HomeMy WebLinkAbout2019 CON Dick Miller - Paradise Creek Water Quality and Community Enhancements, CIP No. 18-11 - Change Order #1lTI
Paradise Creek WQ&C Enh.
CIP No: 18-11
Contractor: Dick Miller Inc.
CHANGE ORDER NO. 1
November 12, 2019
Reason/Purpose for this Change Order:
The city has directed the contractor to excavate and construct a 12" thick aggregate base access road in lieu
of the dirt access road shown on the project plans.
The City of National City and Contractor agree to the following change to the original Contract.
The contractor has been directed to excavate and remove a 12' wide by 9" section of subgrade and place a
12' wide by 12" section of aggregate base with tapered edges for the length of the access road shown on the
plans. All work including all labor, equipment and export of subgrade material will be performed for the lump
sum price listed below.
Original Contract Amount $ 1,010,101.01
Net change by previously authorized Change Orders
Subtotal
Amount of this change order
New contract amount
Working days added: 0
Working days subtracted: 0
1,010,101.01
39,460.00
$ 1,049,561.01
Percent change in Contract to date 3.91 %
Subm,;ttQd
by:
..
roje
a _
r
/
///i /,
Date
'
City ,•je
M alter
r r i(111
Date
povedby:
2,
Cit ngineer
,
Date
City Ma
, require or
ange Orders >$24,999 D e
By signing this Change Order the Contractor confirms that he/she is completely familiar with its terms and conditions and has fairly
negotiated its price, terms and conditions. If this Change Order is approved, Contractor will provide all of the equipment, materials and
labor necessary to provide a complete work as described above at that the price stated herein. Additionally, Contractor confirms that the
price is fair and complete and represents all costs associated with the work, including but not limited to all equipment, materials, labor,
supervision, overhead, fees, bonds, insurance, profit, etc. and that there will be no further compensation. All of the terms and conditions
of the original contract documents are incorporated herein. (2 originals: 1 for City Clerk, 1 for Contractor)
Accepted and agreed to by (DMI):
.....l.7..1ii►.....eat.,,.
Name:
Date
Note to Contractor: If you do not agree with this Change Order you may be directed to proceed with this work under the terms of the
contract and you may proceed under protest. You must comply with the contract requirements of submitting a written protest to protect
your claim.
Originals: City Clerk, Contractor cc: Engineering project file, Project Manager
to./ l3
1243 National City Boulevard, National City, CA 91950 Telephone (619) 336-4380
"A
�'
GENERAL
a
+t - 1- .,.
ENGINEERING CONTRACTOR
DMI
930 Boardwalk, Suite H, San Marcos, CA 92078
Phone 760-471-6842 FAX 760-471-6178
Contractor's State License No. 380204, A, B, C-12 - DVBE / SBE #53651
DMI RFCO NO. 001
ROAD PARADISE WATER IMPROVEMENT
ACCESS
Proposal Submitted To:
ICCS, LLC
Phone:
951-532-6483
Fax:
Date Submitted:
10123119
Street:
PO BOX 6211
Job Name:
PARADISE CREEK WATER IMPROVEMENT
Date Work Performed:
City, State and Zip Code:
NORCO, CA. 92860
Job Location
PARADISE CREEK AVE NATIONAL CITY
Attention:
SEAN GILL
Architect:
Plan Sheets:
E-Mail:
sgill(a)iccsinc.net
Spec Section: N/A
Addendas Noted: N/A
ITEM
DESCRIPTION
ESTIMATED
QUANTITIES
UNIT
MEASURE
UNIT
PRICE
TOTAL
RFCO ACCESS ROAD
1
EXCAVATION & EXPORT FOR ROADWAY CONSTRUCTION 9" DEPTH
183.00
CY
$75,00
$13,725.00
2
REMOVE AND REPLACE DRIVEWAY APPROCH WITH SDRSD G-14D
1.00
EA
$6,600.00
$6,600.00
3
PROVIDE & INSTALL 12" VIRGIN CL II BASE
445.00
TN
$43.00
$19,135.00
TOTAL AMOUNT OF PROPOSAL
$39,460.00
GENERAL EXCLUSIONS:
1. BONDS & PERMITS, OR RELATED COSTS ABOVE ITEMS, COMPLETE, IN -PLACE, PER PLANS & SPECS
2. TESTING, LAB FEES, INSPECTIONS AND MIX DESIGN COSTS
3. SURVEYING, STAKING, LAYOUT, ENGINEERING
4. SANITATION FACILITIES
5. TEMPORARY OR PERMANENT FENCING, PROTECTIVE BARRIERS OR SAFETY FENCING
6. WORK IN THE PUBLIC RIGHT-OF-WAY
