HomeMy WebLinkAbout2023 CON Project Professionals Corp - Paradise Creek Educational Park Extension CIP No. 19-33 Change Order No. 4!PROJECT PRUFE iO °_LS CORPORATION CHANGE ORDER MEMORANDUM February 23, 2023 To: Roberto Yano Director of Engineering & Public Works/City Engineer Engineering and Public Works Department City of National City From: Josh Johnson Project Manager Project Professionals Corporation Project: Paradise Creek Educational Park Extension D PJ 1o; 1933 Subject: Change Order No. 4 Change Order No. 4 provides for: The additional cost of demolition and removal of unforeseen concrete and wire mesh identified in the irrigation lateral trench crossing 18th Street. Demolition includes the pumping out of ground water and removal and disposal of the concrete and wire rnesh. Payment for this change order will be force account. Lipporting Information: While trenching for the irrigation laterals across 18th Street at approximate station +13,00, the Contractor identified concrete containing wire mesh, per RFI #18, beneath the asphalt as well as groundwater within the trench. The Contractor was directed to pump out the groundwater, demo the existing concrete road and dispose of the concrete and wire mesh. Time Adjustment: No additional working days are being provided for this change in the scope of work as it did not affect the critical path of the approved schedule. Cost Adjustment: This change order includes the additional cost to pump out groundwater and demolish and dispose of the existing concrete and wire mesh beneath the asphalt. The additional cost for this change in the scope of work has been agreed upon at a lump sum price of $1,691.52. The cost for this change of work was determined by force account. The pay method and amount have been reviewed by the Project Manager and are considered fair and reasonable. The supporting documentation is on file with the project records. 0 / 3/23 ectMara'r Date CALIFORNIA". ��,TItiP11A triro rip OR Al w) PARADISE CREEK EDUCATIONAL PARK EXTENSION CHANGE ORDER NO. 4 CIP NO. 133 February g, 2023 Contractor: Tri-Group Construction and Development. 9580 Black Mountain Rd. Ste, L San Diego, CA 92126 This Change Order modifies Contractor's and the City's obligations and rights under the abovementioned contract. This change order is not effective until approved by the City. Time diusent: Zero (0) additional working days are to be added to the Contract as the additional work did not affect the critical path of the approved schedule. Cost of Chace Order: The City and the Contractor agreed that the Contractor proceeded under force account with pumping groundwater out of the irrigation lateral trench near station 2+13.00 crossing 18th street, and dernolftion and d sposa he unforeseen -cone r te- i th- wire_rnesh identified -at-approximately t below the finished surface. The additional work included but is not limited to pumping water out of the trench, demo of the concrete and wire mesh, and disposal of the concrete with wire mesh, The total amount for all labor, material, equipment and all other associated work is 1,691.52. Recommended by Project Manager: Date: 02/23i23 By signing this Change Order the Con actor con ms that he/she is completely familiar with and has fairly negotiated its price, terms and conditions. If this ange Order is approved, Contractor will provide all of the equipment, materials and labor necessary to provide a complete work as described above at that the price stated herein. Contractor confirms that the price is fair and complete and represents all costs associated with the work, including but not limited to all equipment, materials, labor, supervision, overhead, fees, bonds, Insurance, profit, etc. and that there will be no further compensation. All of the terms and conditions of the original contract documents are Incorporated herein, The signer for the Contractor confirms that he/she is authorized to bind the Contractor to this Change Order. Agreed and Accepted by Contractor.. (Print Name and Title) s / Date: 2 . 2 2• Z 3 Approved by City Engineer: Date: ao /5, Approved by City Manager: (Required for change Orden $25,000 and above) Cate: CALIFORNIA NNflOPLC1 = zSCe3Cc3 -il �� �ORP08ATEn PARADISE CREEK EDUCATIONAL PARK EXTENSION CIP NO. 19-33 DATE: October 24, 2022 CHANGE ORDER NO. 4 WORK PERFORMED BY: Tri-Group Construction & Development DESCRIPTION OF WORK: Wire Mesh, Concrete, and Groundwater Presence ACCOUNTING FOR TIME, MATERIALS, AND EQUIPMENT LABOR Unit 1) Operating En= ii :Nr. Laborer (G4) 3) Labor Apprentice HR HR HR 2.00 2.00 1.00 Wage 82.58 62.49 43.46 Total 165.16 124.98 43.46 MISCELLANEOUS Disposal Fee Sub -Total Labor: Labor Burden Surcharge (30. 6 ) Labor Markup (20%): Unit 333.60 103. 8 87.38 TOTAL LABOR: 524.26 Rate Total 2) 1Jjk Driver HR EQUIPMENT 1) Work Truck Unit HR • . 00 4 25. 00-S 28.00 Sub -Total Equipment: Equipment Markup (15%): ()Ay 2.00 (30 56.00 625.00 93.75 TOTAL EQUIPMENT: Rate 39.41 718.75 Total 78.82 Mini Excavator HR 2.00 25.14 $ 4) 3- xle Dump Truck HR 2. 00 84.40 50.28 .63.0 Sub-1 tai Equipment: Equipment Markup (15%): 375.44 56.3_ TOTAL EQUIPMENT: 431.76 SUBTOTAL: 1, 674.77 1 BOND: 16.75 GRAND TOTAL: 1,691.52