HomeMy WebLinkAbout2023 CON Project Professionals Corporation - Paradise Creek Educational Park Extension CIP No. 19-33 Change Order No. 12r ••
■
01,
PROJECT PROFESSIONALS CORPORATION
CHANGE ORDER MEMORANDUM
March 30, 2023
To, Roberto Yano
Director of Engineering & Public Works/City Engineer
Engineering and Public Works Department
City of National City
From: Josh Johnson
Project Manager
Project Professionals Corporation
Project: Paradise Creek Educational Park Extension
CIP No.: 19-33
u bJ ect: Change Order No. 12
Change Order. No. 12 provides for:
Removal and disposal of 3/8" Mojave Gold Gravel and planting of 240 1-gallon Salicornia Pacifica in native soil.
Payment for this change order will be as agreed upon at a lump sum price.
Supporting Information:
As per change order #9, the Contractor installed 3/8" Mojave Gold Gravel in ail planter areas. After being informed
of excess gravel Neri Landscape Architecture directed the Contractor to place the excess gravel along the newly
installed paver areas on the southerly portion of the project site. During the punch walk, the Contractor was
directed by theCity to remove the gravel and replant the native plant species in the locations identified south of
the project site to help preserve the wetlands.
`uirne Ad/Lrs trter7t:
Zero (0) additional working days are to be added to the Contract.
•
Cost Adjustment:
The additional cost for this change in the scope of work has been agreed upon at a lump sum price of 7,500.00.
The cost for this change in the work accounts for all labor, equipment, materials and all other work associated with
this change order.
The pay method and amount have been reviewed by the Project Manager and are considered fair and reasonable. The
supporting documentation is on file with the project records.
7/25/23
Pr ct Man ag " Date
CALIFORNIA
NATI: NAL
PARADISE CREEK EDUCATIONAL PARK EXTENSION CHANGE ORDER NO.
CIP NO. 19-33
Contractor: Tri-Group Construction and Development.
9580 Black Mountain Rd. Ste. L
San Diego, CA 92126
March 30, 2023
This Change Order modifies Contractor's and the City's obligations and rights under the abovementioned
contract. This change order is not effective until approved by the City.
Time adustent:
Zero (0) additional working days are to be added to the Contract.
Cost of Chaim a Order:
The City and the Contractor agree that the Contractor shall proceed with removing the 3/8" Mojave
Gold Gravel placed at the southerly end of the project site and restoring the native vegetation in the
same area.. The additional work includes but is not limited to removal and disposal of the 3/8" Mojave
Gold Gravel and planting of 240 1-gallon Salicornia Pacifica on native soil. The total amount for all
labor, material, equipment and all other associated work is $7,500.00.
Recommended by Project Manager:
Approved
by Assistant Director of E & PW:
-
Approved
by City Engineer: Otiegti
Approved
(Required for
by City Manager:
change orders $25,000 and above)
Date:
-)-= CALIFORNIA
NATI NAL Clint
mav
nvcoRPoRATV)
PARADISE CREEK EDUCATIONAL PARK EXTENSION
CIP NO. 1 - 3
DATE: March 22, 2023
CHANGE ORDER NO. 12
BREAKDOWN FROM CONTRACTOR
WORK RK PERFORMED BY: Tri-Group Construction & Development
DESCRI PTION OF WORK: Remove gravel and install native plant species
ACCOUNTING FOR TIME, MATERIALS, AND EQUIPMENT
14/1 LaborerApprentice
Operator
Driver
MATERIALS
1-Gal SaCicornia Pacifica
EQUIPMENT
Work Truck
Skid Steer
Mini Excavator
S uper Ten
Unit
EA
12.00 I $ 10$.15
6.00 36.68
Sub -Total Labor:
Labor Markup ("10):
city
240.00
Rate
5.50
Sub -Total Materials:
1,324A8
1,297.80
20.0E
3,753.08
372.32
TOTAL LABOR:
Total
$ 1,30.00
$ 1,3 0.00
TOTAL MATERIALS:
Sub -Total Equipment:
788,96
465.24
294,00
506.40
2,054. 60
TOTAL EQUIPMENT:
SU BTOTAL:
4,125.40
1s320.00
2,054.E+0
GRAND TOTAL:
$ 7,500.00
7,500 00