Paradise Creek WQ&C Enh. CHANGE ORDER NO. 2
CIP No: 18-11 May 14, 2020
Contractor: Dick Miller Inc.
. Reason/Purpose for this Change Order:
The city has directed the contractor to adjust the hydroseed mix locations called out on the original plans.
The City of National City and Contractor agree to the following change to the original Contract:
.The contractor has been directed to adjust the hydroseed locations as originally called out on the plans. The
mix designs were incorrectly called out requiring an adjustment in the original unit price and quantity. This
change order provide full compensation to the contractor for all work including all labor, equipment and
;material and will be performed for the lump sum price listed below.
i
Original Contract Amount $ 1,010,101.01
Net change by previously authorized Change Orders 39,460.00
Subtotal
1,049,561.01
Amount of this change order 2,468.40
New contract amount $ 1,052,029.41
Working days added: 0 Working days subtracted: 0
Submitted by:
5-21-20
Project Mar I . Proje
Approved b
City E
ee
Percent change in Contract to date 4.15%
ger
£W3120z
Date
Date City Manager, required for Change Orders>S24,999 Date
By signing this Change Order the Contractor confirms that he/she is completely familiar with its terms and conditions and has fairly
negotiated its price, terms and conditions. If this Change Order is approved, Contractor will provide all of the equipment, materials and
labor necessary to provide a complete work as described above at that the price stated herein. Additionally, Contractor confirms that the
price is fair and complete and represents all costs associated with the work, including but not limited to all equipment, materials, labor,
supervision, overhead, fees, bonds, insurance, profit, etc. and that there will be no further compensation. All of the terms and conditions
of the original contract documents are incorporated herein. (2 originals: 1 for City Clerk, 1 for Contractor)
Accepted and geed to by (DMI):
Name: Date
Note to Contractor: If you do not agree with this Change Order you may be directed to proceed with this work under the terms of the
contract and you may proceed under protest. You must comply with the contract requirements of submitting a written protest to protect
your claim.
Originals: City Clerk, Contractor cc: Engineering project file, Project Manager
vs/ 2 eozp
1243 National City Boulevard, National City, CA 91950 Telephone (619) 336.4380
A
DMI
930 Boardwalk, Suite H, San Marcos, CA 92078
Phone 760-471-6842 FAX 760-471-6178
Contractor's State License No. 380204, A, B, C-12 - DVBE / SBE #53651
DMI JOB NO. 19020
PROPOSAL HYDROSEED QUANTITIES DIFFERENCE
PARADISE CREEK WATER QUALITY COMMUNITY ENHANCEMENTS PROJECT
CONTRACT NO.:
Proposal Submitted To:
City of National City
Phone:
951-532-6483
Fax:
Date Submitted:
02111/20
Street:
1243 National City BvId
Job Name:
Paradise Creek Water Quality Community Enhancements Project
Date Work Performed:
TBD
City, State and Zip Code:
National City, CA 91950
Job Location
3624 Paradise Valley Rd, National City CA 91950
Architect:
Plan Sheets:
Attention:
11500-9-D
E-Mall:
Sean Gill
Spec Section:
Addendas Noted: NIA
sgillCn)iccsinc.net
ITEM
DESCRIPTION
ESTIMATED
QUANTITIES
UNIT
MEASURE
UNIT
PRICE
TOTAL
PROPOSAL HYDROSEED QUANTITIES DIFFERENCE
H
HYDROSEED QUANTITIES DIFFERENCE
1.00
LS
$2,420.00
$2,420.00
Delta quantity between original proposal and revised quantities for mix #1 and mix#2
TOTAL
FOR THE
ABOVE ITEMS:
$2,420.00
2.0% ADD FOR
INCREASED BOND & INSURANCE COST:
$48.40
ADDITIONAL WORKING DAYS REQUESTED:
TOTAL AMOUNT OF PROPOSAL:
$2,468.40
Submitted for DMI
BY: Es4ib sy Maya'
Proposal
1 of 1 2/11/2020 5:16 PM
REVISED QUANTITIES PER FIELD RECOMENDATIONS
acific Rim Hijdroseedin.
In.
28319 Valley Center Rd.
Valley Center, CA 92082
760-751-7055
760-751-7385 Fax
760-638-6227 Don's Cell / 760-638-6217 Cory's Cell
teresa.pacificrim@yahoo.com
CA Lic. #886257
CA SB Cert #1211120
ARB Certified
DIR Reg #1000006248
Dick Miller, Inc.
930 Boardwalk, Ste H
San Marcos, CA 92078
Customer Phone
760-471-6842
Customer Fax
760-471-6178
Bid Proposal
DELTA AMOUNT BETWEEN PROPOSAL 1 & 2
$10,964.00 - $8,544.00
= $2,420,00
Description
Qty
Rate
Total
Paradise Creek Water Quality
National City, CA
COMMON SLURRY FOR ALL MIXES:
Application One
. Mulch. 500Ibs/acre
Compost. 1000 Ibs/acre
Biosol 7-2-1. 800 Ibs/acre
Tri C Soluble Humate. 1 Ibs/acre
Mycorh izza I I nn oc. 60 Ibs/acre
Application Two
. Bonded Fiber Matrix. 2000 Ibs/acre
Square Foot Coverage - Seed Mix #1
Square Foot Coverage - Seed Mix #2
Bid considers 2 move -ins, additional at $650.00
Bid considers prevailing wages
Bid considers 2.5" water source at site
Bid includes all equipment, labor & listed materials.
Bid docs not include preparation or maintenance.
Bid does not guarantee germination or growth.
Bid considers no retention
Bid considers standard insurance requirements, additional
insurance requirements will result in additional cost.
Waiver of subrogation will result in additional cost.
55,000
6,300
0.173
0.23
9,515.00
1,449.00
TOTAL = $10,964.00
Agreed to and Accepted in its Entirety by:
Date:
GENERAL RNOINRRNnO CONTRACTOR
pIde k!!l14INC.
930 80AROWAIR•SU11[ G•SAN MARCOS•CA•97071
0: 760.471.6847•t: 160.471.6176
PURCHASE ORDER NO.
19020-002
DMI JOB NO.
19020
DATE: 10122/2019
PROJECT: PARADISE CREEK WATER QUALITY IMPROVEMENTS
Cost Code
TO: PARADISE RIM HYDROSEEDING INC
ADDRESS: 28319 VALLEY CENTER RD
SHIP TO: DICK MILLER INC. - JOB SITE
CITY, STATE, ZIP: VALLEY CENTER CA 92082
PHONE NUMBER: 760.751.7055
FAX NUMBER: 760.751-7385
CONTACT: TERESA
ADDRESS: 3624 PARADISE VALLEY RD
CITY, STATE, ZIP: NATIONAL CITY CA 91950
TBM:
EMAIL: teresa.pacificrim@yahop.com
QUOTE NO.:
DELIVERY: YOUR TRANSPORT • BEST WAY
WHEN NEEDED: ASAP
OTHER:
PAYMENT TERMS: I NET 30 DAYS.
