HomeMy WebLinkAboutWhillock Contracting Inc. Paradise Creek Park Site Remediation and Improvements, CIP No. 18-07 - Change Order #14 -2019P C PR'OJ[ Cl PROFF ES`: IOtvfLPPCR%.11t1' CHANGE ORDER MEMORANDUM October 10, 2019 To: Stephen Manganiello Director of Engineering & Public Works/City Engineer Engineering and Public Works Department City of National City From: Alex Preciado Project Manager Project Professionals Corp Project: Paradise Creek Park Site Remediation & Improvements CIP No.: 18-07 Subject: Change Order No. 14 RECEIVED ENG & PW DEPT. Z019OCT 23 A 8:45 CITY OF NATIONAL CITY Change Order No. 14 Summary: 1. Bid Line Item #11 — Impacted Soil Handling (Export) is complete. The final quantities provide a credit back to the City. 2. The grading, compaction, export/import of soil, import of class II aggregate base, and all other associated work for preparing subgrade and base for the pervious concrete to be placed throughout the multiuse path. 3. Permanent best management practices are required to be installed within the current CIP No. 18-07 Contract. Throughout the multiuse access path, approximately 13,841 square feet of pervious concrete is to be placed to regulate and control all runoff water throughout the park site. 4. The procurement and installation of approximately 1,200 linear feet of permanent fencing and signage to achieve concurrence with U.S. Fish and Wildlife Service and California Department of Fish and Wildlife requirements. All requirements were listed on the Draft Environmental Impact Report for the Westside Specific Plan. 5. The procurement and installation of two retractable and six fixed bollards. To facilitate the follow-on project and benefit from the mobilized contractor, it was determined to procure and install the bollards with the proper equipment onsite. Supporting Information: Attachment A — Estimated vs Actuals — Bid Line Item #11— Impacted Soil Handling Attachment B — Pervious Concrete Section Breakdown Attachment C — Permanent Fencing Breakdown Attachment D — Retractable & Fixed Bollards Breakdown Attachment E — Pervious Concrete, Bollard, Permanent Fence Exhibit Time Adjustment: It is recommended that 0 working days be added to the contract time. Cost Ad/ustment: The additional cost change for Pervious Concrete Section The additional cost change for Permanent Fencing The additional cost change for Retractable & Fixed Bollards The cost reduction for Bid Line Item #11 — Impacted Soil Handling Total Cost of Change Order IG/LZ/r1 Pro ct Manager Date $202,007.83 98,802.73 10,015.61 (431,490.34) $(120,664.17) NATioN ✓ A7 II 3A565PORATS0 PARADISE CREEK PARK SITE REMEDIATION & IMPROVEMENTS CHANGE ORDER NO. 14 CIP NO. 18-07 October 10, 2019 Contractor: Whillock Contracting Inc. PO Box 2322 La Mesa, CA 91943 This Change Order modifies Contractor's and the City's obligations and rights under the abovementloned contract. This change order is not effective until approved by the City. Time adjustment: Zero (0) working days are added to contract time for the preparation of subgrade and base for pervious concrete, placement of pervious concrete, procurement and install of retractable and fixed bollards, and procurement and install of permanent fencing. Cost of Change Order: The City and the Contractor agree that the contractor shall proceed with grading, compacting, export/import soil, import Class II base, and perform all work associated with preparing subgrade and base for pervious concrete. The City and the Contractor agree that the contractor shall proceed with placing approximately 13,841 square feet of pervious concrete per the attached revised plan sheets, 13, 14, 15. The agreed upon lump sum price for this work is $200,527.95. The City and the Contractor agree that the contractor shall proceed with procuring and installing approximately 1,200 linear feet of permanent fencing per the attached Gabion Wall Railing Exhibit. The agreed upon lump sum price for this work is $98,802.73. The City and the Contractor agree that the contractor shall proceed with procuring and installing two retractable bollards and six fixed bollards with a hot rolled plate welded at the top per the attached Emergency Access Post detail. The agreed upon lump sum price for this work is $10,078.61. The City and the Contractor agree that work for line item #11, Impacted Soil Handling (Export) is complete. The total work completed for line item #11 is 4471.64 tons. The remaining bid line item amount, 5,294.36 tons at $81.50 per ton is deleted from the contract for a total reduction of $431,490.34. $ 202,007.83 98,802.73 10,015.61 (431,490.34) Total Cost of Change Order $(120,664.17) Recommended by Project Manager: