CHANGE ORDER MEMORANDUM
June 16, 2023
To: Roberto Yano, PE
Director of Engineering 84 PublicWorks/City Engineer
Engineering and Public Works Department
City of National City
From: Randy Garcia
Construction Manager
Project Professionals Corporation
Project: Police Department Parking Structure Waterproofing
CIP No.. 22-42
Subject: Change Order No. 1
Chanae Order No. 1 provides for:
The removal and replacement of existing waterproofing and joint sealant around the north gate storage room
sidewalk.
Payment for this change order will be as agreed upon at a lump sum price.
Supporting orting information:
Following a rain event on May 4`r'`, Salvador Gil of the National City Police Department identified a leak issue under
the north gate storage room. After discussingwith the Contractor, it was determined that the existing grade of the
sidewalk surrounding the facility sloped inwards towards the building causing the water to drain into and under
the facility. Additionally, the existingwaterproofing displayed several cracks and signs of deterioration.. The joint
sealant surrounding the facility was also cracked and easily stripped away from the building. The Contractor
recommended removing the existing waterproofing, installing polycoat polyprime as a thin set material to direct
water away from the facility and then installing pedestrian traffic waterproofing.
Time Adjustment:
Zero (0) working days are to be added to the Contract.
Cost djcrstment:
The additional cost for this change has been agreed upon at a lump sum price of , 00.00.
The pay method and amount have been reviewed by the Project Manager and are considered fair and reasonable. The
supporting documentation is on file with the project records.
Randy Garcia 6/26/23
Project Manager Date
=CALIFORNIA
NALTIONAL CITY
an4r)
INCORPORATED. )
Police Department Parking Structure Waterproofing CHANGE ORDER NO. 1
CIP NO. 22-42
Contractor: Harbor Coating and Restoration, Inc.
625 W Katella Avenue, Suite 5
Orange, CA 92867
June 16, 2023
This Change Order modifies Contractor's and the City's obligations and rights under the abovernentioned
contract. This change order is not effective until approved by the City.
Time adjustment:
Zero (0) working days are to be added to the Contract.
Cost of Change Order:
TheCity and theContractor agree that theContractor shall proceed with removing and replacing the
existing waterproofing along the north gate storage room sidewalk. The scope of this additional work
includes removal and replacement of existing waterproofing, installing poiycoat po►lyprime as a thin set
material to drain water away from the facility, and removal and replacement of joint sealant along
vertical joints. The total amount for all labor, material, equipment, and all other associated work is
$64O0.00.
Recommended by Project Manager: Randy
Garcia
Date: 6/26/23
By signing this Change Order
negotiated its price, terms and
equipment, materials and labor
stated herein. Contractor confirms
the work, including but not limited
insurance, profit, etc. and that
original contract documents are
authorized to bind the Contractor
the
conditions.
there
Contractor
necessary
that
to
will
incorporated
to this
confirms that he/she is completely familiar with and has fairly
if this Change Order is approved, Contractor will provide all of the
to provide a complete work as described above at that the price
the price is fair and complete and represents all costs associated with
all equipment, rnaterials, labor, supervision, overhead, fees, bonds,
be no further compensation. All of the terms and conditions of the
herein. The signer for the Contractor confirms that hefshe is
Change Order.
Agreed and Accepted by Contractor:
(I ri not Name and Title} r����o�� � - ,� ,
Date:
/ 3/ 0
Approved by Project Coordinator:
Date:- i
Approved by Assistant Director of E & PW:
Date: 41 11 (artr
Al(Approvedby CityEngineer:1Date:f'L/3
_
anager:
Approved by City Manager:
(Required for change orders $25,000 and above)
Date: 1
CALIFORNIA
NATIONAL
le
nor
a ig
INCORPORArfrD
POLICE DEPARTMENT PARKING STRUCTURE WATERPROOFING
CIP NO. 22-42
DATE: May 24, 2023
WORK PERFORMED BY: Harbor Coating and Restoration
CHANGE ORDER NO. 1
DESCRIPTION OF WORK: Remove and replace existing waterproofing along storage room sidewalk at north gate
ACCOU NTING FOR TIME, MATERIALS, AN D EQUIPMENT
LABOR
Laborer(G1)
Laborer (G1)
Laborer (G1)
MATERIALS
2)
4)
Poly rime F M B
Poly coat PC-260 - Grey
PWG Silica Sand
Base coat and top coat
Unit
HR
HR
HR
Unit
EA
EA
EA
LS
aty
16.00
16.00
0
17.00
Wage
64.04
64,04
64.04
Sub -Total Labor:
Labor Markup (20):
Qty
1.00
2.00
10.00
1.00
Total
1,024.64
1,024.64
1,088.68
$ 3,137.96
627.59
TOTAL LABOR: 3, 800. 0
Rate
305.28
265.9-
11.77
1,306.01
Sub -Total Materials:
Materials Markup (15%):
Total
305.28
531.88
117.70
1,306.01
$ 2,260.87
339413
TOTAL MATERIALS:
SUB TOTAL:
GRAND TOTAL:
2,600.00
I
6,400.00