HomeMy WebLinkAbout2022 CON Project Professionals Corp. - Camacho Recreation Center HVAC Replacement Project CIP No. 20-07 Change Order No. 3PP,cJJECT Pq# vcE'1-,/ o AL` CE F ter+ PATIO h4
CHANGE ORDER MEMORANDUM
May 24, 2022
To: Roberto Vano, P.E.
Director of Engineering & Public Works/City Engineer
Engineering and Public Works Department
City of National City
From: Josh Johnson
Senior Project Manager
Project Professionals Corp
Project: Cacho Recreation Center HVAC Replacement-Project-
CIP No.: 20-07
Subject: Change Order No.
Change Order No. 3 provides for:
The removal of the additional asphalt roofing uncovered after removal of PVC roofing for framing. Proceed per
RFI #4 and details provided by the Structural engineer to frame equipment pads on the top side of the
sheathing anchors and install equipment curbs to the structural components. The addition of crickets to
the top of edge of the platforms to flow water runoff around the new platforms is also included. The roofing is to
be replaced with additional insulation board to areas where asphalt roofing was removed to bring elevations
within compliance to remove ponding. The removal of an existing abandoned pad near 5-5.
Supporting ing Information:
During demolition of the existing TPO roof asphalt roofing was uncovered and needed t.o be removed to get to the
structural framing. After removing the existing sleepers and sheeting to install the 4x8 members for the perimeter
of the new HVAC curbs it was found that there was existing sheetrock attached to the 2x4 rafters. Installing the 4x8
members would penetrate the sheetrock and possibly create issues with fireproofing. To avoid this the structural
engineer revised the drawings to have the additional members fit with the existing scenario. Additional demolition
was needed to remove an existing pad/curb that was no longer needed with the new equipment layout that was
not accounted for in the plans.
Time Adjustment:
rent:
Two (2) additional working days are to be added to the Contract as the additional work affected the critical path of
the approved schedule.
CostAdjustment:
Cost was determined by force account analysis for a total of $121221.23.
osh Johnson, PPC 6/10/22
Date
CALIFORNIA
N ANIMAL Cflry
•;, + I e
t1WCoItPoR AT"
CAMACHO RECREATION CENTER HVAC REPLACEMENT PROJECT
CHANGE ORDER NO.
CIP NO. 20-07 May 24, 2022
Contractor: Southwest Construction Services Inc.
11653 Riverside Drive, Ste, 153
Lakeside, CA 92040
This Change Order modifies Contractor's and the City's obligations and rights under the
abovementioned contract. This change order is not effective until approved by the City.
Time adjustment
Two (2) additional working days are to be added to the Contract as the additional work did affect the
critical path of the approved schedule.
Cost of Change Order:
The City and the Contractor agree that the Contractor shall proceed with the removal of the additional
asphalt roofing uncovered after removal of PVC roofing. Proceed per RFI #4 and details provided by the
Structural engineer to frame equipment pads on the top side of the sheathing anchors and install
equipment curbs to the structural components, The addition of crickets to the top of edge of the
platforms to flow water runoff around the new platforms is also included. The roofing is to be replaced
with additional insulation board to areas where asphalt roofing was removed to bring elevations within
compliance to remove ponding. An existing abandoned pad near 5-5 shall also be removed. The total
amount for all labor, material, equipment and ail other associated work is 1 , 2L23.
Recommended by Project Manager: osh Johnson, PPC
Date: 6/10/22
By signing this Change Order the Contracto confirms that he/she is completely familiar with and has fairly
negotiated its price, terms and conditions. If this Change Order is approved, Contractor will provide all of the
equipment, materials and labor necessary to provide a complete work as described above at that the price
stated herein. Contractor confirms that the price is fair and complete and represents all costs associated with
the work, including but not limited to all equipment, materials, labor, supervision, overhead, fees, bonds,
insurance, profit, etc. and that there will be no further compensation. Ail of the terms and conditions of the
original contract documents are incorporated herein. The signer for the Contractor •confirms that he/she is
authorized to bind the Contractor to this Change Order,
Agreed and Accepted by Con _tor;
(Print darns and Title s-- e
Approved by City Engineer:
Approved by City Manager:
(Required for change orders $25,000 and above)
1
CALIFORNIA RNIA -
NAL
a gJe
r ORPORA MD
CAMACHO RECREATION CENTER HVAC REPLACEMENT
CI P NO. 20-07
DATE: May 24, 2022
CHANGE ORDER NO. 3
WORK PERFORMED BY: FrarneCo Construction ACCI Roofing Services / SWCS, I nc.
DESCRIPTION OF WORK: R/lR of various roof areas for equipment
ACCOUNTING FOR TIME, MATERIAL'S, AND EQUIPMENT
LABOR
Unit
1)
Additional Labor
Qty
Wage
Total
91.22
Sub -Total Labor:
Labor Markup (.0 )
SU BCONTRACTOR
1)
2)
3)
F ra rn eCo Construction
ACCI Roofing
ACCI Roofing
Unit
LS
LS
LS
Qty
1.00
456.10
456.10
91.22
TOTAL LABOR:
Rate
1.00
1.00
4,5 3.00
4,042.00
2,3 1.00
Total
4,583.00
4,042.00
2,321.00
547.32
Sub -total Subcontractor: 10,946.00
Prime Contractor Markup W5%): $ 547.30
TOTAL SU B O NTRACTO R:
SUB TOTAL:
$ 11,493.30
12,040.62
Bond (1. 5%) 180.61
GRAND TOTAL:
12,221.23