Change Order No. 17 provides for:
The application of Hydroseed to approximately 2,000 square feet of existing slope between 22nd street and
Paradise Creek.
Supporting Information:
Change Order #7 approved clearing and grubbing of the existing slope between 22"d Street and Paradise
Creek. To meet all current project erosion control plans, all existing slopes that are disturbed or changed by
construction activities, are to be stabilized to minimize erosion by water and wind. Applying a hydroseed mix
to the existing slope will protect the slope and minimize future City maintenance.
Time Adjustment:
It is recommended that 0 working days be added to the contract time.
Cost Adjustment:
The efforts to stabilize the existing slope are to be captured under an agreed lump sum price of $892.50. The
pay method and amount have been reviewed by the Construction Manager and are considered fair and
reasonable.
0-- CALIFORNIA -�
NATIONAL Cm
13 3
L INCORPORATED
PARADISE CREEK PARK SITE REMEDIATION & IMPROVEMENTS CHANGE ORDER NO. 17
CIP NO. 18-07
Contractor: Whillock Contracting Inc.
PO Box 2322
La Mesa, CA 91943
August 26, 2019
This Change Order modifies Contractor's and the City's obligations and rights under the
abovementioned contract. This change order is not effective until approved by the City.
Time adjustment:
Zero (0) working days are added to contract time for stabilizing existing slope at existing creek headwall
with Hydroseed.
Cost of Change Order:
The City and the Contractor agree that the contractor shall stabilize approximately
2,000 square feet of slope at the existing creek headwall with Coastal Sage Scrub
Hydroseed Mix. The agreed upon price for the stabilization of approximately 2,000
square feet of slope is a total lump sum of $892.50.
$892.50
Total Cost of Change Order
$892.50
Recommended by Project Manager:
ir� /
Date: &/28,/9
By signing this Change Order the Contra Igor confirms that he/she is completely familiar with and has fairly
negotiated its price, terms and conditions. If this Change Order is approved, Contractor will provide all of the
equipment, materials and labor necessary to provide a complete work as described above at that the price
stated herein. Contractor confirms that the price is fair and complete and represents all costs associated with
the work, including but not limited to all equipment, materials, labor, supervision, overhead, fees, bonds,
insurance, profit, etc. and that there will be no further compensation. All of the terms and conditions of the
original contract documents are incorporated herein. The signer for the Contractor confirms that he/she is
authorized to bind the Contractor to this Change Order.
Agreed and Accepted by Contr •7
(Print Name and Title)
Date: // Z / '
/ /p,
Approved by City Engineer
Date: j 128' )1
Approved by City Manage :
(Required for change orders $25,000 and above)
74$�/7
Date:
acific Rim Hydroseedin
]nc
28319 Valley Center Rd.
Valley Center, CA 92082
760-751-7055
760-751-7385 Fax
760-638-6227 Don's Cell / 760-638-6217 Cory's Cell
teresa.pacificrim@yahoo.com
CA Lie. #886257
CA SB Cert #1211120
ARB Certified
D1R Reg #1000006248
Bid Proposal
Date
Proposal #
8/15/2019
4504
Cust. P.O. #
Whillock Contracting Inc.
PO Box 2322
La Mesa, CA 91943-2322
Customer Phone
619-579-0700
Customer Fax
619-579-0955
Description
Qty
Rate
Total
Square Foot Coverage
Paradise Creek
National City, CA
Mulch 1400 Ibs/acre
Grow Power Plus with Mycro and Soil penetrant 400 Ibs/acre
Binder 80 Ibs/acre
Coastal Sage Scrub Mix
Bid considers 1 move -in, additional at $650.00
Bid considers prevailing wages
Bid considers 2.5" water source at site
2,000
0.425
850.00
�t- PrtuIQ�C
Bid includes all equipment, labor & listed materials.
Bid does not include preparation or maintenance.
Bid does not guarantee germination or growth.
Bid considers no retention
Bid considers standard insurance requirements, additional
insurance requirements will result in additional cost.
Waiver of subrogation will result in additional cost.
