HomeMy WebLinkAbout2019 CON Fordyce Construction - 1430 Hoover Ave. Tenant Improvements, CIP No. 19-07, Change Order #71
PROJECT PROFESSIO ,• LS CORPORATION
CHANGE ORDER MEMORANDUM
December 26, 2019
To: Roberto Yano
Acting City Engineer
Engineering and Public Works Department
City of National City
From: Alex Preciado
Project Manager
Project Professionals Corp
Project: 1430 Hoover Ave Warehouse Tenant Improvements
CIP No.: 19-07
Subject: Change Order No. 7
RECEIVED
Ei'JG'' DEPT.
Zjll JAN -° P 5: 4
CITY OF NATIONAL CITY
Change Order No. 7 provides for:
The addition of sixty-four (64) working days to the contract.
Supporting Information:
The additional 64 days that are to be added to the contract time are to accommodate the re -design and
coordination of the fire backflow preventer to meet National Fire Protection Association, California Building
Code and Sweetwater Authority requirements. The additional days that are needed are reflected on the Weekly
Statement of Working Days which will bring the time of completion within contract requirements.
Time Adjustment:
Sixty -Four (64) working days are to be added to the original contract.
Cost Adjustment:
There is no cost adjustment associated with this time extension.
Proj t Manager Date
1430 HOOVER AVE WAREHOUSE IMPROVEMENTS CHANGE ORDER NO. 7
CIP NO. 18-07 December 26 2019
Contractor: Fordyce Construction
9932 Prospect Ave, #138
Santee, CA 92071
This Change Order modifies Contractor's and the City's obligations and rights under the
abovementioned contract. This change order is not effective until approved by the City.
Time Adjustment:
Sixty Four (64) working days are added to the contract time to accommodate for the re -design and
coordination of the backflow preventer to meet National Fire Protection Association (NFPA)
requirements and California Building Code requirements.
Cost of Change Order:
The City and the Contractor agree that the Contract will add 64 working days to
accommodate for the re -design and coordination of the backflow preventer to meet
National Fire Protection Association and California Building Code requirements. The
City and the Contractor agree that there is no cost associated with this time
extension and will capture substantial completion within contract requirements.
Recommended by Project Manager: 4 /
Date: \ $ 2s�z-,)
By signing this Change Order the Contractor confirms that he/she is completely familiar with and has fairly
negotiated its price, terms and conditions. If this Change Order is approved, Contractor will provide all of the
equipment, materials and labor necessary to provide a complete work as described above at that the price
stated herein. Contractor confirms that the price is fair and complete and represents all costs associated with
the work, including but not limited to all equipment, materials, labor, supervision, overhead, fees, bonds,
insurance, profit, etc. and that there will be no further compensation. All of the terms and conditions of the
original contract documents are incorporated herein. The signer for the Contractor confirms that he/she is
authorized to bind the Contractor to this Change Order.
Agreed and Accepted by Contractor: v
(Print Name and Title) Cl�-.-+—..-
Date: 01-08-20
Approved by City Engineer: ),`S !/,
Date: //d//20
Approved by City Manager: O
(Required for change orders $25,000 and above)
Date:
-0— CALIFORNIA —�
NATIONAL arTy
�e� r
1430 Hoover Ave Tenant Improvements
CIP No. 19-07
WEEKLY STATEMENT OF WORKING DAYS
To: Fordyce Construction
The following statement indicates the number of WORKING days charged to your contract
for the week ending: November 15, 2019
Date
Day
Weather/ other conditions
Working Days
Non -working Day
11/11/19
Monday
Holiday
0
0
11/12/19
Tuesday
Clear
1
0
11/13/19
Wednesday
Clear
1
0
11/14/19
Thursday
Clear
1
0
11 /15/19
Friday
Clear
1
0
Days this report
4
0
TIME EXTENSIONS
Days Approved CCO
that
Days this report
0
0
Days previously reported
0
0
Total days to date
0
0
COMPUTATION OF CALENDAR DAYS
Date
Number of Days
First working day
7/3/19
581
Number of Working Days
30
Original Date of Completion
8/15/19
611
Total time extensions to date
0
Total non -working days
0
Subtotal
30
New date of completion
8/15/19
611
Revised total number of working days
30
Total expired working days to date
94
Workin. da s remainin.
-64
Remarks:
lam- Pv&TtZ It AS. 1�
P ect Manager
Contractor Name
Note: The contractor has fifteen (15) calendar days to protest this statement in writing, otherwise this
statement will be deemed correct and accepted by the contractor.
\U\kAiEll A,,
,ni�11111,,\`
CITY OF NATIONAL CITY
Office of the City Clerk
1243 National City Blvd., National City, California 91950-4397
619-336-4228
Michael R. Dalla, CMC - City Clerk
Fordyce Construction
1430 Hoover Ave. Warehouse Improvements, CIP No. 18-07
Change Order #7
Judith Hernandez (Engineering/Public Works) forwarded copies of the Change Order to
Fordyce Construction.