HomeMy WebLinkAbout2019 CON Preman Roofing - City Hall Roof Replacement, CIP No. 18-08 - Notice of CompletionPLEASE COMPLETE THIS INFORMATION
RECORDING REQUESTED BY:
City Engineer
City of National City
1243 National City Blvd.
National City, CA 91950
AND WHEN RECORDED MAIL TO:
City Engineer
City of National City
1243 National City Blvd.
National City, CA 91950
DOC# 2019-0533395
1111111111111111111111111111111111111110111111111111111
Nov 18, 2019 12:44 PM
OFFICIAL RECORDS
Ernest J. Dronenburg, Jr.,
SAN DIEGO COUNTY RECORDER
FEES: $0.00 (SB2 Atkins: $0 00)
PAGES: 2
THIS SPACE FOR RECORDER'S USE ONLY
(Note: This document is recorded on behalf of the City of National City, a municipal corporation, and is exempt
from Recorder's fees pursuant to Government Code Section 27383)
NOTICE OF COMPLETION
NATIONAL CITY CITY HALL ROOF REPLACEMENT PROJECT
CIP 18-08
THIS PAGE ADDED TO PROVIDE ADEQUATE SPACE FOR RECORDING INFORMATION
(Additional recording fee applies)
RECORDING REQUESTED BY
WHEN RECORDED MAIL TO:
NAME: CITY OF NATIONAL CITY
ADDRESS: 243 NATIONAL CITY BOULEVARD
NATIONAL CITY, CA 91950
NOTICE OF COMPLETION
CALIFORNIA CIVIL CODE SECTION 3093
NOTICE IS HEREBY GIVEN of the completion on January 18, 2019 of the:
National City City Hall Roof Replacement, CIP No. 18-08
Work of improvement or portion of work of improvement under construction or alteration.
1243 National City Blvd National City CA 91950
Street Address City State Zip Code
The undersigned owns the following interest or estate in said property:
Owner in fee
Nature of the interest or estate of owner (mortgagor, lessee, etc.)
Said work of improvement was performed on the property pursuant to a contract with
A Preman Roofing, Inc.
Name of Original Contractor
The following work and material were supplied:
Labor provided: Roofing Laborer. Materials: TPO membrane, insulation board, covered board,
roofing supplies, fall protection control supplies. Equipment: Roofing equipment.
General statement of kind of labor, services, equipment or materials
The names and addresses of co -owners are: N/A
Dated: November 5, 2019;
Joint tenants, tena
Signa ' re
City of National
243 National City Blvd., National City, CA 91950
I, the undersigned, say: I have read the foregoing Notice of Completion and know the contents
thereof; the same is true of my own knowledge. I declare under penalty of perjury that the forgoing
is true and correct.
Executed on November, Tonal City, California.
Signature:
Alejandr' :off:' -'his, MAYOR
No 9.C5
RESOLUTION NO. 2019 — 143
RESOLUTION OF THE CITY COUNCIL OF THE CITY OF NATIONAL CITY: 1)
ACCEPTING THE WORK PERFORMED BY PREMAN ROOFING, INC., FOR THE
CITY HALL ROOF REPLACEMENT PROJECT, CIP NO. 18-08; 2) APPROVING THE
FINAL CONTRACT AMOUNT OF $325,555.00; 3) RATIFYING THE RELEASE OF
RETENTION IN THE AMOUNT OF $16,277.75; AND 4) AUTHORIZING THE MAYOR
TO SIGN THE NOTICE OF COMPLETION FOR THE PROJECT
WHEREAS, it appearing to the satisfaction of the Engineering Department
that all work required to be done by Preman Roofing, Inc., for the total final contract
amount of $325,555.00, for the City Hall Roof Replacement Project, CIP No. 18-08 has
been completed.
NOW, THEREFORE, BE IT RESOLVED by the City Council of the City of
National City as follows:
The City Council of National City hereby accepts said work approving the
final contract amount of $325,555.000, ratifies the release of the retention in the amount
of $16,277.75, authorizes the Mayor on behalf of the City to execute the Notice of
Completion, and orders that payment for said work be made in accordance with said
contract.
PASSED and ADOPTED this 5th day of No
A ejand
ATTEST:
Michael R/Dalla, City Clerk
APPROVED AS TO FORM: ,,:z.._
ngi
ttorney
Jone
:ote.-S:j.