Agreed to and Accepted in its Entirety by:
Date:
PROJECT PROFESSIO LS CORPORATION
TRANSMITTAL COVER
To: National City Engineering Department
Project Name: Paradise Creek Park Phase III
CIP No.: 18-07
ITEMS DELIVERED:
Change Order #17
Delivered by:
Received by:
Date:
ect Professionals Cor
Vtoks-kry
oration
)12,9, 11
ri
PROJECT PROFESSIO ALS CORPORATION
CHANGE ORDER MEMORANDUM
August 2, 2019
To: Stephen Manganiello
Director of Engineering & Public Works/City Engineer
Engineering and Public Works Department
City of National City
From: Alex Preciado
Project Manager
Project Professionals Corp
Project: Paradise Creek Park Site Remediation & Improvements
CIP No.: 18-07
Subject: Change Order No. 18
Change Order No. 18 provides for:
The grouting of Gabion Wall baskets.
Supporting Information:
The double tier (multi -row) Gabion Wall section has a row of baskets approximately 130 linear feet in length
that rests a foot below the finish surface. The finish surface will be used as a future multi -use access path for
City emergency vehicles, City maintenance trucks and pedestrian traffic. This original detail would not allow
for the subgrade and finish surface to meet compaction requirements which can cause cracking and other
surface failures throughout time. To meet compaction requirements and minimize City maintenance of the
multi -use path, pouring slurry in the Gabion baskets was determined to be a proper solution to support the
base and surface of the access path.
Attachment A — T&M Breakdown
Time Adjustment:
It is recommended that 0 working days be added to the contract time.
Cost Adjustment:
The City and the Contractor agreed that this work shall proceed under Time and Materials. Analysis of this
work by the Construction Manager determined that the cost for this work shall not exceed $2,100. Upon
completion, the Time and Materials total amount associated with this work is $2,055.56. The pay method
and amount have been reviewed by the Construction Manager and are considered fair and reasonable.
Project Manager
Date
CALIFORNIA
NATIONAL C9TI�
1NCORPORAT£D
PARADISE CREEK PARK SITE REMEDIATION & IMPROVEMENTS CHANGE ORDER NO. 18
CIP NO. 18-07
Contractor: Whillock Contracting Inc.
PO Box 2322
La Mesa, CA 91943
August 15, 2019
This Change Order modifies Contractor's and the City's obligations and rights under the
abovementioned contract. This change order is not effective until approved by the City.
Time adjustment:
Zero (0) working days are added to contract time for the grouting of Gabion Baskets.
Cost of Change Order:
The City and the Contractor agree that all work associated with grouting the
Gabion Baskets will be captured under the agreed time and material costs of
$2,055.56.
$2,055.56
Total Cost of Change Order
$2,055.56
Recommended by Project Manager:
ibiv
Date:
g/�
By signing this Change Order the Con actor confirms that he/she is completely familiar with and has fairly
negotiated its price, terms and conditions. If this Change Order is approved, Contractor will provide all of the
equipment, materials and labor necessary to provide a complete work as described above at that the price
stated herein. Contractor confirms that the price is fair and complete and represents all costs associated with
the work, including but not limited to all equipment, materials, labor, supervision, overhead, fees, bonds,
insurance, profit, etc. and that there will be no further compensation. All of the terms and conditions of the
original contract documents are incorporated herein. The signer for the Contractor confirms that he/she is
authorized to bind the Contractor to this Change Order.
