HomeMy WebLinkAbout2023 CON Project Professionals Corp - Paradise Creek Educational Park Extension CIP No. 19-33 Change Order No. 2CHANGE ORDER MEMORANDUM October 21, 2022 To: Roberto ano Director of Engineering Public Works/City Engineer Engineering and Public Works Department City of National City From: Josh Johnson Project Manager Project Professionals Corp Project: Paradise Creek Educational Park Extension CIP No.: 19-33 Subject: Change Order No. Change Order No. 2 provides for: Transporting and delivering decomposed granite from the old walking path to a city yard in lieu of stockpiling the decomposed granite as per the original plans. Payment for this change order will be as determined by lump sum agreement. .uortinp rr�fornotion: The plans called for the Contractor to remove the existing decomposed granite path and install pavers. As per the plans, the decomposed granite was to be stockpiled on site. The Contractor suggested loading and stockpiling the OG offsite with the City instead of stockpiling on site. The Contractor agreed to deliver and transport the existing decomposed granite to the offsite location as directed by the City at an agreed upon lump sum price. Time Adjustment: No additional working days are being provided for this change in the scope of work as it did not affect the critical path of the approved schedule. Cost Adjustment: The additional cost for this change in the scope of work has been agreed upon at a lump sum price of $985.20. The cost for this change of work accounts for all labor, equipment, materials and all other work associated with this change order. The pay method and amount have been reviewed by the Project Manager and are considered fair and reasonable. The supporting documentation is on file with the project records. Project Manager Josh Johnson, PPC 1/5/23 Date CALIFORNIA —.4 NATIONAL CI +NeDReonATso PARADISE CREEK EDUCATIONAL PARK EXTENSION CHANGE ORDER NO. CIP NO. 19-33 October 21, 2022 Contractor: Tri-Group Construction and Development. 9580 Black Mountain Rd. Ste. L San Diego, CA 21 This Change Order modifies Contractor's and the City's obligations and rights under the abovementioned contract. This change order is not effective until approved by. the City. Time adjustment: Zero (0) additional working days are to be added to the Contract as the additional work did not affect the critical path of the approved schedule. Cost of Change Order: The City and the Contractor agree that the Contractor shall proceed with transporting and delivering the decomposed granite from the old walking path to a City yard in lieu of stockpiling the decomposed granite as per the original plans. The total amount for all labor, material, equipment and all other associated work is $985.20. Recommended by Project Manager: Josh Johnson, PPC Date: 1/5/23 By signing this Change Order the Contract confirms that he/she is completely familiar with and has fairly negotiated its price, terms and conditions. If this Change Order is approved, Contractor will provide all of the equipment, materials and labor necessary to provide a complete work as described above at that the price stated herein. Contractor confirms that the price is fair and complete and represents all costs associated with the work, including but not limited to all equipment, materials, labor, supervision, overhead, fees, bonds, insurance, profit, etc. and that there will be no further compensation. All of the terms and conditions of the original contract documents are incorporated herein. The signer for the Contractor confirms that he/she is authorized to bind the Contractor to this Change Order. Agreed and Accepted by Contractor: ‘ i (Print Name anTitle} ' ` + Date. 12/2211 z.... Approved by It Engineer:fq-p-13 Date: r Approved by City Manager: (Required far change orders 25,000 and above) Date: '��' d 31►f 43 CALIFORNIA NATIONAL env aoiol tr x cORpoR AT PARADISE CREEK EDUCATIONAL PARK EXTENSION CI P NO. 19-33 DATE: September '7, 2022 CHANGE ORDER NO, WORK PERFORMED BY: Tri-GroupConstruction & Development DESCRIPTION OF WORK: Haul -off existing removed DG and deliver to the City in lieu of stockpiling ACCOUNTING FOR TIME, MATERIALS, AND EQUIPMENT LABOR 1) Truck Driver MATERIALS 3-Axle Dump Truck Unit Unit Unit -I R Qty 8.00 Wage 36,74 Sub -Total Labor: Labor Markup (20%): Qty Rate Sub -Total Materials: Materials Markup (15%): 8.00 Ff I 293.92 $ 293.92 58.78 TOTAL LABOR: Total I s TOTAL MATERIALS: Rate 67.69 Total 541.52 Sub -Total Equipment: Equipment Markup (15%): TOTAL EQUIP ENT: 541.52 81.23 SUBTOTAL: 1 BOND: GRAND TOTAL: 352.70 622.75 i 975.45 9.75 985.20