Date: 1,d/2 g/i By signing this Change Order the Contra or confirms that he/she is completely familiar with and has fairly negotiated its price, terms and conditions. If this Change Order is approved, Contractor will provide all of the equipment, materials and labor necessary to provide a complete work as described above at that the price stated herein. Contractor confirms that the price is fair and complete and represents all costs associated with the work, Including but not limited to all equipment, materials, labor, supervision, overhead, fees, bonds, insurance, profit, etc. and that there will be no further compensation. All of the terms and conditions of the original contract documents are incorporated herein, The signer for the Contractor conflrms that he/she is authorized to bind the Contractor to this Change Order. Agreed and Accepted by Contractor: Date: J 6 _ 2ir / Gj (Print Name and Title) _ Approved by City Engineer:�� fry Date: // %////7 Approved by City Manager: (Required for change orders $25,000 and above) Date: NO. ITEM PARADISE CREEK PARK SITE REMEDIATION AND IMPROVEMENTS CIP NO 18-07 CALHAZ SUMMARY UNIT QUANTITY UNIT PRICE AMOUNT 11 Impacted Soil Handling (Export) TON 9766 $ 81.50 $ 795,929.00 NO. ITEM UNIT QUANTITY UNIT PRICE AMOUNT 11 Impacted Soil Handling (Export) TON 4471.64 $ 81.50 $ 364,438.66 Original $ 795,929.00 Actual $ 364,438.66 Savings $ (431,490.34) Attachment A - Estimated vs Actuals - Bid Line Item #12 tairION PARADISE CREEK PARK SITE REMEDIATION & IMPROVEMENTS CHANGE ORDER NO. 14 CIP NO. 18-07 DATE: - WORK PERFORMED BY: Whillock Contracting DESCRIPTION OF WORK: Pervious Section Analysis ACCOUNTING FOR TIME, MATERIALS, AND EQUIPMENT Unit Driver - Class 2 Base HR Operator - WA380 HR Operator - CAT246 HR Operator - PC210 HR Labor HR Qty Wage Total 48.00 48.00 40.00 16.00 120.00 35.00 75.12 73.41 75.12 54.18 1,680.00 3,605.76 2,936.40 1,201.92 6,501.60 Sub -Total Labor: Labor Burden (27.02%): Labor Markup (20%): 4 045.76 TOTAL LABOR: $ 15,925.68 $ 4,303.12 Unit Qty Rate Total Class II Base TON 2 Filter Fabric EA 261.00 3.00 10.85 400.00 Sub -Total Materials: Taxes (8.5) - Materials Markup (15%): $ 604.78 TOTAL MATERIALS: 2,831.85 1,200.00 $ 4,031.85 EQUIPMENT Unit Qty Rate Total 1) 2) 3) WA380 CAT246 PC210 HR HR HR 48.00 40.00 16.00 134.24 40.11 98.00 6,443.52 1,604.40 1,568.00 4) Ten Wheeler - Class II Base HR 48.00 71.65 3,439.20 $ 13,055.12 $ 1,958.27 SUB TOTAL: AIRCONTRACTOR Unit Qty Rate Total 1) 2) 3) TB Penick - Pervious Concrete Acculine Survey Incompli (Additional SWPPP) LS LS LS 1.00 1.00 1.00 142, 285.48 4,070.00 4,200.00 Sub -total Subcontractor: Prime Contractor Markup (5%): 142, 285, 48 4,070 00 4,200.00 $ 150,555,48 $ 7,527.77 TOTAL SUBCONTRACTOR: 19/4..25 GRAND TOTAL: Sub -Total Equipment: Equipment Markup (15%): TOTAL EQUIPMENT: $ 15,013.39 Quotation Attn: Chris WHILLOCK CONTRACTING INC. PO BOX 2322 LA MESA, CA 91943-2322 Acct#: 218280 Data: Quote Created: Effective From: Quote Expiration: Price Expiration: Quote Name: Quote #: Monday, June 10, 2019 Sales Rep : Wednesday, September 26, 2018 Thursday, April 18, 2019 Saturday, May 18, 2019 Sunday, June 30, 2019 Vulcan Materials Company and Subsidiaries PARADISE CREEK PARK - NATIONAL CITY 569609 201500580805 21ST ST & HARDING AVE / NA' NATIONAL CITY, CA 91950 Lawson Sanford 7220 Trade Street SAN DIEGO, CA 92121 Phone: 858-530-9459 Fax : Email: sanfordl@vmcmail.com Special Instructions: RIP RAP TRUCKING WILL BE BILLED HOURLY AT $128/HR WITH A 6 HR MINIMUM PER TRUCK. Vulcan has performed analytical testing on Carroll Canyon's aggregates per the guidelines set forth by DTSC's Clean Imported Fill Material advisory, with the exception of CA Title 22 metals, which was performed using EPA Method 200.7. All analyte levels are below the USEPA's Regional Screening Levels (RSL's) for residential soil. The source area sampled consists of undisturbed native materials that have not been subject to impacts from industrial processes or sources. STONE Plant Product Name CHULA VISTA STONE Mel CL 2 BASE! CHULA VISTA STOtilr CHULA VISTA STONE CHULA VISTA STONE CHULA VISTA STONE CHULA VISTA STONE CHULA VISTA STONE CHULA VISTA STONE CHULA VISTA STONE SAND 8. GRAVEL Plant Product Name CARROLL CANYON S&G Import Soil RECYCLED PRODUCTS Plant Product Name 1 121N CR WASHED ASTM #57 3/41N CR UNWASHED SE-30 WASHED CONCRETE SAND CALTRANS BACKING #2 CALTRANS BACKING #1 FOB Haul Product # QtyUlM Plant Rate 16020 250 Tons 810.00 • 6.35 Truck Type STD FRT RATE 16040 250 Tons $18.001r 6.35 Truck Type STD FRT RATE 24010 98 Tons 525.00 6.35 Truck Type STD FRT RATE 25290 255 Tons $20.00 6.35 Truck Type STD FRT RATE 26060 750 Tons $18.00 6.35 Truck Type STD FRT RATE 31450 300 Tons 59.00 6.35 Truck Type STD FRT RATE 31820 35 Tons 525.00 6.35 Truck Type STD FRT RATE 4M160 15 Tons $26.00 0.00 4M170 1,050 Tons $26.00 0.00 Delivered $15.36. 