DESCRIPTION
QTY
UNIT
UNIT PRICE
TOTAL PRICE
COMMON SLURRY FOR ALL MIXES:
APPLICATION ONE
MULCH 500 LBSIACRE
COMPOST 1000 LBSIACRE
BIOSOL 7-2-1 800 LBSIACRE
TRI C SOLUBLE HUMATE 1 LBSIACRE
MYCH. INNOC GO LOBS/ACRE
APPLICATION TWO
BONDED FIBER MATRIX 2000 LBSIACRE
SQUARE FOOT COVERAGE - MIX 1
6,300
SF
$0.23
$1,449.00
SQUARE FOOT COVERAGE- MIX 2
55,000
SF
$0.129
$7,095.00
02
NOTE: ALL PRODUCTS TO BE PER PLANS & SPECIFICATIONS.
TOTAL-
$8,544.00
QUANTITIES & TIME FRAMES NEEDED ARE APPROXIMATE. PLEASE CONFIRM QUANITITY & TIMING BEFORE PRODUCTION.
NOTE: PLEASE PROVIDE THE APPLICABLE SUBMITTALS AS SOON AS POSSIBLE. DO NOT BEGIN PRODUCTION UNTIL YOUR
SUBMITTALS HAVE BEEN APPROVED.
PURCHASE ORDER PREDICATED UPON SUBMITTAL APPROVAL
LEAD TIME IS 8-10 WEEKS UPON SUBMITTAL APPROVAL
PURCHASE ORDER NUMBER MUST APPEAR ON ALL INVOICES. PLEASE NOTIFY US IAIMEDIATF.LY IF YOU ARE UNABLE. TO COMPLETE THIS ORDER
BY THE DATE SPECIFIED.
ACCEPTED BY:
PRINTED NAME:
DATE:
AUTHORIZED BY: ESTEBAN MONTOYA
DATE: 10/22/2019
PLEASE SIGN AND RETURN ONE COPY OF THIS PURCHASE ORDER.
1 of 1
10/22/2019 11:18 AM
acific Rim I Ijc1roseeclin,
Inc.
28319 Valley Center Rd.
Valley Center, CA 92082
760-751-7055
760-751-7385 Fax
760-638-6227 Don's Cell / 760-638-6217 Cory's Cell
teresa.pacificriin@yahoo.com
CA Lie. #886257
CA SB Cert#1211I20
ARB Certified
DIR Reg #I000006248
Dick Miller, Inc.
930 Boardwalk, Ste H
San Marcos, CA 92078
Customer Phone
Customer Fax
760-471-6842
760-471-6178
Description
Paradise Creek Water Quality
National City, CA
COMMON SLURRY FOR ALL MIXES:
Application One
Mulch 500 lbs/acre
Compost 1000Ibs/acre
Biosol 7-2-1 800 Ibs/acro
Tri C Soluble Humate 1 lbs/acre
Mych. I nnoc. 60 Ibs/acre
Application Two
Bonded Fiber Matrix 2000 Ibslacre
Square Foot Coverage - Mix 1
Square Foot Coverage - Mix 2
Bid considers 1 move -in, additional at $650.00
Bid considers prevailing wages
Bid considers 2.5" water source at situ
Bid includes all equipment, labor & listed materials.
Bid dots not include preparation or maintenance.
Bid does not guarantee germination or growth.
Bid considers no retention
Bid considers standard insurance requirements, additional
insurance requirements will result in additional cost.
Waiver of subrogation will result in additional cost.
Agreed to and Accepted In Its Entirety by:
Date:
Rate
6,300 0.23
55,000 0.129
Total
1,449.00
7,095.00
TOTAL $8,544.00
CALIFORNIA
Amount of this change order
NCOI? PO A AT Ell -
Paradise Creek WQ&C Enh. CHANGE ORDER NO. 3
CIP No: 18-11 May 14, 2020
Contractor: Dick Miller Inc.
Reason/Purpose for this Change Order:
The city has directed the contractor to remove unknown concrete encountered and modify slope, backfill and
grade as needed on a T&M basis.
The City of National City and Contractor agree to the following change to the original Contract:
The contractor has been directed to remove unknown concrete found during the excavation of the 12" SDR-35
on a T&M basis. Near station 5+00 the contractor encountered an old concrete road The material was •
removed, broken up and hauled off site. The contractor was also directed to modify sloped grades at the
project gabion walls and backfill and compact area as needed. This change order provides full compensation
to the contractor for all work including all labor, equipment and material and was performed on a T&M basis
for the lump sum price listed below.
Original Contract Amount $ 1,010,101.01
41,928.40
Net change by previously authorized Change Orders
Subtotal 1,052,029.41
2,320.03
New contract amount
Working days added: 0 Working days subtracted: 0
Submitted by:
5-21-20
Project Manager
Approved
Date
-.� G/t o/r•-w
City EDate JCity Manager, required for char,g. Ord= 424,99e Date
By sign j this Change Order the Contractor confirms that he/she is completely familiar with its terms and conditions and has fairly
negotiated its price, terms and conditions. If this Change Order is approved, Contractor will provide all of the equipment, materials and
labor necessary to provide a complete work as described above at that the price stated herein. Additionally, Contractor confirms that the
price is fair and complete and represents all costs associated with the work, including but not limited to all equipment, materials, labor,
supervision, overhead, fees, ponds, insurance, profit, etc. and that there will be no further compensation. All of the terms and conditions
of the original contract documents are incorporated herein. (2 originals: 1 for City Clerk, 1 for Contractor) •
$ 1,054,349.44
Percent change in Contract to date 4.38%
Date
Accepted and agreed to by (DMI):
' --�— -- -t--t 4r -.
Name:
•
S120 /1.‘02.1)
Date
Note to Contractor: If you do not agree with this Change Order you may be directed 10 proceed with this work under the terms of the
contract and you may proceed under protest. You must comply with the contract requirements of submitting a written protest to protect
your claim.
