HomeMy WebLinkAbout2023 CON Project Professionals Corporation - Paradise Creek Educational Park Extension CIP No. 19-33 Change Order No. 11PPCJECT PgO=ES ICE CHANGE ORDER MEMORANDUM April 14, 2023 To. Roberto Yano Director of Engineering & Public Works/City Engineer Engineering and Public works Department City of National +City► From: Josh Johnson Senior Project Manager Project Professionals Corp Project: Paradise Creek Educational Park Extension l P o.: 19-33 Subject: Change Order No. 11 Change Order No. 11 provides for: Removal and replacement of the irrigation controller and pedestal. Payment for this change order was under force account. Supporting Information On January 4, 2022, while attempting to connect the new irrigation wiring to the existing irrigation controller as per plan, the Contractor identified issues with the existing irrigation controller as per RFI #27. The irrigation controller was reporting a "fuse" fault, corroded circuit board, had disconnected wires, a damaged rain sensor and sat upon a corroded pedestal The Contractor was directed to remove and replace the irrigation controller and pedestal with an as -equal product and to only connect the new irrigation lines as per plan. Time Adjustment: No additional working days are being provided for this change in the scope of work as it did not affect the critical path of the approved schedule. Cost Adjustment: The additional cost for this change in the scope of work has been agreed upon by force account for a total of , 7 .5 . The pay method and amount have been reviewed by the Project Manager and are considered fair and reasonable. The supporting documentation is on file with the project records. 7/25/23 Date CIP NO. 19-33 Contractor: Tri-Group Construction and Development. 9580 Black Mountain Rd. Ste. L San Diego, CA 92126 i'°" CALIFORNIA %ATi3OM:L l ✓ ,,, anti !Nen It PO It fif*MCI PARADISE CREEK EDUCATIONAL PARK EXTENSION CHANGE ORDER NO. 11 April 14, 2023 This Change Order modifies Contractor's and the City's obligations and rights under the abovementioned contract. This change order is not effective until approved by the City. Time adiustment: Zero (0) additional working days are to be added to the Contract. cost of C hange Order: The City and the Contractor agreed that the Contractor proceeded under force account with removal and disposal of the existing irrigation controller and pedestal and installing a new irrigation controller and pedestal. The additional work included but was not limited toremoving, hauling and disposing of the existing irrigation controller, raising the foundation of the irrigation controller, placing a stub -out conduit for a future rain meter, and installing a new irrigation controller inside of a stainless -steel pedestal and cabinet. The total amount for all labor, material, equipment and all other associated work is 6,573.56. 1 Recommended by Project Manager: Date: 7/25/23 By signing this Change Order the Cont ctor confi s that he/she is completely familiar with and has fairly negotiated its price, terms and conditions. If this gange Order is approved, Contractor will provide all of the equipment, materials and labor necessary to provide a complete work as described above at that the price stated herein, Contractor confirms that the price is fair and complete and represents all costs associated with the work, including but not limited to all equipment, materials, labor, supervision, overhead, fees, bonds, insurance, profit, etc, and that there will be no further compensation. All of the terms and conditions of the original contract documents are incorporated herein. The signer for the Contractor confirms that he/she Is authorized to bind the Contrador to this Change Order. Agreed and Accepted by Contractor: (Print Name and Title) Approved by Project Coordinator: Approved by Assistant Director of E & PW: ass vi' r - Approved by City Engineer: Approved by City Manager: (Required for change orders $ZS,000and above) utftet52-2 Date: C 7/1 [23 Date: g Date: -tN-it CALIFORNIA NATIONAL Car amv .rco°aoa.Tao PARADISE CREEK EDUCATIONAL PARK EXTENSION CHANGE ORDER NO. 11 CP'NO. 19-33 DATE: April13, 2023 WORK PERFORMED BY: Tri-Group Construction & Development DESCRIPTION OF WORK: Rioe and replace irrigation controller ACCOUNTING FOR TIME, MATERIALS, AND EQUIPMENT LABOR 1) LaborerJourneyman 2) La borer Journey ma n 3) Laborer Apprentice P5 Unit HR FIR Qty 8.0 8.00 8.00 Wage 59.81 59.81 55.48 Sub --Total Labor: Labor Surcharge (30.99%): Labor Markup (20%): Total $ 478.48 478.48 443,84 1,400.80 434.11 366.98 TOTAL L 3 O R: 21201489 MATERIALS 1) I rrlg a Lion Controller EQUIPMENT Work Truck Unit Qty Rate Total LS 1.00 3,376 11 Sub -Total Materials: Materials Markup (15%): Qty 8.00 $ 3,376.11 3,376.11 TOTAL MATERIALS: Rate 49.31 Sub -Total Equipment: Equipment Markup (15%): TOTAL EQUIPMENT: Total 394.48 394.48 29.58 SU BTOTAL: 1% BOND: RAN[ TOTAL: 882.53 6,573.56