5524.35 $31 35 $26.35 $24.35 $15.35 $31 35 FOB Haul Product# QtyU/M Plant Rate Delivered CARROLL CANYON RECYCLE 3/41N CL 2 RECYCLED BASE CARROLL CANYON RECYCLE 3/41N CL 2 RECYCLED BASE Your iJVuIcunccount Anytime kere vont MyVulcan cam QS1000 40,500 Tons $417 8.63 $12.80 Truck Type STD FRT RATE FOB Haul Product# QtyU/M Plant Rate Delivered 16035 1,500 Tons 56.00 8.63 $14.83 Truck Type STD FRT RATE 16035 1,500 Tons $6 00 7 32 $13.32 Truck Type BOTTOM DUMP Page 1 of 3 f 1r.rrlri.,.rur n: 15435 Innovation Dr.. Ste. 100 San Diego. CA 92128 PHONL 858.558.1800 fax. 858.558.1881 TO: FROM: PROJECT: BID DATE: I a. Vegas OIIlit 5275 S. Arvlile St.. Ste. 300 Las Vegas, NV 89118 mow 800.239.3046 fax. 866.245.3416 <>hk, OlfR( 1790 A. Harmon Ave. Columbus. OH 43223 PIK)Ni 614.801.1844 FAX 614.801.1877 Chris Moore Whillock Contracting Frank Klemaske Executive Vice President Curt Trujillo Estimator Paradise -Creek Park July 2, 2019 I t, „• I www.tbpenlck.com T.B.PfNICK a$ONS.INC. California • Nevada • Ohio New York T.B. Penick & Sons', Inc. site concrete bid proposal includes the following conditions, inclusions and exclusions as referenced on the attached pages. Pervious Concrete Paving: At specified Park path locations, 6" thick over aggregate base (by others) natural color concrete. Approx. 13,841 sf $142,285.48 INNOVATIVE CONCRETE SYSTEMS • LITHOCRETE • STF • BOMANITE • NTMA TERRAZZO • GRASSCRETE AccuLine Survey, Inc. 1919 GRAND AVE, SUITE 1 G. SAN DIEGO, CA 92109 (858) 483-6665 FAX (858) 483-6056 EXTRA WORK ORDER No. AO& Date /l09 Job P/LAUl5E (/?3) To «//�lLLacl� Co,/TG (1537) Address Please furnish all Materials and Labor necessary to complete the following work as noted below and charge to our account: ht,m iz— 5—rriz1/61 $g /ALr4 3 OR.div G of17c-E. cOP b4t4 f' GIGGS 10.0///L_ e' fy/162: 150 -� 51Z & toudicols Pi e#15, 5tEvi=s f p&tio ¢Jd Nt, e /85#4 awe_ 01,LMAS e 2& $71/ 04L' c't65 1 L4 /1"-- TEA-. t$ ¢, 070 The work covered by this order shall be performed under the same Terms and Conditions as that included in the Original Contract. 1. The above work to be paid for at actual cost of Labor and Materials, plus percent ( %). 2. All of the above work to be completed for the sum o Signed Dollars. By TOPS FORM NO. 3460 LITHO 1N U.S.A 7�0 QSP Comprehensive Services Harding Ave & 21st Street IMP and Paradise Park Rough Grading Whillock Contracting, Inc. Incompli DIR # 1000018216 September 19, 2019 • • i n cvm iTM simplifying environmental compliance SCOPE OF WORK The following is the scope of work that Incompli intends to provide the client in order to maintain compliance with the current state construction general permit and Caltrans requirements. QSP/WPCM Services: Incompli will provide the necessary QSP personnel to maintain compliance with the general permit and fulfill all requirements necessary. Inclusions: • Initial training session of onsite staff covering SWPPP requirements, monitoring, and reporting for project. • Daily Weather Forecast monitoring and archiving per the CGP requirements • Will include 1 standard weekly site visit by qualified Incompli personnel • Additional inspections based on weather frequency, including REAPs • Rainfall discharge sampling, analysis and reporting when necessary • Consultation throughout project • All required SMARTS reporting, including Annual Reports and the Notice of Termination The number of visits below are estimated based on a 14 additional weeks. Future weather conditions are unpredictable. Should construction exceed 14 additional weeks or in the event of additional unpredicted rain events a change order may be necessary to continue services. (Hard Count) Weekly BMP Inspections (14) @ $180 $2,520 (Estimated) Weather Visits (Pre, During, Post Storm) Inspections (6) @ $180 $1,080 (Estimated) Rainfall Discharge Sampling, Monitoring & Analysis (2) @ $300 $600 Estimated Contract Value $4,200 Rev Date 7/2013 { QSP Comprehensive Services Harding Ave & 21s` Street Imp/ Paradise Creek Rough Grading Whillock Contracting, Inc. September 11, 2018 • • 1 n c.m simplifying environmental compliance SCOPE OF WORK The following is the scope of work that Incompli intends to provide the client in order to maintain compliance with the current state construction general permit and Caltrans requirements. QSP/WPCM Services: Incompli will provide the necessary QSP personnel to maintain compliance with the general permit and fulfill all requirements necessary. Inclusions: • Initial training session of onsite staff