Originals: City Clerk, Contractor
cc: Engineering project file, Project Manager
1243 National City Boulevard, National City, CA 91950
Telephone (619) 336-4380
DMI
930 Boardwalk, Suite H, San Marcos, CA 92078
Phone 760-471-6842 FAX 760-471-6178
Contractor's State License No. 380204, A, B, C•12 • DVBE I SBE #53651
DMI JOB NO. 19020
COR #003: REMOVE EXISTING UNFORESEEN CONCRETE FROM TRENTCHLINE AS
NEEDED TO EXCAVATE FOR PROPOSED 12" SD. SIZE CONCREET TO 2' MINUS FOR
EXPORT. BACKFILL TO RELAYOUT TRENCH. GABION WORK
PARADISE CREEK WATER QUALITY COMMUNITY ENHANCEMENTS PROJECT
CONTRACT NO.:
Proposal Submitted To:
City of National City
Phone:
951-532-6483
Fax:
Date Submitted:
03104120
Street:
1243 National City Bvld
Job Name:
Paradise Creek Water Quality Community Enhancements Project
Date Work Performed:
2/18/2020,313/2020
City, State and Zip Code:
National City, CA 91950
Job Location
3624 Paradise Valley Rd, National City CA 91950
Attention:
Sean Gill
Architect:
Plan Sheets:
11500.9-D
E-Mail:
soiIIt iiccsinc.net
Spec Section:
Addendas Noted: NIA
ITEM
DESCRIPTION
ESTIMATED
QUANTITIES
UNIT
MEASURE
UNIT
PRICE
TOTAL
COR
#003
COR #003: REMOVE EXISTING UNFORESEEN CONCRETE FROM
TRENTCHLINE AS NEEDED TO EXCAVATE FOR PROPOSED 12"
SD. SIZE CONCREET TO 2' MINUS FOR EXPORT. BACKFILL TO
RELAYOUT TRENCH. GABION WORK
MATERIALS:
TOTAL FOR MATERIAL ADD:
EQUIPMENT:
U55 EXCAVATOR
6.00
$62.22
$373.32
AIR COMPRESSOR WITH TOOLS
4.00
$28.52
$114.08
CREW TRUCK
4.00
$25.01
$100.04
COMPACTION WHEEL
4.00
$31.25
$125.00
(NOTE: ALL EQUIP. RATES INCLUDE TAXES, FUEL, 8 MISC COSTS)
TOTAL EQUIPMENT MARK UP 15%
$106.87
SUBTOTAL FOR EQUIPMENT ADD:
$819.31
LABOR:
JIM DASHNEY - OPERATOR
4.00
HRS
$101.41
$405.64
RUBALDINO GAYTAN - LABORER
2.00
HRS
$73.22
$146.44
JAMES COOPER - OPERATOR
4.00
HRS
$101.41
$405.64
PEDROHERNANDEZ-LABORER
4.00
HRS
$73.22
$292.88
LABOR MARK UP 20%
$250.12
SUBTOTAL FOR LABOR ADD:
$1,500.72
TOTAL
FOR THE ABOVE.ITEMS:
' $2;320:03
ADDITIONAL WORKING DAYS REQUESTED:
TOTAL AMOUNT OF COR#003:
$2,320.03
BY
Submitted for DMI
JOSE MENDOZA
Change Orders & Log
1 of 1
3/31/2020 11:58 AM
tIthiria( Ci+y �. CONTRACTORCustomer:L�,�r
Job Name:PA& j6(, Cr ,e W Vr ( a 1.4 : I D2 d
DESCRIPTION OF WORK:
1.1 1 b t;
Field T&M Form
Date: 2 - /8 - Zozo
ete t t7V1li QX i ,g4'j AS IA n -to r SestA CohC r'� ei -ere Nl ' r64011 ! I rte.- /i$
ek_el este.A'a, I -err- fro Po J2" 3b . Si Zo_ 00644m-re- 'f» 2 r 1Yli..iw S
fsi expert-. elem.(, het de -to reladaf- with &V e0 '. eowiry t-
MATERIALS
Quantity
Units
Size
Work Performed By:
Description
Vendor/Source
Unit Price
Extension
EQUIPMENT
Description
Vador/Sauce
I lours
SUBTOTAL
MARK UP %
TOTAL MTL & OTHER EXP.
Rate
Extension
U5C t Etas' 410 r
1\ pe)
2,
err CoMPress Or lu' 408
Are K.
44,
SUBTOTAL
MARK UP %
TOTAL EQUIPMENT
Narac
Class.
Hours OT Hrs DT Hrs Hr Rate OT Rate
DT Rate
Extension
:ftrvaashNoy
R,lbaldtne irk
Of
L
SUBTOTAL
MARK UP %
TOTAL LABOR
REPORT TOTAL
The above breakdown is a specific change to the existing contract_ All other conditions of the a original co tract remain ip force.
Please sign one '�s y and ret it to our office.
Submitted By:
Accepted By:
Date:
White: Office Yellow: Customer Pink: Field
Customer
Na-flnnaI C;ly
Job Name: Par44tjb Creek IAlex 0,„1l-r
DESCRIPTION OF WORK:
DM
GENERAL ENGINEERING CONTRACTOR
Job #:
11020
11155
Field T&M Form
Date: 3— 3— 2 0 2
API) trQT on Enos c4 (-, *' nj4-o o13i 4- -4v vi i Gab%sn ICjrr-i .
Re, r.oa^ paor and ,r�roLck _P141, ,4 ,c ,'Q,,t as mole./
MATERIAIS
Quantity Units Size
Work Performed By:
Dcscripinm
Vendor/Source Unit Price
Extension
EQUIPMENT
Description
SUBTOTAL
MARK UP%
TOTAL MT', & OTHER EXP.
Vendur/Se acc Hours Rate Extension
U55 ItitSeyrq. &cell V4'fnp
Affx
y
LABOR
Name
Class.
Hans
OT Hrs DT Hrs
Hr Rate
OT Rate
SUBTOTAL
MARK UP %
TOTAL EQUIPMENT
DT Rate
Extension
.s efoorpr
Or
y
Ptd ro fit rnalil-
L
I
SUBTOTAL
MARK UP %
TOTAL LABOR
REPORT TOTAL
The above breakdown is a specific change to the existing contract. All other condition o original c . ntract remain in force.
Please sign one cps and returgi( to our office.
Submitted By:
Accepted By:
Dat
White: Otbee Yellow: Customer Pink: Field
CALIFORNIA
ti
NATIONAL cITy
INr0nYOHATti'
Paradise Creek WQ&C Enh. CHANGE ORDER NO. 4
CIP No: 18-11 May 14, 2020
Contractor: Dick Miller Inc.
fReason/Purpose for this Change Order:
The city has directed the contractor to modify an existing wingwall to match the new slope grade.
The City of National City and Contractor agree to the following change to the original Contract:
The contractor has been directed to modify the wing wall installed by cutting it down flush with the slope grade.
The wall will then need to be chipped down at each steel location, cut steel below surface and patch locations
as needed. This change order provides full compensation to the contractor for all work including all labor,
equipment and material for the lump sum price listed below.
Original Contract Amount $ 1,010,101.01
Net change by previously authorized Change Orders 44,248.43
Subtotal
Amount of this change order
New contract amount
Working days added: 1 Working days subtracted. 0
Submitted by:
Project Manager
Approved by,
5-21-20
Date
CityIncur oate City Manager,requ*edforchangeOrders>$24,999 Date
1,054,349.44
4,436.67
$ 1,058,786.11
Percent change in Contract to date 4.82%
Date
By sigrif g this ChAnge Order the Contractor confirms that he/she is completely familiar with its terms and conditions and has fairly
negotiated its price, terms and conditions. If this Change Order is approved, Contractor will provide all of the equipment, materials and
labor necessary to provide a complete work as described above at that the price stated herein. Additionally, Contractor confirms that the
price is fair and complete and represents all costs associated with the work, including but not limited to all equipment, materials, labor,
supervision, overhead, fees, bonds, insurance, profit, etc. and that there will be no further compensation. All of the terms and conditions
of the original contract documents are incorporated herein. (2 originals: 1 for City Clerk, 1 for Contractor)
Accepted and agreed to by (DM!):
t
oglzpizozo
Name: Date
Note to Contractor: If you do not agree with this Change Order you may be directed to proceed with this work under the terms of tho
contract and you may proceed under protest. You must comply with the contract requirements of submitting a written protest to protect
your claim.
