l;ITY OF NATIONAL CITY
CHANGE ORDER MEMORANDUM
April 29, 2020
To: Roberto Yano, P.E. & Jose Lopez, P.E.
Director of Engineering & Public Works, Deputy City Engineer
Engineering and Public Works Department
City of National City
From: Alex Preciado
Project Manager
Project Professionals Corp
Project: Las Palmas Pool Facility Roof Replacement
CIP No.: 19-50
Subject: Change Order No. 1
Change Order No. 1 provides for:
The replacement of damaged miscellaneous wood materials on Las Palmas Pool Facility Building 1 and Building 2.
Supporting Information:
During demolition of the existing roof system of building 1 and building 2 of Las Palmas Pool, it was discovered
that isolated areas of plywood decking, facia, and ledger had been damaged due to the reoccurring water leaks
through the existing roof. Prior to installation of the new TPO roof system, it was determined to replace the
damaged roof areas to minimize City maintenance and provide a completely new roof system. The quantities of
wood replacement are below;
Building 1
1,280 SF of CDX Plywood
40 LF of 2"x8" Lumber
40 LF of Corner Ledger
Building 2
- 96 SF of CDX Plywood
52 LF of 2"x8" Lumber
Time Adjustment:
Three (3) Working Days are suggested to be added to the contract time for miscellaneous wood replacement.
Cost Adjustment:
The total cost for replacing all damaged miscellaneous wood at Las Palmas Pool Facilities is $7,964.00. This will be
paid for by the allowance line item #5, Miscellaneous Wood Replacement (Deck, Trim, Fascia, Etc.)
Pro' ct Manager Date
CALIFORNIA
NT I ONA L (3117
?!: av •
lNCO[tPbti ltT�� �
Las Palmas Pool Facility Roof Replacement CHANGE ORDER NO. 1
CIP NO. 19-50 April 29, 2020
Contractor: Preman Roofing
875 34"' Street
San Diego, CA 92102
This Change Order modifies Contractor's and the City's obligations and rights under the
abovementioned contract. This change order Is not effective until approved by the City.
Time adlustment:
Three (3) working days are added to contract time for the replacement of damaged miscellaneous wood
at Las Palmas Pool Facility's roofs.
Cost of Change Order
The City and the Contractor agree that the Contractor shall proceed under a Time
and Material basis to remove and replace damaged wood on Las Palmas Pool
Facilities Roofs. The City and the Contractor agree that the following wood
quantities have been replaced per building;
Building 1
- 1,280 SF of CDX plywood
- 40 LF of 2"x8' lumber
- 40 LF of corner ledger
Building 2
- 96 SF of CDX plywood
- 52 LF of 2"x8' lumber.
The City and the Contractor agree that there is no additional cost to the contract
and all associated work, labor, equipment and materials required to complete this
work under a time and material basis totals to an agreed price of $7,964.00 and be
paid per allowance Bid Line Item 45, Miscellaneous Wood Replacement.
Total Cost Summary of Miscellaneous Wood Replacement
$7,964.00
$7,964.00
Recommended by Project Manager:
Date: ' ,) t % l)
By signing this Change Order the Contractor confirms that he/she is completely familiar with and has fairly
negotiated its price, terms and conditions. If this Change Order is approved, Contractor will provide all of the
equipment, materials and labor necessary to provide a complete work as described above at that the price
stated herein. Contractor confirms that the price is fair and complete and represents all costs associated with
the work, including but not limited to all equipment, materials, labor, supervision, overhead, fees, bonds,
insurance, profit, etc. and that there will be no further compensation. All of the terms and conditions of the
original contract documents are incorporated herein. The signer for the Contractor confirms that he/she is
authorized to bind the Contractor to this Change Order.
Agreed and Accepted by Contractor:
(Print Narne and Title)
\ Date:
Approved by City Engineer: (j ,
vv
Date:
6hh®
Approved by City Manager:
(Required (or change orders $25,000 and above)
Date:
CALIFORNIA
tauQNA weint
!N('ON1'(ilt It VI,
Las Palmas Pool Facility Roof Replacement
CIP NO. 19-50
DATE: -
CHANGE ORDER NO. 1
WORK PERFORMED BY: Preman Roofing
DESCRIPTION OF WORK: Replace Miscellaneous Wood Building 1
ACCOUNTING FOR TIME, MATERIALS, AND EQUIPMENT
2)
Remove and Replace CDX Plywood
Remove and Replace 2x8
Unit
SF
LF
Qty
1,280.00
40.00
Rate
3.00
10.00
Total
3,840.00
400.00
4)
Remove and Replace NE Corner Ledger
LF
40.00
69.90
2,796.00
Sub -Total Materials:
$ 7,036.00
Materials Markup (15%): -
TOTAL MATERIALS:
GRAND TOTAL:
\11r
CALIFORNIA
NATIONAL CITY
/^� t :i '1
OI(PUI( A, t U
Las Palmas Pool Facility Roof Replacement
CIP NO. 19-50
DATE: -
CHANGE ORDER NO. 1
WORK PERFORMED BY: Preman Roofing
DESCRIPTION OF WORK: Replace Miscellaneous Wood Building 2
ACCOUNTING FOR TIME, MATERIALS, AND EQUIPMENT
1) Remove and Replace CDX Plywood
Unit
SF
Qty
96.00
Rate
3.00
Total
288.00
2)
Remove and Replace 2x8
LF
22.00
10.00
220.00
3)
Remove and Replace 2x8
LF
30.00
14.00
420.00
Sub -Total Materials:
$ 928.00
Materials Markup (15%): -
TOTAL MATERIALS:
GRAND TOTAL:
Judith Hernandez
''
From:
Sent:
To:
Cc:
Subject:
Attachments:
Alex Preciado <alex@ppc-sd.com>
Wednesday, May 20, 2020 1:32 PM
Judith Hernandez
Luca Zappiello
CIP No. 19-50 Las Palmas Roof - Change Order #1
Signed CCO #1.pdf
CAUTION: This email originated from outside your organization. Exercise caution when opening attachments
or clicking links, especially from unknown senders.
Hi Judy,
Please see attached change order #1 for processing for the above referenced project.
Let me know if you have any questions.
Thank you!
Alex Preciado, CMIT
Construction Manager
4499 Ruffin Road, Suite 250
San Diego, CA 92123
Office 858.634.8180
Fax 858.634.8184
1
Vendor:
CONTRACT TRANSMITTAL FORM
(Attach as Cover Sheet to Documents dropped off to City Clerk's Office)
Date:
From (Dept.): Ot /
Submitted by (First & Last Name): �l% d 1 1`'( /1C YTI d vt.
4rtirrrzzr-i_ PNit, (Oa A
Resolution: YES /
0 .,
Resolution No. (if applicable):
1 2 3 4 Originals Provided to City Clerk (Select Quantity)
90 0
giDepartment has Copy / Duplicate Original
17 Vendor has Copy / Duplicate Original