covering SWPPP requirements, monitoring, and reporting for project. • Daily Weather Forecast monitoring and archiving per the CGP requirements • Will include 1 standard weekly site visit by qualified Incompli personnel • Additional inspections based on weather frequency, including REAPS • Stormwater Discharge Sampling, Analysis & Reporting when necessary • Consultation throughout project • All required SMARTS reporting, including Annual Reports and the Notice of Termination The number of visits below are estimated based on a 30 week project. Future weather conditions are unpredictable. Should construction exceed 30 weeks or in the event of additional unpredicted rain events a change order may be necessary to continue services. (Hard Count) Weekly BMP Inspections (30) @ $180 $5,400 (Estimated) Weather Visits (Pre w/ REAP, During, Post Storm) Inspections (27) @ $180 $4,860 (Estimated) Rainfall Discharge Sampling, Analysis & Reporting (9) @ $300 $2,700 Rev Date 7/2013 o- tYc Estimated Contract Value $12,960 5c"(A L N NA ( 1J3'1trycORPORATE �! PARADISE CREEK PARK SITE REMEDIATION & IMPROVEMENTS CHANGE ORDER NO. 14 CIP NO. 18-07 DATE: - WORK PERFORMED BY: Whillock Contracting DESCRIPTION OF WORK: Permanent Fencing Fabrication & Installation Analysis ACCOUNTING FOR TIME, MATERIALS, AND EQUIPMENT Unit Qty Wage Sub -Total Labor: (27.020/0): Labor Markup (200/0): Total TOTAL LABOR: Unit Qty Rate Total Sub -Total Materials: Taxes (8.5) Materials Markup (15%): TOTAL MATERIALS: EQUIPMENT Unit Qty Rate Total Sub -Total Equipment: Equipment Markup (150/0): TOTAL EQUIPMENT: $ SUB TOTAL: SUBCONTRACTOR 1) jInline Fence Unit LS Qty 1.00 Rate 94,097.84 Total 94,097.84 Sub -total Subcontractor: Prime Contractor Markup (5%): $ 94,097.84 $ 4,704.89 TOTAL SUBCONTRACTOR: ♦ 96,0112.73 IN-LIN� TO CONTRACTOR: WHILLOCK CONTRACTING CONTRACT TITLE: PARADISE CREEK PARK EXPANSION CONTRACT NUMBER: CIP #18-07 DESCRIPTION OF WORK: HANDRAIL IN -LINE MASTER BID SHEET REVISED WITH 20D ADDED 8-17-19 CELEBRATING ITEMS OF WORK BREAKDOWN OF DIRECT COST QTY UNIT MATERIALS LABOR EQUIPMENT 1 2 3 4 See Attached Shop Labor See Attached Field Labor See Attached Material See Attached Equipment 5 MEM Direct Materials 6 7 8 9 10 Material O/H Direct Labor Labor O/H Direct Equipment Equip O/H 11 Subtotal (Add Lines 5-10) Direct Materials Labor Rental Equipment Subtotal (Add Lines 12-14) 17 In -Lines Work 18 Subcontractors Work 19 SUBTOTAL (Add Lines 17-18) 20 Overhead on Subcontractor 21 SUBTOTAL (Add Lines 19-20) 22 In -Line Profit (as determined) 23 SUBTOTAL (Add Lines 46-47) 24 In -tines Bond Premium E WORK,. 25 TOTAL C/O COST (Add Lines 23-24) Estimator: 1 T $41,950.94 $0.00 $48,105.35 $0.00 $4,041.55 $0.00 $94,097.84 Unit Cost Total Cost SUBCONTRACTOR'S WORKIMIIMMINP SUMMARY 0� Ortiz $0.00 $0.00 $0.00 $94,097.84 $94,097.84 $0.00 n94,097.84 $0.00 $94,097.84 $94,097.84 Date: 7/25/2019 NATION PARADISE CREEK PARK SITE REMEDIATION & IMPROVEMENTS CHANGE ORDER NO. 14 CIP NO. 18-07 DATE: - WORK PERFORMED BY: Whillock Contracting DESCRIPTION OF WORK: Fixed and Retractable Bollard Furnishing & Installation Analysis 1) Driver - 3/4" Rock 1) Sho Fabrication ACCOUNTING FOR TIME, MATERIALS, AND EQUIPMENT Unit HR HR Qty 1.50 4.00 Wage 35.00 80.00 Total 52.50 320.00 - -Total Labor: Labor Burden (27.02%): Labor Markup (20%): 94.63 TOTAL LABOR $ 372.50 $ 100.65 Unit Qty Rate Total 1) Envirofee Per Load EA 27.00 5.00 135.00 2) Ameristar Bollards LS 1.00 4,974.64 4,974.64 3) Fix Bollards - W8 X 31 LS 1.00 1,549.06 1,549.06 4) 3/4" Rock for Bollard Drain Line TON 3.00 22.00 66.00 5) 4" SDR 35 Perforated Pipe LS 1.00 124.34 124.34 6) Concrete CY 6.00 120.87 725.22 7) Concrete Truck Delivery Charge LS 1.00 200.00 200.00 8) Short Load Fee EA 3.00 16.28 48.84 9) 2" PVC LS 1.00 284.92 284.92 Sub -Total Materials: Taxes (8.5) Materials Markup (15%): TOTAL MATERIALS: $ 8,108.02 $ - $ 1,216.20 EQUIPMENT Unit Qty Rate Total 1) ITen Wheeler - 3/4" Rock HR 1.50 71.66 Sub -Total Equipment: Equipment Markup (15%): TOTAL EQUIPMENT: SUB TOTAL: 107.49 $ 107.49 16.12 123.61 SUSCONTRACrOft Unit Qty Rate Total Sub -total Subcontractor: Prime Contractor Markup (5%): TOTAL SUBCONTRACTOR: GRAND TOTAL: Attn: Customer. Chris Whitlock Contracting Location: Wilson Ave. & 21° St. San Diego, CA Project: Paradise Creek PO# / Job# Superior Ready Mix Concrete, LP 1508 W. Mission Rd Escondido, CA 92029 Phone (760) 745-0556 Fax (760) 740-9557 Date: Expiration: Concrete 15 July 2019 30 Sept 2019 Phone Fax / email: MIX NUMBER MIX DESCRIPTION APPROX YARDS PRICE/YARD 835P 2500 psi Tailgate mix..64 w/c $111.40- SALES TAX: Quoted prices Do Not indude sales tax. MINIMUM LOAD: A single delivery of less than 9 cubic yards will be charged minimum rates. One short load is allowed for a completion of a continuous pour.11111.r yard. STANDING TIME: Unloading time in excess of 4 minutes per cubic yard will be charged at $2.00 per minute. Unloading time starts at the time of arrival at job. SPECIAL PROVISIONS: Prices apply during normal working hours, Monday through Friday. 