7. UTILITY WORK AND/OR LOCATING OF EXISTING UTILITIES
8. REPAIR OR REPLACEMENT OF UNDOCUMENTED OR UNMARKED UNDERGROUND UTILITIES
9. CAPPING OF WELLS
RFCO PARADISE CREEK WATER
1 of 2
11/1/2019 11:26 AM
10. NIGHT, WEEKEND, HOLIDAY OR OTHER OVERTIME WORK
11. DEMOLITION, DOWELLING, SAWCUTTING, CORING AND/OR PATCHING
12. ROCK EXCAVATION INCLUDING: BLASTING, BREAKING, RIPPING OR HANDLING OF MATERIALS THAT CANNOT BE
PRODUCTIVELY MOVED OR RIPPED WITH A JOHN DEERE 310 BACKHOE
13. CONSTRUCTION WATER AND/OR METER (OWNER TO PROVIDE ON -SITE WATER SOURCE AT NO COST TO DMI)
14. DEWATERING, WATER DIVERSION OR PUMPING OF WATER
15. STORM WATER POLLUTION PREVENTION PLAN AND/OR IMPLEMENTATION OF SWPPP MEASURES
16. COMPACTION OVER 90%
17. IMPORT OR EXPORT OF SUBGRADE MATERIAL
18. SELECT BACKFILL MATERIAL, OTHER THAN OUTLINED IN JOB SPECIFICATIONS
19. BUTTRESS AND/OR STABILITY FILLS
20. SPECIAL HANDLING OR DRYING OF MATERIAL
21. HANDLING OR EXPORTING OF OTHER TRADES' SPOILS
22. SPECIAL SUBGRADE STABILIZATION
23. SHORING, FORMING, BRACING AND/OR TEMPLATES OF ANY KIND
24. HANDLING OR DISPOSING OF HAZARDOUS MATERIALS
25. CONCRETE WORK OR FLATWORK
26. PRECISE GRADING FOR CURBING, HARDSCAPE OR LANDSCAPED AREAS
27. WATERPROOFING
28. IRRIGATION SYSTEMS
29. LANDSCAPING OR SEEDING
30. ASPHALT PAVING WORK AND/OR ROCK BASE
31. TRASH CLEANUP OR REMOVAL
32. DEBRIS BOXES
33. ANY OFFSETS TO CONTRACT BILLINGS FOR JOINT CHECKS MADE BETWEEN SUBCONTRACTORS AND/OR SUPPLIERS.
NOTES:
1. PRICES GOOD FOR WORK COMPLETED THROUGH 3/30/20. WORK COMPLETED AFTER 3/30/20 IS SUBJECT TO ADJUSTMENT FOR
INCREASED COSTS OF LABOR, EQUIPMENT, TRUCKING AND/OR MATERIAL.
2. ALL PRICING BASED ON NORMAL 8 HOUR SHIFTS, BETWEEN 7 AM AND 5 PM, MONDAY-FRIDAY. NO NIGHT, WEEKEND OR
HOLIDAY WORK.
3. PRICES ARE BASED ON ALL ITEMS OF WORK BEING PERFORMED. ANY DELETIONS OF SCOPE MAY RESULT IN PRICE ADJUSTMENTS.
4. IF A LETTER OF SUBROGATION IS REQUIRED, A 2% PREMIUM WILL BE ADDED TO THE TOTAL CONTRACT PRICE.
2. ALL PRICING BASED ON NORMAL 8 HOUR SHIFTS, BETWEEN 7 AM AND 5 PM, MONDAY-FRIDAY. NO NIGHT, WEEKEND OR
HOLIDAY WORK.
3. PRICES ARE BASED ON ALL ITEMS OF WORK BEING PERFORMED. ANY DELETIONS OF SCOPE MAY RESULT IN PRICE ADJUSTMENTS.
4. IF A LETTER OF SUBROGATION IS REQUIRED, A 2% PREMIUM WILL BE ADDED TO THE TOTAL CONTRACT PRICE.
5. IF PAYMENT & PERFORMANCE BONDS ARE REQUIRED, ADD AT 2% OF CONTRACT PRICE.
DMI IS A CERTIFIED DVBE I SDVOSB / SB I SLBE, NONUNION COMPANY
1. Terms: Payment upon completion unless otherwise noted.
2. DMI will not be liable for delays due to fires, floods, accidents, strikes or any other cause beyond its control.
3. Buyer agrees to pay court costs and reasonable attomey's fees in the event of default, if this contract is turned over to an attomey for enforcement or
collection. All sums not paid when due shall thereafter bear interest at maximum interest allowed by law.
4. DMI will provide necessary Worker's Compensation, Public Liability and Property Damage Insurance.
5. This proposal shall be null and void if written acceptance and notice to proceed are not received within 30 days.
6. This proposal does not include engineering, inspection, permits or fees unless noted above.
7. Contractors are required by law to be licensed and regulated by the Contractors' State License Board, 1020 N Street, Sacramento, CA 95814.
Acceptance of Proposal
Please sign and retum one copy. This quotation constitutes the sole and only
agreement. Any agreements, negotiations, etc., not set forth herein are of no
force or effect.
Date of Acceptance:
Submitted for DMI
BY: JOHN MARTINEZ
Signature:
RFC() PARADISE CREEK WATER
2 of 2
11 /1 /2019 11:26 AM
CITY OF NATIONAL CITY
Office of the City Clerk
1243 National City Blvd., National City, California 91950-4397
619-336-4228
Michael R. Dalla, CMC - City Clerk
DICK MILLER
Paradise Creek Water Quality and Community Enhancements,
CIP No. 18-11
Judith Hernandez (Engineering/Public Works) forwarded a copy of the Change Order to
Dick Miller.