, Mayor
Passed and adopted by the Council of the City of National City, California, on
November 5, 2019 by the following vote, to -wit:
Ayes: Councilmembers Morrison, Quintero, Rios, Sotelo-Solis.
Nays: None.
Absent: Cano.
Abstain: None.
AUTHENTICATED BY: ALEJANDRA SOTELO-SOLIS
Mayor of the City of National City, California
MICHAEL R. DALLA
City Clerk of the City of National City, California
By:
Deputy
I HEREBY CERTIFY that the above and foregoing is a full, true and correct copy of
RESOLUTION NO. 2019-143 of the City of National City, California, passed and
adopted by the Council of said City on November 5, 2019.
By:
City Clerk of the City of National City, California
65.e)6e€G
eputy
CITY OF NATIONAL CITY, CALIFORNIA
COUNCIL AGENDA STATEMENT
MEETING DATE: November 5, 2019
AGENDA ITEM NO. 10
EM TITLE:
Resolution of the City Council of the City of National City: 1) accepting the work performed by Preman
Roofing, Inc., for the City Hall Roof Replacement Project, CIP No. 18-08; 2) approving the final
contract amount of $325,555.00; 3) ratifying the release of retention in the amount of $16,277.75; and
4) authorizing the Mayor to sign the Notice of Completion for the project.
PREPARED BY: Luca Zappiello, Assistant Civil Engineer
PHONE: 619-336-4360
EXPLANATION:
See attached.
DEPARTMENT: Engineering/Public Works
APPROVED BY: /7
4
JANCIAL STATEMENT:
ACCOUNT NO.
N/A
ENVIRONMENTAL REVIEW:
N/A
ORDINANCE: INTRODUCTION:
FINAL ADOPTION:
APPROVED:
APPROVED:
Finance
MIS
STAFF RECOMMENDATION:
Adopt Resolution accepting the work performed by Preman Roofing, Inc., for the City Hall Roof Replacement Project,
CIP No. 18-08 and approving the final contract amount of $325,555.00.
BOARD / COMMISSION RECOMMENDATION:
N/A
ATTACHMENTS:
1. Explanation
2. Notice of Completion
3. Final Contract Balance Report
4. Resolution
fa/wf';n 5tv. Pof9 - /93
EXPLANATION
The project consisted on the removal and disposal of existing roofing system and install new
thermoplastic polyolefin (TPO) membrane roofing system on the building located at 1243
National City Blvd, National City, CA 91950.
On May 17, 2018, the bid solicitation was posted on PlanetBids, a free public electronic
bidding system for contractors. On May 18, 2018 and May 22, 2018, the bid solicitation was
advertised in local newspapers.
On May 31, 2018, six (6) bids were received electronically on PlanetBids by the 1:00 p.m.
deadline. Bid results were available immediately after the 1:00 p.m. deadline. Preman
Roofing, Inc., was the apparent lowest bidder with a total bid amount of $304,410.00 as the
basis of award.
On June 19, 2018, the City Council adopted Resolution No. 2018-98 awarding the contract
to Preman Roofing, Inc., in the not -to -exceed amount of $304,410.00.
The Notice to Proceed with construction was issued on July 10, 2018. Construction started
on July 26, 2018 and was completed on January 18, 2019. However, after the completion of
the construction, the project was unable to be closed out since Preman Roofing, Inc. took
several months to complete the administrative paperwork.
The change orders issued for this project are detailed in the Final Contract Balance Report
(see attached). The change orders increased the contract by $21,145.00. This results in a
7% contract increase for a final contract balance of $325,555.00.
As a result of satisfactory completion of the project, staff recommends that City Council, 1)
accept the work of Preman Roofing, Inc., for the City Hall Roof Replacement Project, CIP No.
18-08; 2) approving the final contract amount of $325,555.00; 3) ratifying the release of
retention in the amount of $16,277.75; and 4) authorizing the Mayor to sign the Notice of
Completion for the project.
The Notice of Completion will be filed with the San Diego County Recorder's Office.