3/8" pump mix is not recommended for fiatwork. Concrete is a structural building material and not an aesthetic building material. Superior Ready Mix Concrete will not be responsible for pop outs, cracking, etc., when concrete is batched using materials within ASTM specifications. TEMPERATURE: Concrete temperature is subject to ambient conditions and is not controlled unless stated otherwise. Rock / Sand / Base MATERIAL U/M SOURCE or NOTE TRUCK TYPE PRICE/Unit DELIVERY/Unit SALES TAX: Sales tax will be charged on material only, not freight. Title to material passed to customer at time of loading into truck. MINIMUM LOAD: A delivery of less than 25 tons will be charged minimum rates. STANDING TIME: Unloading time in excess of 20 minutes for material and 40 minutes for asphalt will be charged at $2.00 per minute. Unloading time starts at the time arrival at the job. SPECIAL PROVISIONS: Prices apply during normal working hours, Monday through Friday. Price quoted per ton unless otherwise noted. Delivery charges are subject to PUC increase. Subject to availability. Night Asphalt Plant — 48 hours' notice for orders and 24 hours' notice for cancellation! PAYMENT TERMS: Net 30 days. INSURANCE: The insurance carrier for Superior Ready Mix Concrete, LP will not name contractor or owner as additional insured nor will it issue a Waiver of Subrogation endorsement in favor of contractor or owner. DELIVERY: Orders taken with the intent to deliver on time. There is no guarantee as to rate or time of delivery. Additional charges may apply for canceled orders or orders put on hold. MATERIAL SELECTION: The products quoted are not warranted or suggested for any specific application. Buyer is hereby wamed that the selection and ordering of any particular product is the responsibility of the buyer and that the buyer assumes any and all risk associated with the selection of the product. QUOTED RATES: Prices apply to valid Superior Ready Mix account, check, or cash sales only Quoted By: polrc Risie# jkniefft superiorrm.com Office 760-745-0556 X 1132 CeII 760-801-6202 Accepted by: This proposal is subject to signed acceptance by the buyer within 30 days from date hereof after which time it will he of no force or effect except at the option of the seller. Quotation Attn: Chris WHILLOCK CONTRACTING INC. PO BOX 2322 LA MESA, CA 91943-2322 Acct#: 218280 Date: Monday, June 10, 2019 Quote Created: Wednesday, September 26, 2018 Effective From: Thursday, April 18, 2019 Quote Expiration: Saturday, May 18, 2019 Price Expiration: Sunday, June 30, 2019 Quote Name: Quote #: Sales Rep : Phone: Fax : Email: Vulcan Materials Company and Subsidiaries PARADISE CREEK PARK - NATIONAL CITY 569609 201500580805 21ST ST & HARDING AVE / NA1 NATIONAL CITY, CA 91950 Lawson Sanford 7220 Trade Street SAN DIEGO, CA 92121 858-530-9459 Special Instructions: RIP RAP TRUCKING WILL BE BILLED HOURLY AT $128/HR WITH A 6 HR MINIMUM PER TRUCK. sanfordl@vmcmail.com Vulcan has performed analytical testing on Carroll Canyon's aggregates per the guidelines set forth by DTSC's Clean Imported Fill Material advisory, with the exception of CA Title 22 metals, which was performed using EPA Method 200.7. All analyte levels are below the USEPA's Regional Screening Levels (RSL's) for residential soil. The source area sampled consists of undisturbed native materials that have not been subject to Impacts from industrial processes or sources. STONE Plant CHULA VISTA STONE CHULA VISTA STONB CHULA VISTA STONE CHULA VISTA STONE CHULA VISTA STONE CHULA VISTA STONE CHULA VISTA STONE CHULA VISTA STONE CHULA VISTA STONE SAND & GRAVEL Plant CARROLL CANYON S&G RECYCLED PRODUCTS Plant CARROLL CANYON RECYCLE CARROLL CANYON RECYCLE tmVulatC011et can,.. we.MyValun nm Product Name 3/41N CL 2 BASE $MIN CR AGG BASE 1 1/2IN CR WASHED ASTM #57 3/41N CR UNWASHED SE-30 WASHED CONCRETE SAND CALTRANS BACKING #2 CALTRANS BACKING #1 Product Name Import Soil Product Name 3/41N CL 2 RECYCLED BASE 3/41N CL 2 RECYCLED BASE FOB Haul Product # QtyU/M Plant Rate 16020 250 Tons $10.00 • 6.35 Truck Type STD FRT RATE ��a 16040 250 Tons 6.35 Truck Type STD FRT RATE 24010 98 Tons $25.00 6.35 Truck Type STD FRT RATE 25290 255 Tons 520.00 6.35 Truck Type STD FRT RATE 26060 750 Tons 518.00 6.35 Truck Type STD FRT RATE 31450 300 Tons $9 00 6.35 Truck Type STD FRT RATE 31820 35 Tons 525.00 