Euclid Bicycle and Pedestrian Enhancements
CIP No: 18-10
Contractor: Portillo Concrete, Inc.
CHANGE ORDER NO. 1
August 26, 2019
Reason/Purpose for this Change Order:
The city has directed the contractor to construct an additional three each bus pads.
The City of National City and Contractor agree to the following change to the original Contract:
The contractor was directed to construct an additional three each bus pads not originally called out on the bid
plans at the following locations: NB Euclid just south of 20th, SB Euclid just north of 20th, and SB Euclid just
south of 16th. Each bus pad will be performed at the alternate bid price of $15,000 each including all work
stipulated in the project specifications for the lump sum price listed below.
Original Contract Amount
Net change by previously authorized Change Orders
Subtotal
Amount of this change order
New contract amount
Working days added: 10 Workidays subtracted: 0
$ 4,060,691.00
Percent change in Contract to date 1.11 %
4,060,691.00
45,000.00
4,105,691.00
S • edby:
f
&roved by:
..
C. Engineer
• -
eni..?
Date
Change Orders424,999
1 I Sel e 1
Dat
City Man
By signing this Change Order the Contractor confirms that he/she is completely f iliar with it r s and conditions and has fairly
negotiated its price, terms and conditions. If this Change Order is approved, Con ractor will provide all of the equipment, materials and
labor necessary to provide a complete work as described above at that the price stated herein. Additionally, Contractor confirms that the
price is fair and complete and represents all costs associated with the work, including but not limited to all equipment, materials, labor,
supervision, overhead, fees, bonds, insurance, profit, etc. and that there will be no further compensation. All of the terms and conditions
of the original contract documents are incorporated herein. (2 originals: 1 for City Clerk, 1 for Contractor)
Accepted and agreed to by Portillo Concrete, Inc.
Date
Note to Contractor: If you do not agree with this Change Order you may be directed to proceed with this work under the terms of the
contract and you may proceed under protest. You must comply with the contract requirements of submitting a written protest to protect
your claim.
Originals: City Clerk, Contractor
cc: Engineering project file, Project Manager
1243 National City Boulevard, National City, CA 91950
Telephone (619) 336-4380
Euclid Bicycle and Pedestrian Enhancements
CIP No: 18-10
Contractor: Portillo Concrete, Inc.
CHANGE ORDER NO. 2
August 26, 2019
Reason/Purpose for this Change Order:
The city has directed the contractor to replace existing pull boxes with pre-existing damage as encountered.
The City of National City and Contractor agree to the following change to the original Contract:
The contractor was directed to remove and replace existing pull boxes with pre-existing damage as encounter
during construction of new concrete improvements. The cost for the replaced boxes will be as follows: The
smaller HN1324 Pull Box will be $400 Ea. and the larger HN1730 Box $450 Ea. The unit price includes
removal and disposal of the existing pull box and replacement. All pull box lids will received the same labeling
as the existing. A total of two HN1324 and two HN1730's were replaced to date. This work includes all
necessary materials and labor per the lump sum listed below.
Original Contract Amount $ 4,060,691.00
Net change by previously authorized Change Orders
Subtotal
Amount of this change order
New contract amount
Working days added: 0 kjgi
Wor g days subtracted: 0
45,000.00
5,691.00
1,700.00 icibsisq
$ 4,107,391.00
Percent change in Contract to date 1.15%
4,10
Subit
by: /
Prok..
t Man
Date
City Project Manager
Date
proved by:
..
Cit ngineer
p
p/r/i
Date
City Manager, required for Change Orders>$24,999
Date
By signing this Change Order the Contractor confirms that he/she is completely familiar with its terms and conditions and has fairly
negotiated its price, terms and conditions. If this Change Order is approved, Contractor will provide all of the equipment, materials and
labor necessary to provide a complete work as described above at that the price stated herein. Additionally, Contractor confirms that the
price is fair and complete and represents all costs associated with the work, including but not limited to all equipment, materials, labor,
supervision, overhead, fees, bonds, insurance, profit, etc. and that there will be no further compensation. All of the terms and conditions
of the original contract documents are incorporated herein. (2 originals: 1 for City Clerk, 1 for Contractor)
Acce ted and agreed to b Portillo Concrete, Inc.
itfro
Name: pack),
rhf!c
Date
Note to Contractor: If you do not agree with this Change Order you may be directed to proceed with this work under the terms of the
contract and you may proceed under protest. You must comply with the contract requirements of submitting a written protest to protect
your claim.
Originals: City Clerk, Contractor
cc: Engineering project file, Project Manager
1243 National City Boulevard, National City, CA 91950
Telephone (619) 336-4380
CITY OF NATIONAL CITY
Office of the City Clerk
1243 National City Blvd., National City, California 91950-4397
619-336-4228
Michael R. Dalla, CMC - City Clerk
PORTILLO CONCRETE, INC.
Euclid Bicycle and Pedestrian Enhancements, CIP No. 18-10
Change Order #1
Judith Hernandez (Engineering/Public Works) forwarded a copy of the Change Order to
Portillo Concrete, Inc.