Agreed and Accepted by Contractor
(Print Name and Title)
Date:
�/` S/%
Approved by City Engineer: 2
Date:
' fr4 (1
Approved by City Manager:
(Required for change orders $25,000 and above)
?Ad/7
Date:
+ CA F0RN A'
NA'i.'IQNAL, Cflry
V.131
_.• INCORPORATED
PARADISE CREEK PARK SITE REMEDIATION & IMPROVEMENTS CHANGE ORDER NO. 18
CIP NO. 18-07
DATE: August 5, 2019
WORK PERFORMED BY: Whillock Contracting
DESCRIPTION OF WORK: Grout Gabion Baskets
ACCOUNTING FOR TIME, MATERIALS, AND EQUIPMENT
Unit Qty Wage
Total
1) Stewart Grieser
HR 1.00 52.94
52.94
2)
Polo Vasquez
HR 1.00 52.94
52.94
3)
Ricardo Marquez
HR 1.00 52.94
52.94
4)
Nahim Flores
HR 1.00 52.94
52.94
5)
Aaron Ryales
HR 1.00 52.94
52.94
6)
Ryan Mchale
HR 1.00 52.94
52.94
Sub -Total Labor:
Labor Burden (27.02%):
Labor Markup (20%):
TOTAL LABOR:
$ 317.64
$ 85.83
$ 80.69
Unit
Qty
Rate
Total
1)
2 Sack Slurry
YDS
10.00
101.90
1,019.00
1)
SRM Environmental Fee
LS
1.00
40.00
40.00
1)
SRM Public Works Fee
LS
1.00
200.00
200.00
Sub -Total Materials:
Taxes (8.5)
Materials Markup (15%):
TOTAL MATERIALS:
$ 1,259.00
107.43
$ 204.97
EQUIPMENT
Unit
Qty
Rate
Total
Sub -Total Equipment:
Equipment Markup (15%):
TOTAL EQUIPMENT:
$
SUB TOTAL:
1,571.40
$ 2,055.56
SUBCONTRACTOR
Unit
Qty
Rate
Total
Sub -total Subcontractor:
Prime Contractor Markup (5%):
$
TOTAL SUBCONTRACTOR:
$
GRAND TOTAL:
2,055,56
•
914
--INVOICE
iNIPMa
WHILL010 08/05/2019 65653 1
liMag\FML\‘
LI AUG 12 2019 v
SUPERIOR READY MIX
= --CONCRETE,-L.P.
1508 W. MISSION RD.' ESCONDIDO, CA 92029
PHONE (760) 746-0556' FAX: (760) 740-9557
WHILLOCK CONTRACTING INC
P 0 BOX 2322
LA MESA, CA 91943-2322
SWC �$x'i: :Ti4 T'%:`�ewl e ffy+�+1;"f1x"x,A�
TERMS NET 30 DAYS
A FINANCE CHARGE WILL BE IMPOSED ON PAST DUE ACCOUNTS. THE
FINANCE CHAROE IS COMPUTED BY A PERIODIC RATE OF 1 1/2% PER
MONTH. WHICH IS AN ANNUAL PERCENTAGE RATE OF 16%OR A MINIMUM
SERVICE CHARGE OF i6.O0 WHICHEVER IS GREATER.
000190 (1537) PARADISE CREEK PARK
WILSON AVE. & 20TH ST. NATIONAL CITY
t
0
08/05/19 10.00 CY CS-2 101.900 78.97
2 SK SANDSLURRY
1.00 LD EE 40.000 3.10
ENVIRONMENTAL/ENERGY SUR
1.00 LD PWF 200.000 15.50
PUBLIC WORKS FEE
TICKET DATE TOTALS: 1259.00 97.57
JOB TOTALS 1259.00 97.57
TICKETS: 017-49405
1097.97
43.10
215.50
1356.57
1356.57
PROJECT PROFESSI❑ LS CORPORATION
TRANSMITTAL COVER
To: National City Engineering Department
Project Name: Paradise Creek Park Phase III
CIP No.: 18-07
ITEMS DELIVERED:
Change Order #18
Delivered by: Am.._ex2a
roject Professionals Corporation
Received by:
Date:
N.
CITY OF NATIONAL CITY
Office of the City Clerk
1243 National City Blvd., National City, California 91950-4397
619-336-4228
Michael R. Dalla, CMC - City Clerk
WHILLOCK CONTRACTING, INC.
Paradise Creek Park Site Remediation & Improvements, CIP No. 18-07
Change Orders #17 and #18
Judith Hernandez (Engineering/Public Works) forwarded a copy of the Change Orders to
Whillock Contracting, Inc.