6.35 Truck Type STD FRT RATE 4M160 15 Tons 526.00 0.00 4M170 1,050 Tons $26.00 0.00 FOB Product# QtyU/M Plant QS1000 40,500 Tons $4 17 Truck Type STD FRT RATE Product # QtyU/M 16035 1,500 Tons Truck Type STD FRT RATE 16035 1,500 Tons Truck Type BOTTOM DUMP FOB Plant $6.00 Haul Rate 8.63 Haul Rate 8.83 $8.00 7.32 Delivered $16.35 $24 35 $31.35 $26 35 $24.35 $15.35 $31 35 Delivered $1280 Delivered $14.83 $13.32 Page 1 of 3 AMERLSTAlt ASSA ABLOY Ameristar Tulsa 1555 N Mingo Road Tulsa, OK 74116 SALES QUOTE Order Number: 794106-SQ Order Date: 8/29/2019 Total (USD): $4,974.64 Page: 1 of 1 Sold To: 4329447 Ship To: 4329447 RIVERSIDE SSC CASH CUSTOMER 5678 CONCURS ST ONTARIO CA 91764 UNITED STATES RIVERSIDE SSC CASH CUSTOMER 5678 CONCURS ST ONTARIO CA 91764 UNITED STATES Customer PO: quote Order No: 794106 SQ Job Name: Price Book: Carrier & Freight Method: CCF #/Reference Order: Load No: 0 Freight Terms: Terr: P06 FOB ORIGIN, FREIGHT PREPAID Quote No: Order By: Delivery Instructions: CHRIS Taken By: JASGOI Header Notes: Line Plant No Bid DocumentsProvided / Minimal requirements from the Contractor Quote is for a base system. No Specification Plans or Sequence ofOperation provided at the time of quote. It is the responsibility of theContractor to ensure this quote meets the requirements of the ConstructionDocuments. Please verify. Item Number / Description Qty/UM Weight List Discount Net Extended 1.000 Requested Date: 8/29/2019 Scheduled Date: 8/29/2019 Tulsa, OK 943424X 4.5"X36" RET SS GA T/HND PKG 2 / EA 260.00 1,751.5753 1,751.5753 3,503.15 2.000 Requested Date: 8/29/2019 Tulsa, OK FREIGHT Freight Signature: Scheduled Date: 8/29/2019 1 / EA 1,200.0000 1,200.0000 Total Order Weight: 260.00 Additional Savings Applied: .0000 This acknowledgment supersedes the customer's purchase order in representing current pricing & shipping information. If the customer for any reason is not in agreement with the information listed above, please contact Customer Service at 1-888-333-3422 upon receipt of this document (delay in contact may affect the scheduled ship date). Any changes to this order may be subject to processing fees. Please refer to the Terms & Conditions section in the price book(s). Ameristar Perimeter Security USA Inc. This quote is valid for 15 days R5942565 PSG0007 JDEAMRACK. qfs Terms: Credit Card 1,200.00 Total Sale $3,503.15 Sales Tax $271.49 Freight $1,200.00 Total (USD) $4,974.64 ERP 8/30/2019 170825 DP. 08/30/19 0608 PM 1110 RELIANCE METALCENTER 2100 Cleveland Avenue Reliance National City CA 91950 Metalcenter® 619-263-2141 - Phone 619-474-3935 -Fax Sold to: WHILLOCK CONTRACTING P.O. Box 2322 La Mesa CA 91943 SALES QUOTATION Date Quote Number Buyer Sales Person Mode of Delivery Payment Terms Ship to: WHILLOCK CONTRACTING 346 FRONT ST El Cajon CA 92020 8-21-2019 RSQ-009709 Mark Hicks MHicks@rsac.com 619-259-5399 N30 Thank you for this opportunity to quote your metal requirements. If you have any questions or wish to place an order, please contact your Inside Sales Representative Line Item Description Proc Quantity UOM Weight Group Price UOM Amount Lead Time 1 101266 HOT ROLLED WIDE FLANGE BEAM W8" X 31# (7.995" X 0.285") ASTM A992 6' 3" (75") To be bevel cut on one end per customer drawing 4 pcs 25 FT 775 # 190.00 pcs $760.00 8-21-2019 2 101266 HOT ROLLED WIDE FLANGE BEAM W8" X 31# (7.995" X 0.285") ASTM A992 9' 6" (114") To be bevel cut on one end per customer drawing 2 pcs 589 # 298.00 pcs $596.00 8-21-2019 19 FT 3 101538 HOT ROLLED PLATE 1/4" ASTM A36 8" X 8" Delivery Charges 6 pcs 0 FT Total Weight Subtotal 27.23 # 10.00 pcs 15.00 Lot $60.00 8-21-2019 $15.00 Charges Net Amount Sales tax Total 1,391 # $1,416.00 $15.00 $1,431.00 $118.06 $1,54906 ***Sales Quotation is Subject to Confirmation at time of Order."" This Quotation is not a Guarantee of Price or Availability as Price may Change for any Reason, at Reliance's Discretion. Changes to Quantity, Ship Date, Delivery Destination or any Term or Condition of Inquiry or Order may result in a Change in the Price and Availability at Reliance's Discretion. Any Ship Date not Firm and immediate will be Subject to Price Change. A written Purchase Order may be required. Surcharges and Increases may apply at time of Shipment. Please review this document for Errors and Omissions. Terms and conditions can be viewed at: http://reliancemetalcentersd.com/forms-center/3269136 Form 030619 Page 1 of 1 FERGUSON` WATERWORKS FERGUSON WATERWORKS #1083 11909 TECH CENTER COURT POWAY, CA 92064 Phone: 858-391-3700 Fax: 858-391-5958 Deliver To: 231451 From: Cody Reilly Comments: 15:57:53 SEP 13 2019 Bid No: B350280 Bid Date: 09/13/19 Quoted By: CPR Customer: Cust PO#: WHILLOCK