CHANGE ORDER NO. 6
August 2, 2019
Reason/Purpose for this Change Order:
The city has directed the contractor to install one additional pedestrian barricade and modify the mounts for
two pedestrian barricades.
The City of National City and Contractor agree to the following change to the original Contract:
The contractor was directed to install one additional pedestrian barricade at the southeast corner of 2nd and
Harbison. The contractor was also directed to modify the two pedestrian mounts originally called out on the
plans on the west side or Harbison and 2nd All barricades shall be installed per Caltrans Std. ES-7Q Type I
Detail C modified. All work was performed for the total lump sum price listed below.
Original Contract Amount
Net change by previously authorized Change Orders
Subtotal
Amount of this change order
New contract amount
Wor ng days added: a 0 Wor in
days subtracted: 0
$ 290,575.00
51,218.82
341,793.82
2,310.00
$ 344,103.82
Percent change in Contract to date 18.42%
Sub i ed by.:
Proj ct Mana
r
5
5 - /
Date
3-1
City Project Manager
Date
roved by:
City gineer
Date
City Manager, required for Change Orders>$24,999
Date
By signing this Change Order the Contractor confirms that he/she is completely familiar with its terms and conditions and has fairly
negotiated its price, terms and conditions. If this Change Order is approved, Contractor will provide all of the equipment, materials and
labor necessary to provide a complete work as described above at that the price stated herein. Additionally, Contractor confirms that the
price is fair and complete and represents all costs associated with the work, including but not limited to all equipment, materials, labor,
supervision, overhead, fees, bonds, insurance, profit, etc. and that there will be no further compensation. All of the terms and conditions
of the original contract documents are incorporated herein. (2 originals: 1 for City Clerk, 1 for Contractor)
Accepted and agreed to by Portillo Concrete, Inc.
Name:
rh 16
O',2-1cp
Date
Note to Contractor: If you do not agree with this Change Order you may be directed to proceed with this work under the terms of the
contract and you may proceed under protest. You must comply with the contract requirements of submitting a written protest to protect
your claim.
Originals: City Clerk, Contractor
cc: Engineering project file, Project Manager
1243 National City Boulevard, National City, CA 91950
Telephone (619) 336-4380
P11
PORTILLO
CONCRETE INC
3527 CITRUS ST, LEMON GROVE, CA. 91945
OFFICE: (619) 466-4639 FAX: (619) 466-4685
PROJECT: National City Harbison Ave Road Diet
Request for Change Order
Date:
Subcontractor:
Description / Reason for Change:
7/30/19
Statewide
Due to the installation of a one directional ramp on the SE corner of 2 nd street we need to dircet
pedetrain traffic to continue North and South only. This also means we need to block pedestrains
from trying to walk from East and West at such location.
Description
T&M #
Price
Change 2 signs to - ES-7Q Barricades
-
1 - Add ES-7Q with signage
$2,200.00
PCI Mark Up
Change Order Total
5% $110.00
Origional Contract Amount
Previous Change Order Amount
Subtotal
$ 290,575.00
$ 51,218.82
$ 341,793.82
Statewide Stripes, Inc.
P.O. Box 600710
San Diego, CA 92160-0710
858.560.6887
858.560.0158 fax
Tax ID #33-0915254
Class: C32 SLBE# 10SS0008
MB/SB# 40421 DBE# 32232
PW Contractors Reg# 1000001334
Customer Info
ESTIMATING DEPARTMENT
CA Lie. #788286
Since 1990
Signatory Local 1184
PROJECT
REP
TERMS
ES-7Q Barricades Added
AJO
30 Days Net
ESTIMATE
DATE
7/26/2019
NO.
18268
QTY
DESCRIPTION
2
1
Change Two Signs to ES-7Q Barricades
Add ES-7Q with signage on East Corner of Harbinson and E 2nd street
Includes: Items listed, Prevailing wages, Coring
Excludes:
TOTAL
$2, 200.00
EXCLUDE: Adjust Cancellation Clause @ $250.00 ea Cert., Additional Insured Endorsements on Auto Liability @ $75.00 ea., bonds, notary services, night work,
prevailing wages (unless included above), flashing beacon assemblies, mast arm signs. Not responsible for A.D.A. Compliance. Items not specifically included are
excluded and require an Additional Bid.
Acceptance of Estimate and Agreement.
The undersigned hereby contracts for the services noted above and agrees to pay for the services upon completion and receipt of an invoice. The undersigned agrees to
pay reasonable attorney's fees and costs if incurred in the enforcement of this contract.
STATEWIDE STRIPES, INC. REQUIRES TWO WEEKS ADVANCE WRITTEN NOTICE PRIOR TO SCHEDULING.
STATEWIDE STRIPES WILL NOT BE RESPONSIBLE FOR LIQUIDATED DAMAGES UNLESS MUTUALLY AGREED TO IN WRITING
Co. Name:
By:
(Print Name and Title)
Date:
Signature:
CITY OF NATIONAL CITY
Office of the City Clerk
1243 National City Blvd., National City, California 91950-4397
619-336-4228
Michael R. Dalla, CMC - City Clerk
PORTILLO CONCRETE, INC.
Harbison Road Diet, CIP No. 18-17
Change Order #6
Judith Hernandez (Engineering/Public Works) forwarded a copy of the Change Order to
Portillo Concrete, Inc.