Originals: City Clerk, Contractor cc: Engineering project file, Project Manager
1243 National City Boulevard, National City, CA 91950 Telephone (619) 336-4380
r4' Sda:
• DMI
• 930 Boardwalk, Suite H, San Marcos, CA 92078
Phone 760-471-6842 FAX 760-471-6178
Contractor's State License No. 380204, A, B, C-12 - DVBE I SBE #53651
DMI JOB NO. 19020
COR #007: CUT 5" TO 6" OFF OF THE TOP OF HEADWALL & PATCH
PARADISE CREEK WATER QUALITY COMMUNITY ENHANCEMENTS PROJECT
CONTRACT NO.:
Proposal Submitted To:
City of National City
Phone:
951-532-6483
rax
Date Submitted:
05106120
Street
1243 National City Bvld
Job Name:
Paradise Creek Water Quality Community Enhancements Project
Date Work Performed:
City, State and Zip Code:
National City, CA 91950
Job Location
3624 Paradise Valley Rd, National City CA 91950
Attention:
Sean Gill
Architect
Plan Sheets:
11500-9-D
E-Mail.
sqill@iccsinc.net
Spec Section
Addendas Noted: NIA
ITEM
DESCRIPTION
ESTIMATED
QUANTITIES
UNIT
MEASURE
UNIT
PRICE
TOTAL
COR
#007
COR #007: CUT 5" TO 6" OFF OF THE TOP OF HEADWALL &
PATCH
MATERIALS: INCLUDE TAX 8.75%
CONCRETE PATCH
3.00
BAG
$18.00
$54.00
TOTAL MATERIAL MARK UP 15%
$8.10
• TOTAL FOR MATERIAL ADD:
- $62.10
EQUIPMENT:
WALL SAW (OPERATED BAKER CONCRETE CUTING)
8.00
HRS
$200.00
$1,600.00
AIR COMPRESSOR
6.00
HRS
$28.52
$171.12
CREW TRUCK
4.00
HRS
$25.01
$190.04
U55 EXCAVATOR
4.00
HRS
$62.22
$248.88
(NOTE: ALL EQUIP. RATES INCLUDE TAXES, FUEL, & MISC COSTS)
TOTAL EQUIPMENT MARK UP 15%
$318.01
SUBTOTAL FOR EQUIPMENT ADD:.
$2,438.05
LABOR:
JIM DASHNEY - OPERATOR
4.00
HRS
$101.41
$405.64
RUBALDINO GAYTAN - LABORER
8.00
HRS
$73.22
$585.76
_
PEDRO HERNANDEZ - LABORER
8.00
HRS
$73.22
$585.76
LABOR MARK UP 20%
$315.43
SUBTOTAL FOR LABOR ADD:
$1,892.59
TOTAL FOR THE ABOVE ITEMS: •
. • $4,392.74
1% ADD BOND
& INSURANCE
$43.93
ADDITIONAL WORKING DAYS REQUESTED: 1.00
TOTAL AMOUNT OF COR#007:
$4,436.67
BY
Submitted for DMI
JOHN MARTINEZ-
Change Orders & Log
1 of 1
5/6/2020 4 26 PM
CALIFORNIA
Paradise Creek WQ&C Enh.
CIP No: 18-11
Contractor: Dick Miller Inc.
NATIONALCft
Wk �^~�
(-- INCORPO1tAT£1)
CHANGE ORDER NO. 5
May 14, 2020
Reason/Purpose for this Change Order:
The city has granted the contractor 22 additional working days as requested due to rain delays.
The City of National City and Contractor agree to the following change to the original Contract:
The contractor has submitted a request for 22 additional working days due to rain' delays. This is a no cost
change order and includes all days reviewed and evaluated as requested by the contractor. There were
several days the contractor was unable to perform at the site due to wet or muddy conditions, the contractor
was making repairs from previous storm events and unable to perform contract work or was preparing site
BMPS for upcoming storm events. This change order provides full compensation to the contractor for all days
and work including all labor, equipment and material impacted by rain events and no addition days or
compensation will be allowed..
Original Contract Amount... $ 1,010,101.01
Net change by previously authorized Change Orders
Subtotal
Amount of this change order
44, 248.43
1,054,349.44
New contract amount $ 1,054,349.44
Working days added: 22 Working days subtracted: 0 Percent change in Contract to date 4.38%
Submitted by:
Project Manager
Approved b
City E n-_
iNc•ps.
tow
Date JCity Mana er,requ+r+,aforChangeoro.rs>$24,999 Date
By sign this Ch ge Order the Contractor confirms that he/she is completely familiar with its terms and conditions and has fairly
negotiated its pric , terms and conditions. If this Change Order is approved, Contractor will provide all of the equipment, materials and
labor necessary to provide a complete work as described above at that the price stated herein. Additionally, Contractor confirms that the
price is fair and complete and represents all costs associated with the work, including but not limited to all equipment, materials, labor,
supervision, overhead, fees, bonds, insurance, profit, etc. and that there will be no further compensation. All of the terms and conditions
of the original contract documents are incorporated herein. (2 originals: 1 for City Clerk, 1 for Contractor)
Accepted and agreed to by (DMI):
10
_....t_,..._,......_..�;....._.............. _...:.. __...._.......w o S 120 f Iv t
Name: Date
Note to Contractor: If you do not agree with this Change Order you may be directed to proceed with this work under the terms of the
contract and you may proceed under protest. You must comply with the contract requirements of submitting a written protest to protect
your claim.
Originals: City Clerk, Contractor
cc: Engineering project file, Project Manager
a3� .
1L40`1.,
1243 National City Boulevard, National City, CA 91950 Telephone (619) 336-4380
GENERAL ENGINEERING CONTRACTOR
930 BOARDWALK, SUITE H, SAN MARCOS,CA,92078
0: 760.471 .6842 F: 760.471 .61 78
February 27, 2020
CITY OF NATIONAL CITY
Engineering Department
1243 National City Boulevard
National City, CA 91950
Attn: Sean Gill C.C.M.
Re: Paradise Creek Water Quality and Community Enhancements CIP 18-11
Subject: Notice of Delay due to Unforeseen Conditions
Mr. Sean Gill:
As you know, the DMI crews are working diligently with your assistance to maintain the
latest schedule provided January 15,2020. To help in your planning, DMI is providing this
notice of delay due to unforeseen conditions. These unforeseen conditions are directly
related to the rain events the project experienced during the month of December 2019.