CONTRACTING INC PARADISE CREEK PARK SITE PO BOX 2322 LA MESA, CA 91943 FERGUSON WATERWORKS #1083 Price Quotation Phone: 858-391-3700 Fax: 858-391-5958 Cust Phone: 619-579-0700 Terms: NET 10TH PROX Ship To: WHILLOCK CONTRACTING INC PARADISE CREEK PARK SITE PO BOX 2322 LA MESA, CA 91943 Job Name: PARADISE CREEK PARK SITE Rom Dsscripdon SDR35SWPPP20 4X20 SDR35 SW PVC SWR PERF PIPE C0420100B 4X100 SILT GUARD FLTR SOCK Quantty 60 100 Not Primo UM Total 1.080 FT 0.290 FT 64.80 29.00 Page 1 of 1 Net Total: Tax: Freight: Total: $93.80 $7 98 $0.00 $101.78 Quoted prices are based upon receipt of the total quantity for immediate shipment (48 hours). SHIPMENTS BEYOND 48 HOURS SHALL BE AT THE PRICE IN EFFECT AT TIME OF SHIPMENT UNLESS NOTED OTHERWISE. QUOTES FOR PRODUCTS SHIPPED FOR RESALE ARE NOT FIRM UNLESS NOTED OTHERWISE CONTACT YOUR SALES REPRESENTATIVE IMMEDIATELY FOR ASSISTANCE WITH DBE/MBE/BE/SMALL BUSINESS REQUIREMENTS Seller not responsible for delays, lack of product or increase of pricing due to causes beyond our control, and/or based upon Local, State and Federal laws goveming type of products that can be sold or put into commerce. This Quote is offered contingent upon the Buyer's acceptance of Seller's terms and conditions, which are incorporated by reference and found either following this document, or on the web at https://www.ferguson.com/content/website-info/terms-of-sale Govt Buyers: All items are open market unless noted otherwise. LEAD LAW WARNING: It is illegal to install products that are not "lead free" in accordance with US Federal or other applicable law in potable water systems anticipated for human consumption. Products with *NP in the description are NOT lead free and can only be installed in non -potable applications. Buyer is solely responsible for product selection. WATER FLOW RATE NOTICE: Lavatory Faucets with flow rates over 0.5 GPM are not allowed for 'public use' in California. HOW ARE WE DOING? WE WANT YOUR FEEDBACK! Scan the QR code or use the link below to complete a survey about your bids: https://survey.medallia.com/?bidsorder&fc=1083&on=25432 From: Mitchell.Harkev@Wereuson.com To: Chris Subject: FW: Email Bid# B345060 Date: Monday, July 15, 2019 9:54:10 AM Attachments: image001.onq SEPARATE BID AS REQUESTED MITCH Thank v<nr, Mitchell Harkey Outside Sales Waterworks 11909 Tech Center Ct. Poway, Ca. 92064 USA C: 619-279-6065 0: 858-391-3700 F: 858-391-5958 E: mitchell.harkeyanferguson.com www.ferguson.com/waterworks Pollardwater From: Mitchell Harkey - 1083 SOCALWW <mitchell.harkey@ferguson.com> Sent: Monday, July 15, 2019 9:53 AM To: Harkey, Mitchell [Ferguson] - 1083 SAN DIEGO CA - WW <Mitchell.Harkey@Ferguson.com> Subject: Email Bid# B345060 Price Quotation # B345060 FERGUSON WATERWORKS #1086 1149 N MARSHALL AVE SUITE B EL CAJON, CA 92020 Phone : 858-391-3700 Fax: 858-391-5958 Bid No B345060 Bid Date...: 07/15/19 Cust Phone: 619-579-0700 Quoted By: MGH Terms • NET 10TH PROX Customer.: WHILLOCK CONTRACTING INC Ship To WHILLOCK CONTRACTING INC PARADISE CREEK PARK SITE PARADISE CREEK PARK SITE PO BOX 2322 PO BOX 2322 LA MESA, CA 91943 LA MESA, CA 91943 Cust PO#..: Job Name.: PARADISE CREEK PARK SITE I it it r r r I Item Description Quantity Net Price UM Total P4OBEPK20 2X20 FT PVC S40 BE PIPE 260 I 101.000 I C Subtotal: $262.60 Inbound Freight: $0.00 Tax: $22.32 Order Total: 4:021t 262.60 Item Code Description Notice P4OBEPK20 2X20 FT PVC S40 BE PIPE WARNING: Cancer and Reproductive Harm - k1 k1 NN.1)65‘‘tunings.ca gov Quoted prices are based upon receipt of the total quantity for immediate shipment (48 hours). SHIPMENTS BEYOND 48 HOURS SHALL BE AT THE PRICE IN EFFECT AT TIME OF SHIPMENT UNLESS NOTED OTHERWISE. QUOTES FOR PRODUCTS SHIPPED FOR RESALE ARE NOT FIRM UNLESS NOTED OTHERWISE. CONTACT YOUR SALES REPRESENTATIVE IMMEDIATELY FOR ASSISTANCE WITH DBE/MBE/WBE/SMALL BUSINESS REQUIREMENTS. Seller not responsible for delays, lack of product or increase of pricing due to causes beyond our control, and/or based upon Local, State and Federal laws governing type of products that can be sold or put into commerce. This Quote is offered contingent upon the Buyer's acceptance of Seller's terms and conditions, which are incorporated by reference and found either following this document, or on the web at https:/lwww•ferguson.com/content/website-info/terms-of-sale. Govt Buyers: All items quoted are open market unless noted otherwise. LEAD LAW WARNING: It is illegal to install products that are not "lead free" in accordance with US Federal or other applicable law in potable water systems anticipated for human consumption. Products with *NP in the description are NOT lead free and can only be installed in