HomeMy WebLinkAbout2019 CON San Diego Mechanical and Energy - Public Library Chiller Replacement, CIP No. 19-26 - Change Order #2CALIFORNIA --� NATIONAL.cnnr INCORPORATED National City Chiller Replacement CHANGE ORDER NO. 002 CIP NO. 19-26 September 13, 2019 Contractor: San Diego Mechanical Energy 7568 Trade St. San Diego, CA 92121 This Change Order modifies Contractor's and the City's obligations and rights under the abovementioned contract. This change order is not effective until approved by the City. Time adjustment: Time is adjusted with this Change Order with an extension of 50 calendar days beyond the original 120 calendar days for a total of 170 calendar days Cost of Change Order: Prior Change Orders: Up $39,233 Current Change Order: Up $9,216 Original Contract Amount: $318,792 Total Revised Contract Amount: $367,241 Recommended by Construction Manager, NV5: 7— , Date: September 13, 2019 _ By signing this Change Order, the Contractor 'onfirms that e/she is completely familiar with and has fairly negotiated its price, terms and conditions. If this Change Order is approved, Contractor will provide all of the equipment, materials and labor necessary to provide a complete work as described above at that the price stated herein. Contractor confirms that the price is fair and complete and represents all costs associated with the work, including but not limited to all equipment, materials, labor, supervision, overhead, fees, bonds, insurance, profit, etc. and that there will be no further compensation. All of the terms and conditions of the original contract documents are incorporated herein. The signer for the Contractor confirms that he/she is authorized to bind the Contractor to this Change Order. Agreed and Accepted by Contractor: G06'/1 LI ill (Print Name and Title) p V • e /• p \% A `fivl A 'eV Date: CI 1 ((0 1 1 ci Approved by City Engineer:'7 r/ ' Date: ///Z aa Approved by City Manager: (Required for change orders $25,000 and above) Date: N To: Stephen Manganielio Director of Engineering & Public Works/City Engineer Engineering and Public Works Department City of National City 1243 National City Blvd. National City, CA 91950 From: NV5 15092 Avenue of Science Suite 200 San Diego, CA 92128 V 5 CHANGE ORDER MEMORANDUM September 11, 2019 Project: National City Chiller Replacement CIP No.: 19-26 Subject: Change Order No. 002 Change Order No. 002 provides for: A) Add a factory condenser coil coating for an additional $9216.00 per the manufacturer recommendations to provide coatings on chiller's condenser coils within 50 miles of the Ocean. This coating will help prevent the salt air from causing deterioration and will prolong the useful Operational life of the chiller. The project specifications did not require a condenser coil coating. B) Extend the contract duration from the original 120 calendar days by 50 calendar days for a total of 170 calendar days to accommodate the unanticipated length of manufacturing the specified Daikan chiller. Payment for this change order will covered in the Contractor's regular payment applications prorated on a weekly basis for the temporary chiller rental only until work begins on the existing chiller replacement. Supporting Information: ➢ SDME's letter detailing the coil condenser coating costs and reasons ➢ SDME Letter dated 8/13/19 requesting a time extension until 11/13/19. ➢ SDME's project schedule showing a completion date of 11/13/19 Time Adjustment: 50 additional calendar days Cost Adjustment: Prior Change Orders: Up $39,233 Current Change Order: Up $9,216 Original Contract Amount: $318,792 Total Revised Contract Amount: $367,241 The pay method and amount have been reviewed by NV5's Construction Manager, Luanne Bean, PE and is considered fair an. - _ onabl The supporting documentation is on file with the project records. September 13, 2019 Co.: uciion a ager, NV5 Date N v 5 Change Order 2 Item A SAN DIEGO MECHANICAL ENERGY CHANGE ORDER REQUEST FORM