-1-
RECORDING REQUESTED BY
WHEN RECORDED MAIL TO:
NAME: CITY OF NATIONAL CITY
ADDRESS: 243 NATIONAL CITY BOULEVARD
NATIONAL CITY, CA 91950
NOTICE OF COMPLETION
CALIFORNIA CIVIL CODE SECTION 3093
NOTICE IS HEREBY GIVEN of the completion on January 18, 2019 of the:
National City City Hall Roof Replacement, CIP No. 18-08
Work of improvement or portion of work of improvement under construction or alteration.
1243 National City Blvd National City CA 91950
Street Address City State Zip Code
The undersigned owns the following interest or estate in said property:
Owner in fee
Nature of the interest or estate of owner (mortgagor, lessee, etc.)
Said work of improvement was performed on the property pursuant to a contract with
A Preman Roofing, Inc.
Name of Original Contractor
The following work and material were supplied:
Labor provided: Roofing Laborer. Materials: TPO membrane, insulation board, covered board,
roofing supplies, fall protection control supplies. Equipment: Roofing equipment.
General statement of kind of labor, services, equipment or materials
The names and addresses of co -owners are: N/A
Dated: November 5, 2019;
Joint tenants, tenants in common, or other owners
Signature of Owner
City of National City, 1243 National City Blvd., National City, CA 91950
I, the undersigned, say: I have read the foregoing Notice of Completion and know the contents
thereof; the same is true of my own knowledge. I declare under penalty of perjury that the forgoing
is true and correct.
Executed on November 5, 2019 at, National City, California.
Signature:
Alejandra Sotelo-Solis, MAYOR
Noc09-05
-2-
\
4)- CALIPORK
NkU0! AL mirir
anv
+NCORpOAA,
FINAL CONTRACT BALANCE
DATE: 11/05/2019
PROJECT: National City City Hall Roof Replacement
FY 18-19
CIP No. 18-08
TO:
Preman Roofing
875 34th Street
San Diego, CA, 92102
ORIGINAL CONTRACT AMOUNT:
START DATE:
COMPLETION DATE:
ORIGINAL CONTRACT LENGTH:
EXTENTION OF WORK DAYS:
TOTAL CONTRACT TIME:
FINAL CONTRACT AMOUNT:
DESCRIPTION:
$ 304,410.00
July, 26, 2018
January 18, 2019
40 Working Days
80 Working Days
120 Working Days
$325,555.00
The Final Contract Balance reports final line item amounts and summarizes all change orders to produce
a final contract amount.
CHANGE ORDERS AND LINE ITEM ADJUSTMENTS:
Change Order #1 removed and replaced the 4 existing lower roof drains of The City Hall Building with 4
new TPO roof drains that connect to the existing piping for proper drainage. This Change Order total
amount is $4,800.00.
Change Order #2 directed the contractor to repair the existing defective roof drain at City Library and
install twenty (20) one way TPO vents to mitigate future moisture under the TPO membrane. This
Change Order total amount was $7,262.00.
Change Order #3 directed the contractor to remove and replace the corroded existing cap that houses
the 4 existing weather heads with a new 24-gauge galvanized cap. This Change Order total amount was
$300.00.
Change Order #4 directed the contractor to provide 320 2'x3' TPO slip sheets to The City to furnish to
Ameresco. The purpose of the slip sheets is to preserve the warranty of the new TPO roof system from
any damage from the solar equipment. This Change Order total amount was $3,380.00.
-3-
FINAL CONTRACT BALANCE
NATIONAL CITY CITY HALL ROOF REPLACEMENT
CIP No. 18-08
Changer Order #5 directed the contractor to procure and install approximately 100 rubber conduit
support blocks. Due to a separate contract with Ameresco and a change order that covered this scope of
work, Change Order #5 was cancelled. This Change Order total amount was $00.00.
Changer Order #6 directed the contractor to remove Change Order #3 work and extend the conduits
above curb and install TPO boots with proper TPO flashing. The need for extending the conduits above
curb is to allow access to the existing spare conduits for potential future use. This Change Order total
amount was $740.00.
Changer Order #7 directed the contractor to provide proper waterproofing and roofing membrane
termination along the perimeter of both new mechanical penthouses installed by AMERESCO. This
Change Order total amount was $2,388.00.
Changer Order #8 directed the contractor to perform additional repairs to the library upper roof drains.
This repair consisted of removal and replacement of 80 square feet of TPO roofing membrane. This
Change Order total amount was $2,275.00.