non -potable applications. Buyer is solely responsible for product selection. WATER FLOW RATE NOTICE: Lavatory Faucets with flow rates over 0.5 GPM are not allowed for 'public use' in California. HOW ARE WE DOING? WE WANT YOUR FEEDBACK! Enter the following link to complete a survey about your bids: https://survey.medallia.com/?bidsorder&fc=1083&on=25432 Uwwl 6141 .8 MY 9NI0NVH a TV' 5ON1tlV3e 10 S1SV6 SW 1336 31(1 33 .011.31d1460 31. .01J3dSN1 966Ob3C (Ka) scla-aM (us) OWC-us (613) 0660XV6 63134 5.3610 306VJ1A0N10 Drown O350Nvtl3 ,ansa nr e31vn133aS anam EMU x3wuxuusens leer Wa/s 9VU0 aa(vums V cu 63000 30Nvw W xrs-11s6 (a19) Hve xNM1V3NMIW x03 .xr-ws (scs) OWlSPO vaNn'ONOwn a S3Vw6 JWval 431avu 31v0 s11S-Ks (Re) Owv. 3v1n 011LLJ313 31V0 JB 'OM SAN :NO1.31tlfS SON003O NOLLOn&SN00. 3nR)Pd7131 01N3111NVd30 UI ILLn 1N31LL6Yd30 ONIN33NION3 Wvv-s,-v1<1\ro\w4\m-moo000- na3".e rfb slse 110n •11 wn 16n0 wn s none Paige xns a NSTNA VRRRU-RRRRaRI-PAGANINT.,”-.ti's_E9. M ENGINEERING DEPARTMENT UTILITY DEPMTNPNTS socaa TEIEPNCNE ' CONSTRUCTION RECORDS SURVEYOR: NV5 INC. AS-aOLT REVISIONS to TNANGE ORDER nD p RIF WALL RENS. A(AENDUN a 1i roh DATE OPT MNE KNG INNTIC SIGNALS AL c, lWA BUSTARD TONS. RAMNA IYEVERS AT&T SUaSTRUCNFCS, IRED RRUSE S9EETRATER AUTHORITY, PR (NIEMGSIIE REPAURNS. PETER NAIR0W30 (aaa) 9J9-ST9 BM) 60E-631H (619) xaa-aw (919) 5T4-2n* (919) A09-67S6 (axa) 320-0996 DATE STARTED: 919ECTOR DATE ORIP1ETE0: SEE TOIL SHEET FOR aAAS OF BEARINGS AND SOURCE Or TOPOONAPNR NVS NNa i I l 20th ST. zd a a 3a e` dg R 8 S e tut 6 4 A NWiAYMA1Ep sm EE SHEET 15 SEE SHEET 13 WCTALL r o c WALL A �M uE vm•er0c ,Isamurz wuWw a MST Me KOK MO DM Six TO OE OW EAST OF EAST sew FOP • =xC O <Ci r. m MINN / 1 !/ NiV!5 D UJR&1pN R NESPONSO1E CHYME PP DP FOAM PF MOP 00019 PPP. WAN MI PK MEN PI MOW MOM IP DAMP MO P•70100. IN WIPP W0136101, MOSSO MI PP PP Pf MP PPP PPP PEPPI1011 •I IP MY OP PPP cnr• es cormll 10 • NBA OW MO OM KO .M 40,14.1100, 5/11/20111 PAIVASE CREEK NW CITY OF NAIIO AL a1Y Mow MOP MI-:,. TAB, MW• M00% POPP PRI POP KM O.:BMOC NO PPE IMO 6i0Z 3Nflf £ - 019 - )l Vd IVNOIIVJfl03 N331:1J 3SI0V9Vd - 91-81 dIJ N930 '9 3N0L Y9 CO IIll00150 900 xu0l 63100]9(1010* I SI A.W'6 51N1 6U. 501.tl9B f0 5.13 3. .10D0403 191.31310.1 A 1L 9331.10N . .0 .K 61N061.9A333 SL0.0N .110190 '1339A 10Tlrvg3NN000000150N1 0 v'3001'(L00 ) «61 DLLOidm'35 .0 55.9.13 .S Z 09rONvls .1991.0109 cgivi D. 9A03 3190 .113103.141 NII9U ■Ny(O0*1900 1 N01L)'n310 dL3919 d* SCS x di ligEV 9e a. in 59- OLD (9L9) 00 N `4°3 s 7.Osuneawy A raa 09 dO b3ddY3lg6 A i ZOOM 5911 LL . 33105 4— Nam .64 1 Rio <9 (919) 351.1 03Nf ssWllonhu59n5 1i10 5.106M39 9595-99L (619) 593.310 3.1M'6 ia39Y311091NO3 600 .9L9-959 (999) 00Y15n0 3GN11 vdoon 9 51006 3113011 9119-959 (999) OAg9 3b1 .016110333 3.0 ONOIDDIV 131n9-s9 0dlIV5 �3013na115 501003N. N00311311.S400. 3900S . 3N0Nd4l31 w 51031513Yd40 011100 9.1030 .w 9,-r09119000'.w wn N1 th'd30 014I213310N3 •..-n.0 0-s .0'l9. 99.9..9.1910 sweet a 40 If 10 .we To •1A...nm. FINISH SURF BEVELED EDGE DG PA I-12' DIA. SCN 40 GALV. PPE HNDRA L AND MID -MIL PAIN SIDE (� r111 . -: ' I� II lI-1l...`.,.,....... uI.................:.:...... _.....:........+I= 1 A�.A k SFIKEWBD a T 20d GAly. 11='il-n-iw;u-.;1=r:=u-.:u`=n=u•;n=`H= Ir•=i1-.n=1_ ii. II= ��- Fie ::11=!I::��:il.7.; ��I,-1 ��.I' -,m�11 _ 1- i�:Il.� di lY 11 i:i �� r: ill `�"'y1ji TDGREEKSIDEDFPDST ll''IIE=I2111.11=1,41'-11=.11=.11=11=11.=.11=11=11=11 =L ��.A.Q��p�.:'..,� zooPBICGNCFrG.-Pam .ii �r°iroir=ir=�arn.��arTrniiarn n:n nji r=:Trn:n °ar ir= �-`fit =' rMi=..- GAB�N BAS GRADE ®SaL GP n r ir.=n 7r n=" 71 .i Ir II - 11=11=n n ni 1„I p ° 1�,i 7..4 117.. .. � v,A ��+- >'s:ae�v�Ycv �Y 1 ! 1!11 re n 1- 11 i�i �i0i�i��y� v �i�0i !pj�� � j � Oi�Oj.:, . Oi�0i�0i�� y�Oj�iv..s. • i��i� �j' � •> .. ', %i,� ���.. , ,������ ��G���i`�i%,�i`��i���i�,�i`��i`��i,4 �� �4G��i`44.N..p, \ p �`�r��Gp�i���r���ip�������������p��� GABION WALL SECTION 12,0 CUM 1.112'DIA. SCN 40 G1LV. PIPE POSTS B-P O.C: CENTER IN CONCRETE FTG. w GALV. WIRE TES TOP 8 BOTT. GABON WALL C pA x 7B'2'Ili O PSI CCNC. FTG. CREEK SIDE so' 00. (TYYT PAINSIOE BEVATION -A 1-1/7 DI& SCH 40 GALV. PIPE HAIDRAL AND MID -RAIL 1-17 DIA SCH 40 GALV. FIRE POSTS ® 5-0' 0.C. CENTER IN CONCRETE FTG. GABION BASKET FINISH SURFACE SCALE 1? • 1'd \\\��\\\ ,"!=.:J"loin( /OPA rL�\t' /1/ nxu.mxoon O� CITY OF NATIONAL CITY Office of the City Clerk 1243 National City Blvd., National City, California 91950-4397 619-336-4228 Michael R. Dalla, CMC - City Clerk WHILLOCK CONTRACTING Paradise Creek Park Site Remediation & Improvements, CIP No. 18-07 Change Order #14 Judith Hernandez (Engineering/Public Works) forwarded a copy of the Change Order to Whillock Contracting.