Date: 9/12/19 Change Order #: 02 To: City of National City Change Order Amount: $9216.00 Company: C / 0 : Luanne Bean Project Name: National City Chiller Replacement I CIP NO. 19-26 Address: 1243 National City Blvd. SDME Project Number: P-19-41 National City, CA CHANGE ORDER DESCRIPTION: - Manufacturer recommendation is to provide coating on chillers within 50 miles of the Ocean. This coating will help prevent the salt air from causing deterioration and will prolong the useful Operational life of the chiller. Change Order Breakdown: Current Change Order: Previous Change Order Total: Total Change Order Amount to date: Original Contract Amount: Total Revised Contract Amount: $9216.00 $ 39,233.00 $ 48,449.00 $318,792.00 $ 367,241.00 Submitted : Accepted By: Signature Signature C�—\-1 �- i 1YV o\o 9 -1(0 -1 `1 Printed Name Date Printed Name Date DATE: SAN IDIEGO MECHANICAL ENERGY (FIELD CHANGE ORDER FORM 9/12/2019 LOCATION: National City Public Library Chliler Replacement JOB # I P-19-41 Foreman / Technician YES NO Time Extension: COR# 2 Schedule Impact: X N/A Description of Work: Provide Corrosion Coil Coating on Daikan Chiller -- manufacturer recommended at locations 50 miles or less from Coast Trade Job # Hours Rate Labor Extension $0.00 $0.00 $0.00 $0.00 $0.00 Total Labor $0.00 Description Unit QTY Cost Material Extension Daikan Luvata Corrosion Coating EACH 1 $7,437.50 $7,437.50 Total Material $7,437.50 Total Labor $0.00 Total Material $7,437.50 Sales Tax 7.75% $576.41 Prime (Equipment) 58,013.91 Overhead 10% 5801.39 Profit 5 % $400.70 Total Price: $9,216 NORMAN S. WRIGHT CLI MATEC MECHANICAL EQUIPMENT TO: Cathy Filmore COMPANY: San Diego Mechanical Energy FROM: Dennis Christie RE: 19-1083 - National City Public Library Chiller Replacement Addenda: 0 Plan Date: Specifications: Proposal Date: 5/20/2019 PROPOSAL 4/16/2019 (1) Daikin Applied Model AGZ Air Cooled Scroll Chiller Tag: CH-1 Product Data: 208/60/3 power R-410a refrigerant Painted, galvanized steel cabinet 0.75" insulation on evaporator and cold surfaces MicroTech III unit controller with BACnet, Lon or ModBus interface Single point disconnect with circuit protection Across the line starter Dual refrigerant circuits Aluminum microchannel condenser coils Epoxy coating TEFC condenser fan motors Evaporator strainer FOB Factory... $7437.50 Thermal dispersion flow switch Compressor sound blankets 1st year, parts -only warranty Start up Not Included: Hot gas bypass, Copper fins, External vibration isolation, Seismic calculations or attachments, Testing, Training, Extended or labor warranties. Factory production lead time is approximately: 12 weeks Due to recent volatility in raw material prices, unless quote is accepted within 30 days and released for shipment in 90 days, prices are subject to change. Freight is included. Pricing is based off of single release. Sales taxes are not included. 9885 Carroll Canyon Road, San Diego, CA 92131 Phone: 858-368-3800 N v 5 Change Order 2 Item B San Diego Mechanical Energy 7568 Trade Street I San Diego, CA 92121 (858) 566-8200 Office I (858) 566-8203 Fax License # 997083 Attn: Luanne Bean I City of National City CIP No. 19-26 National City Public Library Chiller Replacement Project Schedule Extension Request 8/13/19 To whom it may concern: Please consider this San Diego Mechanical Energy's formal request to extend the substantial completion date for above mentioned project until 11/13/19. The Daikan chiller has an estimated delivery date of 10/22/19 which has caused our schedule to be extended, but not the estimated duration of the work on site. Below is email from vendor : From: Dennis Christie <dchristie@nswcsd.com> Subject: RE: National City Library Chiller Lead Tlme.pdf Scheduled ship date is 10/14/2019. Add 7-10 days for delivery from Virginia. Dennis Christie 1 Sales Engineer NSWC Please feel free to reach out with any questions or concerns. Kind Regards, Cathy Fillmore, Project Manager San Diego