Due to the scope of work and nature of this project, the rehabilitation process after each
rain event had significant impact in production, subsequently affecting the project
schedule and completion date.
The contract term has as completion date of April 2"d, 2020. Due to the delays
rehabilitating the jobsite to normal conditions after the rain events, the new completion
date is scheduled to be May 6th, 2020. I have attached the Statement of Working Days #12
- #20 for your reference. Keep in mind the majority of working days in January were
devoted to the rehabilitation of the jobsite to normal conditions.
DMI assures you that we will do everything we can to minimize impacts beyond this date.
Your cooperation in minimizing this impact will be appreciated. Should you have any
questions or need additional information to support the necessity of the contract time
extension, please contact me (760) 471-6842
Thank you very much
Sincerely,
Esteban Montoya
Senior Project Engineer
CALIFORNIA 4--0-
sAwri.coNrAL
C rNCORpbRATE�
WEEKLY STATEMENT OF WORKING DAYS
PROJECT NAME
Paradise Creek Water Quality and Community Enhancements
CONTRACTOR
Dick Miller, Inc.
ADDRESS (Street, City, State, ZIP Code)
930 Boardwalk, Suite H San Marcos, CA 92078
CIP No.
18-11
DATE:
12/16/2019
THE FOLLOWING STATEMENT SHOWS THE NUMBER OF WORKING DAYS CHARGED TO YOUR CONTRACT
FOR THE WEEK ENDING: 12/14/2019,
DATE
DAY
WEATHER CONDITION
WORKABLE
DAYS
UNWORKABLE
DAYS
NOTES/
REASON FOR UNWORKABLE DAYS
12/8/2019
Sunday
Weekend
12/9/2019
Monday
Wet
1
Non -Working
12/10/2019
Tuesday
Wet
1
Non -Working
12/11/2019
Wednesday
Wet
1
Non -Working
12/12/2019
Thursday
Wet
1
Non -Working
12/13/2019
Friday
Wet
1
Non -Working
12/14/2019
Saturday
Weekend
DAYS THIS WEEK
DAYS PREVIOUSLY REPORTED
TOTAL DAYS TO DATE
0
5
40
12
40
17
CURRENT STATUS
WORKING DAYS SPECIFIED IN CONTRACT
100
APPROVED EXTENSION OF TIME
0
TOTAL AUTHORIZED TIME OF CONTRACT
100
LESS WORKABLE DAYS CHARGED
40
WORKING DAYS REMAINING
60
NOTE: ROUND ALL TIME TO THE
NEAREST 1/2 DAY.
SUMMARY OF WEEK'S ACTIVITIES
Contractor spent the week cleaning up the site from the prior week's rain event. Installing additional BMP's.
Project Engineer
c5feam pa/
NOTE:
The contractor will be allowed 10 days from the date of this report in which to protest in writing the correctness of this statement, otherwise it shall be
deemed to have been accepted as correct.
CALIFORNIA
INCORPORATED
WEEKLY STATEMENT OF WORKING DAYS
PROJECT NAME
Paradise Creek Water Quality and Community Enhancements
CONTRACTOR
Dick Miller, Inc.
ADDRESS (Street, City, State, ZIP Code)
930 Boardwalk, Suite H San Marcos, CA 92078
CIP No.
18-11
DATE:
12123/2019
THE FOLLOWING STATEMENT SHOWS THE NUMBER OF WORKING DAYS CHARGED TO YOUR CONTRACT
FOR THE WEEK ENDING: 12/21/2019
DATE
DAY
WEATHER CONDITION
WORKABLE
DAYS
UNWORKABLE
DAYS
NOTES/
REASON FOR UNWORKABLE DAYS
12/15/2019
Sunday
Weekend
12/16/2019
Monday
Sunny (Site wet)
1
Non -Working
12/17/2019
Tuesday
Sunny (Site wet)
1
Non -Working
12/18/2019
Wednesday
Sunny (Site wet)
1
Non -Working
12/19/2019
Thursday
Sunny (Site wet)
1
Non -Working
12/20/2019
Friday
Sunny (Site wet)
1
Non -Working
12/21/2019
Saturday
Weekend
DAYS THIS WEEK
DAYS PREVIOUSLY REPORTED
TOTAL DAYS TO DATE
0
5
40
17
40
22
CURRENT STATUS
WORKING DAYS SPECIFIED IN CONTRACT
100
APPROVED EXTENSION OF TIME
0
TOTAL AUTHORIZED TIME OF CONTRACT
100
LESS WORKABLE DAYS CHARGED
40
WORKING DAYS REMAINING
60
NOTE: ROUND ALL TIME TO THE
NEAREST 1/2 DAY.
SUMMARY OF WEEKS ACTIVITIES
Site has been too wet to perform contractor work. Contractor has been preparing site for upcoming storm events and making repairs from previous
storm events.
Project Engineer
c57-ea/mgr;
NOTE:
The contractor will be allowed 10 days from the date of this report in which to protest in writing the correctness of this statement, otherwise it shall be
deemed to have been accepted as correct.
N
+ CALIFORNIA
-
\t c* ryiLIL CIrT`
COAPORATE�
WEEKLY STATEMENT OF WORKING DAYS
PROJECT NAME
Paradise Creek Water Quality and Community Enhancements
CONTRACTOR
Dick Miller, Inc.
ADDRESS (Street, City, State, ZIP Code)
930 Boardwalk, Suite H San Marcos, CA 92078
CIP No.
18-11
DATE:
12/30/2019
THE FOLLOWING STATEMENT SHOWS THE NUMBER OF WORKING DAYS CHARGED TO YOUR CONTRACT
FOR THE WEEK ENDING: 12/28/2019
DATE
DAY
WEATHER CONDITION
WORKABLE
DAYS
UNWORKABLE
DAYS
NOTES/
REASON FOR UNWORKABLE DAYS
12/22/2019
Sunday
Weekend
12/23/2019
Monday
Rain
1
Non -Working
12/24/2019
Tuesday
Rain
1
Non -Working
12/25/2019
Wednesday
Holiday
1
Holiday
12/26/2019
Thursday
Rain
1
Non -Working
12/27/2019
Friday
Sunny (Site wet)
1
Non -Working
12/28/2019
Saturday
Weekend
DAYS THIS WEEK
DAYS PREVIOUSLY REPORTED
TOTAL DAYS TO DATE
0
5
40
22
40
27
CURRENT STATUS
WORKING DAYS SPECIFIED IN CONTRACT
100
APPROVED EXTENSION OF TIME
0
TOTAL AUTHORIZED TIME OF CONTRACT
100
LESS WORKABLE DAYS CHARGED
40
WORKING DAYS REMAINING
60
NOTE: ROUND ALL TIME TO THE
NEAREST 1/2 DAY.
SUMMARY OF WEEK'S ACTIVITIES
Site has been too wet to perform contractor work. Contractor has been preparing site for upcoming storm events and making repairs from previous
storm events.
