTABLE
IT IS ILLEGAL
OTHER APPLICABLE
IN THE DESCRIPTION
APPLICATIONS.
TO INSTALL PRODLCTS
LAW IN POTABLE
ARE NOT LEAD
BUYER IS SOLELY RESFONSIBLE
THAT ARE NOT "LEAD FREE" IN ACCORDANCE WITH
WATER SYSTEMS ANTICIPATED FOR HUMAN CONSUMPTION.
FREE AND CAN ONLY BE INSTALLED IN
FOR PRODUCT SELECTION.
cyM
tm
} ;
fir:
ff i'"
N /y
gory �r
Y 'r �.v
+I 201
WATER FLOW
NOT ALLOWED
RATE NOTICE: LAVATORY
FOR 'PUBLIC USE'
FAUCETS WITH
IN CALIFORNIA.
FLOW RATES OVER 0.5 GPM ARE
VENDOR# ()
ft
/ .7'':
PO#
. -
JOB# / • — :
COST CODE 63
CT ACCT#
APPROVED BY: pi ----
Thank
your ou for
businessYits4.1
I I
r
TERMS: NET 10TH PROX ORIGINAL INVOICE
TOTAL DUE
All past due amounts are subject to a service charge of 1.5% per month, or the maximum allowed by law, if lower. If Buyer fails to
pay within terms, then in addition to other remedies, Buyer agrees to pay Seller all costs of collection, including reasonable
attorney fees. Complete terms and conditions are available upon request or at http://wolseleyna.com/terms_conditionsSale.html
and are incorporated by reference. Seller may convert checks to ACH.
nnm •nnni
CITY OF NATIONAL CITY
Office of the City Clerk
1243 National City Blvd., National City, California 91950-4397
619-336-4228
Michael R. Dalla, CMC - City Clerk
AMERESCO, INC.
Energy Services Agreement, CIP No. 17-03
Change Order #6
Judith Hernandez (Engineering/Public Works) forwarded a copy of the Change Order to
Ameresco, Inc.