Mechanical Energy cfillmore@sdme-inc.com C: 858.322.1302 1 0: 858.566.8200 11Page Confidential between Customer & San Diego Mechanical Energy ID • Task !Task Name Mode I 1 2 3 0 4 S A 6 r, 7 8 I 9 10 t1 11 �► 12 13 t♦ 14 • 15 16 17 A 18 19 20 r. 21 ._ 22 23 24 • 25 • 26 • 27 • 28 1 29 30 31 32 33 >♦ 35 36 37� II • Notice to Proceed 1♦ Kickoff Meeting Approved chiller submittal - Procure : 12 week lead time Estimated delivery date of new Chiller : October 22nd - TENTATIVE Temporary chiller installed On site meeting to formalize construction timeline :TBD Verify proper lock out tag out of all equipment to be removed Prep existing mechanical equipment & DDC controls for removal Provide all crane services required to remove existing and set new equipment Set new air cooled chiller on existing pad Provide all piping modifications to accommodate new equipment Demo and remove existing pumps Provide insulation on chilled water piping and pumps Heffler Electric : Extend feeds in new junction box to new pumps Splice existing feeder in new underground pull box for chiller Power connections to new chiller control panel Saw cut and patch as required Trench and backfill as required R & R Controls Take system off line and power down existing DDC panel Remove monitoring and control devices for chiller and pumps Remove existing meter transducers and safe off Modbus comm bus Provide DDC controller programs Modify existing graphics to include new chiller and pumps Update existing Honeywell WEBstation with modified DDC programs and graphics Supply and wire 2' bypass valve on chiller bypass piping - install by SDME 1 day DurationiStart ,Finish 1 day Wed 6/12/19 Wed 6/12/19 1 day Tue 6/18/19 Tue 6/18/19 90days Mon 6/24/19 Fri 10/25/19 1 day 1 day 1 day 4 days 1 day 1 day 5 days 1 day 3 days !QUA 2019 Oct Tue 7/30/19 Tue 7/30/19 TBD Mon 10/21/19 Mon 10/21/19 Mon 10/21/19Thu 10/24/19 Mon 10/28/19 Mon 10/28/19 Mon 10/28/19Mon 10/28/19 Mon 10/28/15Fri 11/1/19 Mon 10/28/19Mon 10/28/19 Mon 11/4/19 Wed 11/5/19 12 days Mon 10/21/1c. Tue 11/5/19 5 days 3 days 3 days 2 days 2 days 4 days 4 days 4 days 5 days 1 day 1 day Supply and install 24 VOC power supply to serve new temp transmitters 4 days Furnish CAD drawings to customerof updated system Provide point to point checkout of installed components Task Coordination between trades : SDME - R & R - TAB Provide start up of all new equipment Provide chemical cleaning, flushing and treatment of new system Verify proper operation of all new equipment Perform Testing & Balancing of all new equipment P ovide day of training for customer personnel Provide Close out package 1 day 1 day 5 days? 2 days 1 day 1 day 2 days 1 day 1 day Mon 10/21/19 Fri 10/25/19 Tue 10/22/19 Thu 10/24/19 Mon 10/28/19 Wed 10/30/19 Mon 10/28/19Tue 10/29/19 Mon 10/28/19Tue 10/29/19 Mon 10/21/19Thu 10/24/19 Mon 10/21/19Thu 10/24/19 Mon 10/21/19Thu 10/24/19 Mon 10/21/19 Fri 10/25/19 Mon 10/21/19Mon 10/21/19 Mon Mon 10/28/19 10/28/19 Mon Mon 10/28/19 10/28/19 Mon 11/4/19 Thu 11/7/19 Fri 11/8/19 Fri 11/8/19 Mon 11/11/19Mon 11/11/19 Mon 11/4/19 Fri 11/8/19 Mon 11/4/19 Tue 11/5/19 Tue 11/5/19 Tue 11/5/19 Tue 11/5/19 Tue 11/5/19 Wed 11/6/19 Thu 11/7/19 Wed 11/13/19Wed 11/13/19 Wed 11/13/19 Wed 11/13/19 • • ■ VIM MIN Imo moo f♦ • M ■ Project: V1 National City Public Date. Tue 9/10/19 Task Split Milestone Summary • Project Summary Inactive Task Inactive Milestone tnartrve Summary Manual Task Duration -only Manual Summary Rollup Manual Summary Start -only Finish -only External Tasks External Milestone C Deadline Critical Critical split Progress • Manual Progress Page 1 CITY OF NATIONAL CITY Office of the City Clerk 1243 National City Blvd., National City, California 91950-4397 619-336-4228 Michael R. Dalla, CMC - City Clerk SAN DIEGO MECHANICAL ENERGY National City Chiller Replacement, CIP No. 19-26 Change Order #2 Judith Hernandez (Engineering/Public Works) forwarded a copy of the Change Order to San Diego Mechanical Energy.