Project Engineer
NOTE:
The contractor will be allowed 10 days from the date of this report in which to protest in writing the correctness of this statement, otherwise it shall be
deemed to have been accepted as correct.
`, CALIFORNIA
-sATIEINI 1L
�. ZNCOR,POiiATEp
WEEKLY STATEMENT OF WORKING DAYS
PROJECT NAME
Paradise Creek Water Quality and Community Enhancements
CONTRACTOR
Dick Miller, Inc.
ADDRESS (Street, City, State, ZIP Code)
930 Boardwalk, Suite H San Marcos, CA 92078
CIP No.
18-11
DATE:
1/6/2020
THE FOLLOWING STATEMENT SHOWS THE NUMBER OF WORKING DAYS CHARGED TO YOUR CONTRACT
FOR THE WEEK ENDING: 1/4/2020
DATE
DAY
WEATHER CONDITION
WORKABLE
DAYS
UNWORKABLE
DAYS
NOTES/
REASON FOR UNWORKABLE DAYS
12/29/2019
Sunday
Weekend
12/30/2019
Monday
Cloudy (Site wet)
1
Non -Working
12/31/2019
Tuesday
Sunny (Site wet)
1
Non -Working
1/1/2020
Wednesday
Holiday
1
Holiday
1/2/2020
Thursday
Sunny
1
Working
1/3/2020
Friday
Sunny
1
Working
1/4/2020
Saturday
Weekend
DAYS THIS WEEK
DAYS PREVIOUSLY REPORTED
TOTAL DAYS TO DATE
2
3
40
27
42
30
CURRENT STATUS
WORKING DAYS SPECIFIED IN CONTRACT
100
APPROVED EXTENSION OF TIME
0
TOTAL AUTHORIZED TIME OF CONTRACT
100
LESS WORKABLE DAYS CHARGED
42
WORKING DAYS REMAINING
58
NOTE: ROUND ALL TIME TO THE
NEAREST 1/2 DAY.
SUMMARY OF WEEK'S ACTIVITIES
Site has been too wet to perform contractor work. Contractor has been preparing site for upcoming storm events and making repairs from previous
storm events. DMI repaired 24" RCP pipe, backfilling and recompacting as needed.
Project Engineer
c57-ear& ,9tY/
NOTE:
The contractor will be allowed 10 days from the date of this report in which to protest in writing the correctness of this statement, otherwise it shall be
deemed to have been accepted as correct.
-*—, CALIFORNIA *—f+-
.1NT Air IM IL/ CIE WV
INCORPORATED
WEEKLY STATEMENT OF WORKING DAYS
PROJECT NAME
Paradise Creek Water Quality and Community Enhancements
CONTRACTOR
Dick Miller, Inc.
ADDRESS (Street, City, State, ZIP Code)
930 Boardwalk, Suite H San Marcos, CA 92078
CIP No.
18-11
DATE:
1/13/2020
THE FOLLOWING STATEMENT SHOWS THE NUMBER OF WORKING DAYS CHARGED TO YOUR CONTRACT
FOR THE WEEK ENDING: 1/11/2020
DATE
DAY
WEATHER CONDITION
WORKABLE
DAYS
UNWORKABLE
DAYS
NOTES/
REASON FOR UNWORKABLE DAYS
1/5/2020
Sunday
Weekend
1/6/2020
Monday
Sunny
1
Working
1/7/2020
Tuesday
Sunny
1
Working
1/8/2020
Wednesday
Cloudy
1
Working
1/9/2020
Thursday
Cloudy (Forecast Rain)
1
Non -Working
1/10/2020
Friday
Sunny
1
Working
1/11/2020
Saturday
Weekend
DAYS THIS WEEK
DAYS PREVIOUSLY REPORTED
TOTAL DAYS TO DATE
4
1
42
30
46
31
CURRENT STATUS
WORKING DAYS SPECIFIED IN CONTRACT
100
APPROVED EXTENSION OF TIME
0
TOTAL AUTHORIZED TIME OF CONTRACT
100
LESS WORKABLE DAYS CHARGED
46
WORKING DAYS REMAINING
54
NOTE: ROUND ALL TIME TO THE
NEAREST 1/2 DAY.
SUMMARY OF WEEK'S ACTIVITIES
Contractor processing bottom of basin, failed trenches, slopes and making general repairs from storm event.
Project Engineer
.5fea.& ge:i(
NOTE:
The contractor will be allowed 10 days from the date of this report in which to protest in writing the correctness of this statement, otherwise it shall be
deemed to have been accepted as correct.
a
} F l
Si
CALIFORNIA
" 'I. v r L crivir
C
a � r
INCORPORATED
WEEKLY STATEMENT OF WORKING DAYS
PROJECT NAME
Paradise Creek Water Quality and Community Enhancements
CONTRACTOR
Dick Miller, Inc.
ADDRESS (Street, City, State, ZIP Code)
930 Boardwalk, Suite H San Marcos, CA 92078
CIP No.
18-11
DATE:
1/20/2020 ,
THE FOLLOWING STATEMENT SHOWS THE NUMBER OF WORKING DAYS CHARGED TO YOUR CONTRACT
FOR THE WEEK ENDING: 1/18/2020
DATE
DAY
WEATHER CONDITION
WORKABLE
DAYS
UNWORKABLE
DAYS
NOTES/
REASON FOR UNWORKABLE DAYS
1/12/2020
Sunday
Weekend
1/13/2020
Monday
Sunny
1
Working
1/14/2020
Tuesday
Sunny
1
Working
1/15/2020
Wednesday
Sunny
1
Working
1/16/2020
Thursday
Sunny
1
Working
1/17/2020
Friday
Rain
1
Non -Working
1/18/2020
Saturday
Weekend
DAYS THIS WEEK
DAYS PREVIOUSLY REPORTED
TOTAL DAYS TO DATE
4
1
46
30
50
31
CURRENT STATUS
WORKING DAYS SPECIFIED IN CONTRACT
100
APPROVED EXTENSION OF TIME
0
TOTAL AUTHORIZED TIME OF CONTRACT
100
LESS WORKABLE DAYS CHARGED
50
WORKING DAYS REMAINING
50
NOTE: ROUND ALL TIME TO THE
NEAREST 1/2 DAY.
SUMMARY OF WEEK'S ACTIVITIES
Contractor processing basin slopes, creek bottom and repairing slopes as needed.
Project Engineer
ga(
NOTE:
The contractor will be allowed 10 days from the date of this report in which to protest in writing the correctness of this statement, otherwise it shall be
deemed to have been accepted as correct.
N
43-• CALIFORNIA —+
\VFf1.0Ni .. �-� , CR: WV
aoo
C' XAT cc) RPOR.per ED
WEEKLY STATEMENT OF WORKING DAYS
PROJECT NAME
Paradise Creek Water Quality and Community Enhancements
CONTRACTOR
Dick Miller, Inc.
