HomeMy WebLinkAbout2023 CON Project Professionals Corporation - Paradise Creek Educational Park Extension CIP No. 19-33 Change Order No. 14J �1 PROJECT PROFESSIONALS CORPORATION CHANGE ORDER MEMORANDUM March 30, 2023 To: Roberto Vano Director of Engineering & Public Works/City Engineer Engineering and Public Works Department City of National City From: Josh Johnson Project Manager Project Professionals Corporation Project: Paradise Creek Educational Park Extension SIP No: 19-33 Subject: Change Order No. 14 r f r� Y. 1 Change Order No. 14 provides for: Surface mounting the bike racks by "ARTS" to the pavers as per the revised detail E on sheet L1,2. Payment for this change order will be as agreed upon at a lump sum price. Supporting information.. on.• As described in change orders #6 and , the installation of the bike racks needed to be changed due to the hike racks requiring surface mounting. The original plans included bike racks being installed in a shallow footing beneath the paver surface. However, after discovering that the bike racks were surface mounted, Neri Landscape Architecture directed the Contractor to surface mount the bike racks using tamper -resistant anchor bolts as shown on detail E on sheet L1,2 on November 11, 2022. Section 30-,1 of the contract special provisions states that payment for "Bike Rack By 'ARTS' Center" shall include full compensation for the coordination and installation of the ARTS bike racks. As the installation type, details, foundation, and bike racks were all changed by the designer from the originally bid line item "Bike Rack — By 'ARTS' Center" the Contractor agreed to a lump sum price for the coordination and surface mounted installation of the bike racks. Time Adjustment: Zero (0) additional working days are to be added to the Contract. Cost Adjustment: The additional cost for this change in the scope of work has been agreed upon at a lump sum price of 4,4 9.09. The cost for this change in the work accounts for all labor, equipment, materials and all other work associated with this change order. I The pay method and amount have been reviewed by the Project Manager and are considered fair and reasonable. The supporting documentation is on file with the project records. 7/25/23 Date CALI FO F,■ t :.�+r NATIONAL lavy PARADISE CREEK EDUCATIONAL PARK EXTENSION CHANGE ORDER NO. 14 C1P NO. 19-33 March 30, 2023 Contractor: Tri-Group Construction and Development. 9580 Black Mountain Rd. Ste. L San Diego, CA 92126 This Change Order modifies Contractor's and the Cit s obligations and rights under the abovernentioned contract. This change order is not effective until approved by the City. Time adjustment: Zero (0) additional working days are to be added to the Contract. Cost of Change Order: The City and the Contractor agree that the Contractor shall proceed with surface mounting the bike racks by "ARTS" to the pavers as per the revised detail E on sheet L1.2 using tamper -resistant anchor bolts. The additional work includes but is not limited to sourcing anchor bolts, coordinating bike rack selection with the City, loading and transporting bike racks from city yard, drilling andsurface mounting the bikeracks, and repairing damaged pavers during drilling. The total amount for all labor, material, equipment and all other associated work is 4,439.09. . f Recommended by Project Manager: Date: 7/25123 By signing this Change Order the Co • ractor co rms that he/she Is completely familiar with and has fairly negotiated its price, terms and conditions. If thi Change Order is approved, Contractor will provide all of the equipment, materials and labor necessary to p vide a complete work as described above at that the price stated herein. Contractor confirms that the price is fair and complete and represents all costs associated with the work, including but not limited to all equipment, materials, labor, supervision, overhead, fees, bonds, insurance, profit, etc. and that there will be no further compensation. All of the terms and conditions of the original contract documents are incorporated herein. The signer for the Contractor confirms that he/she is authorized to bind the Contractor to this Change Order. Agreed and Accepted by Contractor: (Print Name and Title) Approved by Project Coordinator: Approved by Assistant Director of E & PW: Approved by City Engineer: Approved by City Manager: (Required for change orders $25,000 and above) 14( �-o►.� � Ads; V+l' Date: 7 f /i/ Date: 8 14111-3 Dais: INa3 Date: g/ Date: -P-w CALIFORNIA NATIO NAL rATCORPORATZ9 PARADISE CREEK EDUCATIONAL PARK EXTENSION CIP NO. 19-33 1) 4) DATE: March 22, 2023 WORK PERFORMED BY: Tri-Group Construction & 'Development CHANGE ORDER NO. 14 DESCRIPTION OF WORK: Surface Mount Bicycle Racks ACCOUNTING FOR TIME, MATERIALS, AND EQUIPMENT Laborer Laborer Laborer Apprentice Administration Unit HR HR MATERIALS 3/8" 6" Ultra-6 13TN Anchor Bolts Shipping Fee EQU IPMENT 1) Work Truck Work Truck HR HR Unit EA LS Unit HR HR Qty 10.00 10.00 8.00 16.00 'Wage 86.25 86.25 $ 56.92 43.21 Sub -Total Labor: Labor Markup (20%): Qty 40.00 1.00 Rate 6.99 52.58 Sub -Total Materials: Materials Markup (15%): Qty 5.00 5.00 Total 862.50 862.50 455.36 691.36 2187132 574.34 TOTAL LABOR: Total 279.60 52.58 3,446.06 332.18 49.83 TOTAL MATERIALS: Rate 49.31 49.31 Sub -Total Equipment: Equipment Markup (15%): TOTAL EQU I PM ENT: Total 246.55 246.55 493.10 73.97 SUBTOTAL: 1 BOND: 382.01 567.07 GRAND TOTAL: