HomeMy WebLinkAbout2019 CON Select Electric - Citywide Traffic Signal and ADA Improvements, CIP No. 18-05 - Change Order #2P
c
PROJECT PROFESSIONALS CORPDPATIO'J
CHANGE ORDER MEMORANDUM
July 29, 2019
To: Stephen Manganiello
Director of Engineering & Public Works/City Engineer
Engineering and Public Works Department
City of National City
From: Vinnie Aguelo
Project Manager
Project Professionals Corp
Project: Citywide Signals & ADA Improvements
CIP No.: 18-05
Subject: Change Order No. 2
Change Order No. 2 provides for:
The additional potholing work at National City Blvd and 16th St due to utility conflicts
Supporting Information:
This change order includes the potholing work for a new proposed location for a traffic signal pole at 2nd Ave
and Sweetwater Rd due to utility conflicts. The contractor noted that there is an unforeseen existing
foundation in the original proposed location for the new traffic signal. STC provided new locations and the
contractor required to pothole the assigned locations for viability. All work associated with the additional
potholing were performed through a Time and Material basis. The location was changed twice due to having
conflicts on the location that was provided by the design engineer.
Cost Adjustment:
The total cost for the additional potholing work at 2nd Ave and Sweetwater Rd is $2,937.53.
`T. zq. Zvi q
Proj '9 nager O Date
J
CITYWIDE SIGNALS & ADA IMPROVEMENTS (HSIP) CHANGE ORDER NO. 2
CIP NO. 18-05
Contractor: Select Electric, Inc.
2790 Business Park Drive
Vista, CA 92081
JULY 29, 2019
This Change Order modifies the Contractor's and the City's obligations and rights under the
abovementioned contract. This change order is not effective until approved by the City.
Cost of Change Order:
The City and the Contractor agree that the Contractor proceed with additional
potholing work at 2nd and Sweetwater Rd St due to utility ground conflicts. A
total of two (2) days of potholing were done to relocate original traffic signal pole
location. The agreed upon price for all labor and equipment were measured based
on Time and Material totaling to
T1 $2,937.53
Recommended by Project Manager:
Date: eizti aof
By signing this Change Order the Contractor con i hat he/she is completely familiar with and has fairly
negotiated its price, terms and conditions. If this Change Order is approved, Contractor will provide all of the
equipment, materials and labor necessary to provide a complete work as described above at that the price
stated herein. Contractor confirms that the price is fair and complete and represents all costs associated with
the work, including but not limited to all equipment, materials, labor, supervision, overhead, fees, bonds,
insurance, profit, etc. and that there will be no further com nsation. All of the terms and conditions of the
original contract documents are incorporated herein. Th si*ner for the Contractor confirms that he/she is
authorized to bind the Contractor to this ange rde .
Date:
Z e1
Agreed and Accepted by Contra'. crr:
(Print Name and Title) CpfIAf,E T E5i D E N T
Approved by City Engineer:
Date: ,, s, 7
Approved by City Manager:
(Required for change orders $25,000 and above)
Date:
CALIFORNIA
NATIONAL Cilry
Y, �CORPORATRD
Citywide Traffic Signal and ADA Improvements (HSIP)
CIP NO. 18-05
T&MNO. 4
DATE: April 1, 2019
WORK PERFORMED BY: Select Electric, INC
DESCRIPTION OF WORK: Completed breaking existing unforseen foundation to continue pipe
run and tie into existing pullbox.
ACCOUNTING FOR TIME, MATERIALS, AND EQUIPMENT
LABOR
Unit
Qty
Wage
1)
2)
Miguel Enriquez
Eduardo Ramirez Jr.
HR
HR
8.00
8.00
54.18
55.93
Sub -Total Labor:
Labor Surcharge (10%)
Labor Markup (20%):
Total
433.44
447.44
$ 880.88
$ 88.09
$ 193.79
TOTAL LABOR:
Unit
Qty
Rate
Total
1)
Sub -Total Materials:
Materials Markup (15%):
TOTAL MATERIALS:
EQUIPMENT
Unit
Qty
Rate
Total
1)
TRUCK T&TT
HR
8.00
38.38
307.04
$ 307.04
$ 46.06
SUB TOTAL:
$ 353.10
$ 1,515.86
SUBCONTRACT MARKUP (- - %): $
GRAND TOTAL:
$ 1,515.86
Sub -Total Equipment:
Equipment Markup (15%):
TOTAL EQUIPMENT:
_.__Z ALI ORNIA
NATIONAL. CITY
uectmpoRATrD J
Citywide Traffic Signal and ADA Improvements (HSIP)
CIP NO. 18-05
DATE: April 12, 2019
T&MNO.5
WORK PERFORMED BY: Select Electric, INC
DESCRIPTION OF WORK: Potholed 3rd location for Pole A
ACCOUNTING FOR TIME, MATERIALS, AND EQUIPMENT
Miguel Enriquez
Rob Butts
Unit
HR
HR
Qty
6.00
6.00
Wage
54.08
58.55
Sub -Total Labor:
Labor Surcharge (10%)
Labor Markup (20%):
Unit
Qty
Total
324.48
351.30
$ 675.78
TOTAL LABOR:
Rate
Total
Sub -Total Materials:
Materials Markup (15%):
TOTAL MATERIALS:
EQUIPMENT
Unit
Qty
Rate
Total
1)
TRUCK T&TT 12-20
HR
6.00
38.38
230.28
2)
TRUCK T&TT 12-20
HR
6.00
38.38
230.28
$ 460.56
Sub -Total Equipment:
Equipment Markup (15%):
TOTAL EQUIPMENT:
$ 69.08
SUB TOTAL:
$ 529.64
$ 1,421.67
SUBCONTRACT MARKUP (- - %): $
GRAND TOTAL:
$ 1,421.67
PROJECT PROFESSIONALS CORPORATION
TRANSMITTAL COVER
To: National City Engineering Department
Project Name: Citywide Traffic Signal and ADA Improvements
CIP No. 18-05
ITEMS DELIVERED:
Change Order No. 2
Delivered by: Vinin1(a Project Professionals Corporation
Received by:
Date:
i
4441,iATED D �
CITY OF NATIONAL CITY
Office of the City Clerk
1243 National City Blvd., National City, California 91950-4397
619-336-4228
Michael R. Dalla, CMC - City Clerk
SELECT ELECTRIC, INC.
Citywide Signals & ADA Improvements, CIP No. 18-05
Change Order #2
Judith Hernandez (Engineering/Public Works) forwarded a copy of the Change Order to
Select Electric, Inc.