ADDRESS (Street, City, State, ZIP Code)
930 Boardwalk, Suite H San Marcos, CA 92078
CIP No.
18-11
DATE:
1/27/2020
THE FOLLOWING STATEMENT SHOWS THE NUMBER OF WORKING DAYS CHARGED TO YOUR CONTRACT
FOR THE WEEK ENDING: 1/25/2020
DATE
DAY
WEATHER CONDITION
WORKABLE
DAYS
UNWORKABLE
DAYS
NOTES/
REASON FOR UNWORKABLE DAYS
1/19/2020
Sunday
Weekend
1/20/2020
Monday
Cloudy
1
Working
1/21/2020
Tuesday
Rain
1
Working
1/22/2020
Wednesday
Sunny
1
Working
1/23/2020
Thursday
Sunny
1
Working
1/24/2020
Friday
Sunny
1
Working
1/25/2020
Saturday
Weekend
DAYS THIS WEEK
DAYS PREVIOUSLY REPORTED
TOTAL DAYS TO DATE
3
2
50
31
53
33
CURRENT STATUS
WORKING DAYS SPECIFIED IN CONTRACT
100
APPROVED EXTENSION OF TIME
0
TOTAL AUTHORIZED TIME OF CONTRACT 100
LESS WORKABLE DAYS CHARGED
53
WORKING DAYS REMAINING
47
NOTE: ROUND ALL TIME TO THE
NEAREST 1/2 DAY.
SUMMARY OF WEEK'S ACTIVITIES
Contractor excavating for basin keyways, processing creek slopes and basin.
Project Engineer
NOTE:
The contractor will be allowed 10 days from the date of this report in which to protest in writing the correctness of this statement, otherwise it shall be
deemed to have been accepted as correct.
t. CALIFORNIA t-
Z2VCORPORATEp
WEEKLY STATEMENT OF WORKING DAYS
PROJECT NAME
Paradise Creek Water Quality and Community Enhancements
CONTRACTOR
Dick Miller, Inc.
ADDRESS (Street, City, State, ZIP Code)
930 Boardwalk, Suite H San Marcos, CA 92078
CIP No.
18-11
DATE
2/3/2020
THE FOLLOWING STATEMENT SHOWS THE NUMBER OF WORKING DAYS CHARGED TO YOUR CONTRACT
FOR THE WEEK ENDING: 2/1/2020
DATE
DAY
WEATHER CONDITION
WORKABLE
DAYS
UNWORKABLE
DAYS
NOTES/
REASON FOR UNWORKABLE DAYS
1/26/2020
Sunday
Weekend
1/27/2020
Monday
Sunny
1
Working
1/28/2020
Tuesday
Sunny
1
Working
1/29/2020
Wednesday
Sunny
1
Working
1/30/2020
Thursday
Sunny
1
Working
1/31/2020
Friday
Sunny
1
Working
2/1/2020
Saturday
Weekend
DAYS THIS WEEK
DAYS PREVIOUSLY REPORTED
TOTAL DAYS TO DATE
5
0
53
33
58
33
CURRENT STATUS
WORKING DAYS SPECIFIED IN CONTRACT
100
APPROVED EXTENSION OF TIME
0
TOTAL AUTHORIZED TIME OF CONTRACT
100
LESS WORKABLE DAYS CHARGED
58
WORKING DAYS REMAINING
42
NOTE: ROUND ALL TIME TO THE
NEAREST 1/2 DAY.
SUMMARY OF WEEK'S ACTIVITIES
Contractor raking and cleaning debris from slopes, excavating creek for pyramat, excavating for rip -rap and hydroseed..
Project Engineer
ga(
NOTE:
The contractor will be allowed 10 days from the date of this report in which to protest in writing the correctness of this statement, otherwise it shall be
deemed to have been accepted as correct.
-t-- CALIFORNIA
C- INCORPORATED =�
WEEKLY STATEMENT OF WORKING DAYS
PROJECT NAME
Paradise Creek Water Quality and Community Enhancements
CONTRACTOR
Dick Miller, Inc.
ADDRESS (Street, City, State, ZIP Code)
930 Boardwalk, Suite H San Marcos, CA 92078
CIP No.
18-11
DATE:
2/10/2020
THE FOLLOWING STATEMENT SHOWS THE NUMBER OF WORKING DAYS CHARGED TO YOUR CONTRACT
FOR THE WEEK ENDING:
2/8/2020
DATE
DAY
WEATHER CONDITION
WORKABLE
DAYS
UNWORKABLE
DAYS
NOTES/
REASON FOR UNWORKABLE DAYS
2/2/2020
Sunday
Weekend
2/3/2020
Monday
Sunny
1
Working
2/4/2020
Tuesday
Sunny
1
Working
2/5/2020
Wednesday
Sunny
1
Working
2/6/2020
Thursday
Sunny
1
Working
2/7/2020
Friday
Sunny
1
Working
2/8/2020
Saturday
Weekend
DAYS THIS WEEK
DAYS PREVIOUSLY REPORTED
TOTAL DAYS TO DATE
5
0
58
33
63
33
CURRENT STATUS
WORKING DAYS SPECIFIED IN CONTRACT
100
APPROVED EXTENSION OF TIME
0
TOTAL AUTHORIZED TIME OF CONTRACT
100
LESS WORKABLE DAYS CHARGED
63
WORKING DAYS REMAINING
37
NOTE: ROUND ALL TIME TO THE
NEAREST 1/2 DAY.
SUMMARY OF WEEKS ACTIVITIES
Contracotr placing pyramat, irrigation mainline and rip rap in front of and behind weir wall in creek.
Project Engineer
c.5fear 9,a(
NOTE:
The contractor will be allowed 10 days from the date of this report in which to protest in writing the correctness of this statement, otherwise it shall be
deemed to have been accepted as correct.
DICK MILLER INC.
CITY OF NATIONAL CITY - PARADISE CREEK WATER QUAUTY COMMUNITY ENHANCEMENTS PROJECT
ID
BID Task Name Duration Stan Finsh Cut Predecessors
ITEM
4th Omni" I16Oanw Imo tame!
1
2
Notice To Proceed 0 days Mon 9/16/19 Mon 9/16/19 $0.00
Submittals 10 days Tue 9/24/19 Mon 10/7/19 $000 1E54 days
geggoi Submittals
--_.
3
1 Mobilization 1 day Tue 10/8/19 Tue 10/8/19 $90,000.00 2
M8bifutl0F8
4
11 SWPPP Implement 2 days To 10/8/19 Wed 10/9/19 $0.00 355
a SWPPPImplement
SWPPP Maintenance
S
6
7
8
9
31 SWPPP Maintenance 138 days Thu 10/10/19 Mon 4/20/20 $14, 500.00 4
2 Traffic Control 138 days Thu10/10/19 Mon 4/20/20$19,500.00 4
Site Survey Staking 5 days Tue 10/8/19 Mon 10/14/15$0.00 355
13 Subsurface Utility Locating and Potholing 5 days Tue 10/8/19 Mon 10/14/1S$2,500.00 355
Rough Tue Mon 12/2/19 $62,100.00 355
*. 1 Site Survey Staking
:E, Subsurface Utility Locating and Potholing
1 Rough Grade
F Traffic Control
10
11
10 Grade 40 days 10/8/19
9 SlopeImprovement 15 days Tue 10/15/19 Mon 11/4/19 provemen ys$0.00 8
's
Slope Improvement
Ilse Grade Fill Slope
12
13
9 Fine Grade Fill Slope 10 days Tue 10/15/19 Mon 10/28/1550.00 105S
12 Creek Diversion Plan 10 days Tue 10/29/19 Mon 11/11/1S$16,551.01 11
14 Above- Grade and Surface Utility Relocatl3 days Tue 10/29/19 Thu 10/31/19 $1,500.00 1255
^".; I ---Creek Diversion Plan
L.1;.1 Above- Grade and Surface Utility Relocation
14
1S
16
Rain Events 14 days Mon 11/18/19 T1w 12/5/19 $0.00
12 Dewatering/Rain Damage Cleanup 5 days Thu 11/21/19 Wed 11/27/15$0.00 12E5+7 days
9 Slope Improvement 6 days Thu 11/28/19 Thu 12/5/19 $0.00 15
p,_...,.,,�„�..n......1
I u Dewatering/Rain Damage Cleanup
i. /, Slope Improvement
17
Rain Events 18 days Fri 12/6/19 Tue 12/31/19 $0.00 16
Is�.�.= ks
18
19
20
21
22
23
24
25
26
27
28
29
12 Dewatering/Rain Damage Cleanup 5 days Fri 12/6/19 Thu 12/12/19 $0.00 16
9 Slope Improvement 16 days Fri 12/13/19 Fri 1/3/20 $0.00 18SSe5 days
9 Fine Grade Fill Slope 15 days Mon 1/6/20 Fri 1/24/20 $0.00 19
19 6' PVC Trench/ Install 5 days Mon 1/27/20 Fri 1/31/20 $26,900.00 20
18 8" PVC Trench/ Install 10 days Mon 2/3/20 Fri 2/14/20 $64,000 00 21
Install Fabric & Riprap on Retention and F10 days Mon 1/27/20 Fri 2/7/20 $0.00 20
6 1/2 Ton Riprap 5 days Mon 1/27/20 Fri 1/31/20 514,000.00 20
7 '02 Backing Rip Rap Install 10 days Mon 2/3/20 Fri 2/14/20 $19,600.00 24
21 Prep for Pyromat 5 days Mon 2/17/20 Fri 2/21/20 $0.00 25
21 High Performance Turf Install 5 days Mon 2/17/20 Fri 2/21/20 $43,750.00 26
3 Sheet, Shoring and Bracing 10 days Mon 2/24/20 Fri 3/6/20 545,000.00 27
15 RCP Install 5 days Mon 2/24/20 Fri 2/28/20 S0.00 27
3 1
--{ i.. Slope Improvement
j F.. Fine Grade Fill Slope
1, 6' PVC Trench/ Install
y 1 8" PVC Trench/ Install
y I Install Fabric & Riprap on Retention and Paradise Creek Slope
1 1„ 1/2 Ton Riprap
`I 1_,62 Backing Rip Rap Install
.„ Prep for Pyromat
144 p1High Performance Turf Install
'.. Sheet Shoring and Bracing
i t.
30
8 Concrete Headwall Install 5 days Mon 3/2/20 Fri 3/6/20 $12,000.00 29
1 Concrete Headwall Install j
31
32
4 Diversion Weir Wall 5 days Mon 3/2/20 Fri 3/6/20 $14,20000 29
5 Gabwn Berm 4 days Mon 3/9/20 Thu 3/12/20 $18,500 00 31
` Diversion Wen Wall
`Gabson Berm
33
Biobasin Install 18 days Mon 2/24/20 Wed 3/18/20 $440,020.00 27
/
1
34
3S
36
37
38
39
4023
41
42
10 Biobasin Floor Install 5 days Mon 2/24/20 Fri 2/28/20 $385,020.00 27
Meandering Swale Install 5 days Mon 3/2/20 Fri 3/6/20 $0.00 34
20 Biofiltration Media Section Detail B days Mon 3/9/20 Wed 3/18/20 $55,000.00 35
17 Emergency Overflow Spillway Install 10 days Fri 3/13/20 Thu 3/26/20 $19,000.00 32
23 Irrigation 8 days Thu 3/19/20 Mon 3/30/20 $20,000.00 36
23 Landscaping 8 days Tue 3/31/20 Thu4/9/20 $27,000.00 38
....................
Planting Bdays Tue 3/31/20 Thu4/9/20 $20,1700.00 38
22 Install Water Quality Interpretative Si 2 days Fri 4 SO 20 Mon $1,5(10.00 39
Y pre g^ Y / /4/13/20
1.03 Final Grade/Clean-up 5 days Tue 4/14/20 Mon 4/20/20 50.00 41
I k., Biobasin
'l F., Menndering
"j
I.
Floor Install
Swale Install
1, Biofiltration Media Section Detail
1 Emergency Overflow Spillway Install
1 1 Irrigation
j 1,, Landscaping
i" I Planting
I - }, Install Water Quality Interpretative Sign
I" 1 Final Grade/ Clean-up
43
44
45
46
Project Closeout 12 days Tue 4/21/20 Wed 5/6/20 $0.00 42
Punchl st 10 days Tue 4/21/20 Mon 5/4/20 50.00 42
1.04 Demobilization 2 days Tue 5/5/20 Wed 5/6/20 $0.00 44
24 landscape Maintenance Period 261 days Fri 4/10/20 Fri 4/9/21 $18,000.0047 40
......... $0.00
F^-1
k:. ;Punchlist
i Demobilization
1
Project DMI 19020 Nations Cit
Tau 11111111111111111111111111C Sumnuy f-1 Man„,.. MJesmrc Duration -only ROMPREVEIIIIWIR Stan -my 1 bawd lbaar • mantel Peyyee
Date:Wed 1/15/20
Hs. Frolea Sum 1----1 kuriw snmmay 1 '"- 1 Manual Summary adkp sminEmemoom fuie,aiy 1 0seie •
-
Maestcne • Mann! Task Manual Task Manual Summary Enwnd Tale Ropes
Page 1
CONTRACT TRANSMITTAL FORM
(Attach as Cover Sheet to Documents dropped off to City Clerk's Office)
Date:
From (Dept.):
r7
Submitted by (First & Last Name): TV / "t`?
Vendor:
—9/4. /////e v
Resolution: YES / NO
O
Resolution No. (if applicable):
\o
1 Z 3 0 4
0
(hc( °role aVani
Originals Provided to City Clerk (Select Quantity)
pDepartment has Copy / Duplicate Original
IM.Vendor has Copy / Duplicate Original