All Change Orders listed above increased the total contract amount $21,145.00.
CONTRACT ADJUSTMENT:
As a result of the above change orders and line item adjustments, the contract price is adjusted as
follows:
1. The final contract price is adjusted to $325,555.00.
2. As a result of the satisfactory completion of said project, a retention amount of $16,277.75 is set
for invoice processing and payment upon the receipt of signatures and City Council's ratification
of this agreement and the Notice of Completion.
This document and its purpose to balance payment shall be considered full compensation for furnishing
and installing the materials, labor, tools and equipment, profit, overhead, and all incidentals for
performing the work described above. Preman Roofing will not be entitled to damages or additional
payment for delays as described in the 2012 edition of the Standard Specifications for Public Works
Construction, Section 6-6.3, for performing the work as described above.
-4-
CITY OF NATIONAL CITY
City Hall Roof Replacement
CIP 18-08
FINAL BILLING STATEMENT
Original Contract
lo Date
No.
Item
Unit
Quantity
Unit Price
Amount
Quantity
Amount
1
Mobilization
LS
1
54,500.00
4,500.00
1
4,500.00
2
Remove and Replacement of Entire Roofing System
LS
1
$299,910.00
299,910.00
1
299,910.00
BASE BID TOTALS:
304,410.00
-
304,410.00
Change Orders:
1
Removal and Installation of Roof Drains
LS
1
$4,800.00
4,800.00
1
4,800.00
2
Installation of 20 One Way Vents
LS
1
$7,262.00
7,262.00
1
7,262.00
3
24 Gauge Cap
LS
1
$300.00
300
1
300
4
TPO Slip Sheets for The City to Provide Ameresco
LS
1
$3,380.00
3,380.00
1
3,380.00
5
Rubber Conduit Support Blocks - CANCELLED
LS
-
$0.00
-
6
Extend Spare Conduits Above Curb
LS
1
$740.00
740
1
740
7
24 Gauge Counterflashing Around 2 Mechanical Penthouses
LS
1
$2,388.00
2,388.00
1
2,388.00
8
Library Roof Drain Additional Repairs
LS
1
$2,275.00
2,275.00
1
2,275.00
CHANGE ORDER TOTALS:
21,145.00
-
21,145.00
GRAND TOTAL BID (BASE BID+ALTERNATE BID+CHANGE ORDERS):
-5-
RESOLUTION NO. 2019 —
RESOLUTION OF THE CITY COUNCIL OF THE CITY OF NATIONAL CITY: 1)
ACCEPTING THE WORK PERFORMED BY PREMAN ROOFING, INC., FOR THE
CITY HALL ROOF REPLACEMENT PROJECT, CIP NO. 18-08; 2) APPROVING THE
FINAL CONTRACT AMOUNT OF $325,555.00; 3) RATIFYING THE RELEASE OF
RETENTION IN THE AMOUNT OF $16,277.75; AND 4) AUTHORIZING THE MAYOR
TO SIGN THE NOTICE OF COMPLETION FOR THE PROJECT
WHEREAS, it appearing to the satisfaction of the Engineering Department
that all work required to be done by Preman Roofing, Inc., for the total final contract
amount of $325,555.00, for the City Hall Roof Replacement Project, CIP No. 18-08 has
been completed.
NOW, THEREFORE, BE IT RESOLVED by the City Council of the City of
National City as follows:
The City Council of National City hereby accepts said work approving the
final contract amount of $325,555.000, ratifies the release of the retention in the amount
of $16,277.75, authorizes the Mayor on behalf of the City to execute the Notice of
Completion, and orders that payment for said work be made in accordance with said
contract.
PASSED and ADOPTED this 5th day of November, 2019.
Alejandra Sotelo-Solis, Mayor
ATTEST:
Michael R. Dalla, City Clerk
APPROVED AS TO FORM:
Angil P. Morris -Jones
City Attorney
CITY OF NATIONAL CITY
Office of the City Clerk
1243 National City Blvd., National City, California 91950-4397
619-336-4228
Michael R. Dalla, CMC - City Clerk
PREMAN ROOFING
CITY HALL ROOF REPLACEMENT, CIP NO. 18-08
Notice of Completion
A Preman Roofing kept a copy of the recorded Notice of Completion.